United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Decided February 24, 2022

No. 22-1011

IN RE: NTE CONNECTICUT, LLC, PETITIONER

ISO NEW ENGLAND INC., INTERVENOR

On Petition for an Emergency Stay Pursuant to the All Writs Act

David W. DeBruin, Suedeen G. Kelly, and Zachary B. Cohen were on the petition and the reply.

Matthew R. Christiansen, General Counsel, Federal Energy Regulatory Commission, Robert H. Solomon, Solicitor, Beth G. Pacella, Deputy Solicitor, and Matthew W.S. Estes, Attorney, were on the response to the petition.

Before: WILKINS, RAO and JACKSON, Circuit Judges.

Opinion for the Court filed by Circuit Judge RAO.

Dissenting opinion filed by Circuit Judge WILKINS.

RAO, Circuit Judge: Petitioner NTE Connecticut, LLC (“NTE”) acquired valuable authorization to sell electricity 2 from its new power plant. The Federal Energy Regulatory Commission (“FERC”) revoked that authorization and, in so doing, very likely fell short of its obligation under the Administrative Procedure Act (“APA”) to explain the reason for its decision. See Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983). Absent emergency relief from this court, FERC’s order would have irreparably harmed NTE, preventing it from participating in a February 7, 2022, auction to sell future electricity capacity to New England consumers. On February 4, 2022, we granted NTE’s petition for an emergency stay of FERC’s order, with an opinion to follow. This is that opinion.

I.

A.

For the past seven years, NTE has been working to build a new natural gas fueled power plant in Killingly, Connecticut. In order to sell electricity on the New England grid, NTE had to work with ISO New England Inc. (“ISO-NE”) to have the project “qualified.” ISO-NE is the independent system operator authorized by FERC to manage the regional grid. ISO-NE oversees annual “forward capacity auctions” at which the owners of generation facilities bid for the right to sell electricity on the grid in the future. See NextEra Energy Res., LLC v. FERC, 898 F.3d 14, 17 (D.C. Cir. 2018) (describing this process). The right to provide “capacity” (i.e., the ability to produce electricity), in the quantity and at the price fixed at auction, is called a facility’s “capacity supply obligation” (“CSO”). The CSO is tied to a one-year “capacity commitment period” that begins three years after the auction. In concrete terms, a generation facility awarded a CSO at the 2022 auction gains the right to sell electricity for one year beginning June 1, 3 2025. A facility with a CSO is automatically “qualified” to participate in future ISO-NE auctions.

After locating a suitable parcel of land, designing the facility, and preparing a timeline for the project’s financing and construction, NTE applied to have the Killingly plant “qualified.” ISO-NE approved the application, and in the 2019 auction NTE secured a CSO for the 2022 commitment period. Under ISO-NE’s rules at the time, a newly qualified facility was permitted to “lock in” the terms of its initial CSO for six subsequent capacity commitment periods (i.e., for seven years total). See ISO New England Inc., 173 FERC ¶ 61,198 at PP 2– 4 (2020). NTE exercised this option, giving it a guaranteed income stream for the first seven years of the Killingly plant’s operation, which in turn made it more attractive to potential investors. NTE thereafter participated in the 2020 and 2021 auctions, securing contract rights to supply electricity for the 2023 and 2024 commitment periods.

Initially, NTE had planned for the Killingly facility to come online in early 2022. But soon after securing its first CSO in 2019, NTE encountered a series of setbacks that prevented it from meeting its financing and construction goals. First, just after the 2019 auction, incumbent energy generators in New England asked FERC to review ISO-NE’s qualification of the Killingly plant, placing NTE’s CSO in jeopardy. FERC eventually upheld NTE’s rights, but the results of the 2019 auction did not become final until September 2019. Second, while the incumbent competitors’ challenge was pending before FERC, several environmental groups sued in state court to block the Connecticut Siting Council’s decision to approve the Killingly plant. One of them, a nonprofit called Not Another Power Plant, appealed the case to the Connecticut Supreme Court, which did not issue a decision in NTE’s favor until September 2021—some thirty-one months after the 2019 4 auction. See Not Another Power Plant v. Conn. Siting Council, 265 A.3d 900 (Conn. 2021). In the interim, NTE had located a potential investor for the Killingly plant. But because the project’s viability depended on a favorable legal ruling, NTE was unable to finalize financing while the case was under review. Third, the arrival of the COVID-19 pandemic in early 2020 caused further complications. Disruptions to supply chains and labor markets required NTE and its potential investor to frequently recalculate the project’s shifting costs, while pandemic related delays slowed NTE’s ability to secure necessary construction permits. Because of these obstacles, NTE was repeatedly forced to revise its timeline for the Killingly plant’s construction.

If the Killingly plant was not operational by May 31, 2024, ISO-NE had the right to request that FERC terminate NTE’s existing CSO, disqualifying it from participating in future auctions. ISO-NE Tariff § III.13.3.4A.1 By September 2021, ISO-NE was concerned that NTE was running out of time to meet that deadline. As revised, NTE’s timetable required it to finalize equity financing for the Killingly plant in mid-January 2022, to finalize debt financing in early March 2022, and to begin commercial operation of the plant on May 31, 2024. NTE also planned to issue full notices to proceed to its contractors by January 1, 2022, before financing was finalized.

ISO-NE hired a consultant to assess whether these plans were feasible. After reviewing NTE’s timeline and conferring with the parties, the consultant concluded that if NTE issued full notices to proceed by January 1, 2022, “commercial 1 “[I]f, as a result of milestone date revisions, the date by which a resource will have achieved [operations] is more than two years after the beginning of the Capacity Commitment Period for which the resource first received a [CSO],” ISO-NE may request that FERC terminate the resource’s CSO. ISO-NE Tariff § III.13.3.4A. 5 operation of [the Killingly plant] could occur on or about the stated proposed commercial operation date of May 31, 2024.” Issuing full notices on January 1, 2022, would give NTE twenty-nine months to build the Killingly facility—“an aggressive, but achievable schedule for a project of this scope.” However, according to the consultant, full notices to proceed typically cannot be issued before financing is secured. NTE’s “assumption” that it would be able to issue full notices by January 1, 2022, was therefore “unlikely.” Under a more “realistic scenario,” the consultant concluded, NTE would be able to issue full notices only after securing financing in mid- January, resulting in a “likely commercial operation date” beyond the deadline of May 31, 2024.

On November 4, 2021, shortly after receiving the consultant’s report, ISO-NE met with NTE to review its plans for the Killingly plant. At the meeting, NTE told ISO-NE that it remained confident it could complete construction on time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Gas and Electric Company v. FERC
113 F.4th 943 (D.C. Circuit, 2024)
United States v. Facebook, Inc.
District of Columbia, 2023
Evergy Kansas Central, Inc. v. FERC
77 F.4th 1050 (D.C. Circuit, 2023)
Cboe Futures Exchange, LLC v. SEC
77 F.4th 971 (D.C. Circuit, 2023)
Restaurant Law Center v. LABR
66 F.4th 593 (Fifth Circuit, 2023)
In re: National Nurses United
47 F.4th 746 (D.C. Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
26 F.4th 980, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-nte-connecticut-llc-cadc-2022.