Evergy Kansas Central, Inc. v. FERC

77 F.4th 1050
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 1, 2023
Docket22-1221
StatusPublished
Cited by2 cases

This text of 77 F.4th 1050 (Evergy Kansas Central, Inc. v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evergy Kansas Central, Inc. v. FERC, 77 F.4th 1050 (D.C. Cir. 2023).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued April 4, 2023 Decided August 1, 2023

No. 22-1221

EVERGY KANSAS CENTRAL, INC., ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

OKLAHOMA GAS AND ELECTRIC COMPANY, ET AL., INTERVENORS

Consolidated with 22-1252, 22-1291

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

John Lee Shepherd, Jr. argued the cause for petitioners. With him on the briefs were C. Dixon Wallace III and Ted J. Murphy.

Charlotte H. Taylor argued the cause for intervenor in support of petitioners. With her on the brief was James C. Beh. 2 Matthew W.S. Estes, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

Matthew J. Binette argued the cause for respondent- intervenor American Electric Power Service Corporation, et al. With him on the brief were Christopher R. Jones, Miles H. Kiger, Heather H. Starnes, Ashley M. Bond, Elizabeth P. Trinkle, Craig W. Silverstein, Phyllis G. Kimmel, and F. Alvin Taylor.

Before: WILKINS and WALKER, Circuit Judges, and SENTELLE, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge WALKER.

WALKER, Circuit Judge: The Federal Energy Regulatory Commission must ensure that the rules for funding new transmission facilities are just and reasonable. A funding regime is not just and reasonable if it makes one party foot the bill for a project with broad benefits. Old Dominion Electric Cooperative v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018).

Here, two transmission owners and a utility company say FERC approved an unjust and unreasonable change to the transmission-funding regime in a region managed by Southwest Power Pool. The new regime, the Petitioners say, will likely force transmission owners to pay for projects that benefit the entire power grid. So they petitioned for judicial review.

But the Petitioners oversell the risk that the new regime will foist the costs of new projects on individual owners. For that to happen, the regime’s primary mechanisms for allocating 3 costs would have to fail. In any case, FERC may balance the need to ensure that transmission owners bear perfectly proportional costs and benefits with other policy goals. Consolidated Edison Co. v. FERC, 45 F.4th 265, 286 (D.C. Cir. 2022). It did that here by approving a regime that allows participants in regional transmission zones to collaborate on selecting and funding new projects.

We thus deny the petitions for judicial review.

I

A

The transmission grid takes electricity from power plants to end users. Regional Transmission Organizations help manage the grid by coordinating the “planning, operation, and use” of electricity transmission within a given area. South Carolina Public Service Authority v. FERC, 762 F.3d 41, 50 (D.C. Cir. 2014). Among other things, RTOs set the rules for “transmission planning and operation,” including planning and funding new transmission facilities. Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1364 (D.C. Cir. 2004) (cleaned up); see also Order No. 1000, 136 FERC ¶ 61,051 (2011).

But RTOs do not have a free hand setting the rules. Instead, FERC reviews RTOs’ rules (called “rates”) to ensure that they are “just and reasonable.” 16 U.S.C. § 824d(a). A rate is not just and reasonable if it violates the cost-causation principle, which mandates that “the rates charged for electricity should reflect the costs of providing it.” Old Dominion Electric Cooperative v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018). 4 B

Here, transmission owners and a utility company in a region managed by an RTO called Southwest Power Pool say its funding rules violate the cost-causation principle.

Southwest’s region covers seventeen states in the center of the country. Its territory is divided into zones, ten of which have multiple transmission owners. For years, Southwest applied the same cost-allocation rules in those ten zones with multiple transmission owners.

Under those rules, each transmission owner could unilaterally decide to build new transmission facilities. The costs would then be paid by zone customers (companies using the transmission grid) in proportion to how much they used the grid. But that let transmission owners thrust the costs of new facilities onto customers, regardless of how much the customers benefited.

To give customers more say, Southwest proposed a new way to fund transmission projects in its region. Its proposal works like this. The largest customer in a zone selects a transmission owner as the Facilitating Transmission Owner for that zone. With input from other owners and customers, the Facilitating Transmission Owner proposes Zonal Planning Criteria — selecting new transmission facilities to build and choosing how to fund them. The criteria are then put to a two- step vote. • Step 1: The zone’s customers vote, with each customer’s vote weighted according to its use of the transmission facilities in the zone. To pass step one, the criteria must be approved by a percentage of votes greater than or equal to the 5 largest customer’s load plus one half of the zone’s remaining load. • Step 2: All the zone’s transmission customers and transmission owners vote on the criteria, with each receiving one vote. A simple majority is enough to pass step two.

Southwest’s proposal also puts in place three backup plans. • Backup Plan A: If the proposed Zonal Planning Criteria do not get enough votes under the two- step voting process, the last approved Zonal Planning Criteria apply. If there are no approved Zonal Planning Criteria, Backup Plan B applies. • Backup Plan B: Southwest’s Regional Planning Criteria apply. • Backup Plan C: At any time, any transmission owner in the zone can create its own Local Planning Criteria, regardless of the Zonal or Regional Planning Criteria in place. That lets the owner build any facility it likes, even though the project does not satisfy the Zonal or Regional Planning Criteria, but it must foot the bill itself.

To put its proposal into action, Southwest first had to prove to FERC that its new funding regime was “just and reasonable.” 16 U.S.C. § 824d(a). Several members of the region objected, including petitioners Evergy and GridLiance, and intervenor Oklahoma Gas and Electric Company (we’ll refer to these three parties as the “Petitioners”).

The Petitioners claimed that Southwest’s plan violated the cost-causation principle, which generally prohibits FERC from 6 “singl[ing] out a party for the full cost of a project, or even most of it, when the benefits of the project are diffuse.” Old Dominion Electric Cooperative v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018) (cleaned up). The Petitioners claimed that Backup Plan C runs afoul of that rule because it can force one transmission owner to pay for a new facility with widespread benefits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
77 F.4th 1050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evergy-kansas-central-inc-v-ferc-cadc-2023.