Long Island Power Authority v. FERC

27 F.4th 705
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 4, 2022
Docket20-1033
StatusPublished
Cited by18 cases

This text of 27 F.4th 705 (Long Island Power Authority v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long Island Power Authority v. FERC, 27 F.4th 705 (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued May 13, 2021 Decided March 4, 2022

No. 20-1033

LONG ISLAND POWER AUTHORITY AND LONG ISLAND LIGHTING COMPANY, D/B/A LIPA, PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

AMERICAN ELECTRIC POWER SERVICE CORPORATION, ET AL., INTERVENORS

Consolidated with 20-1035, 20-1273

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Michael F. McBride argued the cause for petitioners Long Island Power Authority, et al. Eric J. Konopka argued the cause for petitioner Linden VFT, LLC. On the briefs were Richard P. Bress, David L. Schwartz, and Joseph B. Nelson.

Anand R. Viswanathan, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. 2 With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

John Longstreth argued the cause for respondent- intervenors. With him on the brief were Gary E. Guy, Donald A. Kaplan, Cara J. Lewis, Richard P. Sparling, Bradley R. Miliauskas, Morgan E. Parke, Evan K. Dean, Pauline Foley, Paul M. Flynn, Miles H. Mitchell, Stacey Burbure, Robert Adkins, David Yost, Attorney General, Office of the Attorney General for the State of Ohio, Werner L. Margard, Assistant Attorney General, Steven D. Hughey and Spencer A. Sattler, Assistant Attorneys General, Office of the Attorney General for the State of Michigan, Daniel E. Frank, Allison E. Speaker, Kriss E. Brown, Aspassia V. Staevska, Christian A. McDewell, Gurbir S. Grewal, Attorney General, Office of the Attorney General for the State of New Jersey, Paul Youchak, Deputy Attorney General, Christopher R. Jones, Molly Suda, and Christopher J. Barr. William M. Keyser III, Steven M. Nadel, and Alex Moreau, Deputy Attorney General, Office of the Attorney General for the State of New Jersey, entered appearances.

Before: HENDERSON, KATSAS, and WALKER, Circuit Judges.

Opinion of the Court filed by Circuit Judge KATSAS.

KATSAS, Circuit Judge: This case arises from a long- running dispute over how to allocate the costs of high-voltage facilities to transmit electricity within the mid-Atlantic planning region. The question is difficult because high-voltage projects afford two different kinds of benefits—local benefits that accrue primarily to utilities close to the project at issue, and regional benefits that accrue throughout the grid. The Seventh Circuit has twice set aside cost allocations that ignored 3 the local benefits, Illinois Commerce Comm’n v. FERC, 576 F.3d 470 (7th Cir. 2009) (Illinois Commerce I); Illinois Commerce Comm’n v. FERC, 756 F.3d 556 (7th Cir. 2014) (Illinois Commerce II), and we have set aside cost allocations that ignored the regional benefits, Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254 (D.C. Cir. 2018).

This case involves a contested settlement covering high- voltage projects approved between 2007 and 2013. The settlement allocates their costs through hybrid formulas that account for both local and regional benefits. In that respect, it tracks the allocation formula for high-voltage projects approved after 2013, which is not challenged here.

The Federal Energy Regulatory Commission approved the settlement over the objection of two utilities that transmit electricity from the mid-Atlantic region to New York. These utilities argue that the approval was inconsistent with the Seventh Circuit’s decisions, with FERC’s own precedent, and with an underlying cost-causation principle. One of the utilities also argues that FERC erroneously assigned it costs based on a flawed interpretation of the settlement. We agree with the second contention but not the first.

I

A

The Federal Power Act requires utilities to charge “just and reasonable” rates for the transmission of electricity in interstate commerce. 16 U.S.C. § 824d(a). To be just and reasonable, rates must “reflect to some degree the costs actually caused by the customer who must pay for them.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) (cleaned up). This “cost causation principle” requires “comparing the costs assessed against a party to the burdens 4 imposed or benefits drawn by that party.” Id. If FERC determines that a particular rate is unjust or unreasonable, it must “determine the just and reasonable rate.” 16 U.S.C. § 824e(a).

B

PJM Interconnection, LLC is the regional transmission organization (RTO) for an area encompassing much of the mid- Atlantic and part of the Midwest. PJM takes its name from Pennsylvania, New Jersey, and Maryland, the first three states in which it operated, but its territory now extends as far west as Illinois. As an RTO, PJM coordinates the movement of electricity across the region. It operates transmission facilities owned by member utilities, approves the construction of new facilities, and files tariffs allocating among its members the costs of the facilities.

This case involves high-voltage transmission facilities within the PJM region. For over a decade, member utilities disputed how to allocate the cost of these projects, which provide both local and regional benefits. The facilities most obviously benefit nearby utilities that use them directly, but they also provide “backbone infrastructure” that improves reliability and reduces congestion regionwide. PJM Interconnection, L.L.C., 119 FERC ¶ 61,063, P 80 (2007) (Opinion No. 494). A geographic asymmetry exacerbated the dispute: Given the location of generators, electricity must flow longer distances to reach consumers in the eastern part of PJM than to reach their western counterparts. And because high- voltage facilities work best to transmit electricity over long distances, they are more useful in the eastern part. See Ill. Com. II, 756 F.3d at 558; Ill. Com. I, 576 F.3d at 475.

Initially, PJM allocated the cost of its high-voltage facilities based on what FERC calls the violation method (or, 5 less concisely, the violation-based distribution-factor method). This method assumes that new projects are approved in response to violations of reliability standards at overburdened facilities. And it allocates costs based on use of those facilities at the time of each violation. The violation method thus deems utilities using overburdened facilities to have “cause[d]” the relevant problem and to “benefit from” upgrades that eliminate it. See Opinion No. 494, 119 FERC ¶ 61,063, P 2 n.3.

In 2007, FERC ordered PJM to replace its violation method with a “postage stamp” method. This method allocates the cost of a new facility in proportion to each utility’s sale of electricity, regardless of where the facility is located or how much each utility uses it. The Commission reasoned that the postage-stamp method accounts for the regional benefits of high-voltage facilities, incentivizes their development, and avoids the trouble of quantifying the specific benefits that each facility provides to each utility. Opinion No. 494, 119 FERC ¶ 61,063, PP 79–82.

In Illinois Commerce I, the Seventh Circuit set aside FERC’s order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
27 F.4th 705, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-island-power-authority-v-ferc-cadc-2022.