Maine v. Federal Energy Regulatory Commission

854 F.3d 9, 2017 WL 1364988, 2017 U.S. App. LEXIS 6406
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 14, 2017
Docket15-1118 Consolidated with 15-1119, 15-1121
StatusPublished
Cited by39 cases

This text of 854 F.3d 9 (Maine v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maine v. Federal Energy Regulatory Commission, 854 F.3d 9, 2017 WL 1364988, 2017 U.S. App. LEXIS 6406 (D.C. Cir. 2017).

Opinion

SENTELLE, Senior Circuit Judge:

Under the Federal Power Act (“FPA”), the Federal Energy Regulatory Commission (“FERC” or “the Commission”) must ensure that all rates charged for the transmission or sale of electric energy are “just and reasonable.” 16 U.S.C. §§ 824d(a), 824e(a). Petitioners New England Transmission Owners (“Transmission Owners”) provide transmission services for customers in New England. In 2011, Petitioners Massachusetts and various consumer-side stakeholders (“Customers”) filed a complaint under section 206 of the FPA, 16 U.S.C. § 824e, alleging that Transmission Owners’ base return on equity (“ROE”) had become unjust and unreasonable. FERC’s orders in that section 206 proceeding are the subjects of the petitions for review in this case.

After creating a new zone of reasonableness and identifying a specific base ROE it found to be just and reasonable, FERC held that Transmission Owners’ existing ROE — which was within the newly determined zone of reasonableness but did not equal FERC’s new ROE — was unlawful. FERC explained that by setting a new just and reasonable ROE, it necessarily found that Transmission Owners’ existing ROE was unjust and unreasonable, thus satisfying its burdens under section 206.

In setting Transmission Owners’ new ROE, FERC deviated from its traditional use of the midpoint of the zone of reasonableness, citing the presence of anomalous capital market conditions and concluding that a mechanical application of the midpoint would not result in a just and reasonable rate in this case. After considering additional record evidence, FERC placed the ROE at the midpoint of the upper half of the newly determined zone of reasonableness.

*16 FERC then informed Transmission Owners that their total ROE — base ROE plus any incentive adders — was now capped at the upper end of the newly determined zone of reasonableness. Rather than change Transmission Owners’ previously approved incentive adders, FERC explained that its decision merely applied the Commission’s well-established policy that a utility’s total ROE must remain within the zone of reasonableness.

Both Transmission Owners and Customers filed petitions for review challenging whether FERC satisfied the statutory requirements under section 206 in setting a new ROE. Transmission Owners argue that FERC’s orders must be vacated because it failed to find that the existing ROE was unjust and unreasonable before setting a new ROE. Customers contend that FERC arbitrarily placed the new ROE at the midpoint of the upper half of the zone of reasonableness. Because FERC failed to articulate a satisfactory explanation for its orders, we grant the petitions for review.

I.

ISO New England Tariff

Transmission Owners are a group of privately owned utilities that provide transmission services in New England. In 2004, Transmission Owners and ISO New England, Inc. established ISO New England as a regional transmission organization. See Conn. Dep’t of Pub. Util. Control v. FERC, 593 F.3d 30, 32 (D.C. Cir. 2010). Transmission Owners recover their transmission revenue requirements through formula rates included in ISO New England, Inc.’s open access transmission tariff (“ISO New England Tariff’). To calculate the total cost for each Transmission Owner to provide transmission service from its facilities, the ISO New England Tariff uses formula rates, which are based on the aggregated cost of all the transmission assets of each Transmission Owner. The revenue requirements for Transmission Owners are calculated using the same single base ROE. Each Transmission Owner’s costs are calculated under the formula, summed, and then divided by the aggregate demand in New England to produce the regional transmission rates under the ISO New England Tariff. This is known as “rolled-in” ratemaking. See, e.g., Otter Tail Power Co., 12 FERC ¶ 61,169 at 61,420 (1980).

Section 205 Proceedings Before the Commission

Pursuant to section 205 of the FPA, 16 U.S.C. § 824d, Transmission Owners submitted a proposal in 2003 to establish ISO New England as a regional transmission organization. Transmission Owners also submitted “a related section 205 filing seeking approval for the ROE component recoverable under the regional and local transmission rates charged by ISO New England.” Bangor Hydro-Elec. Co., 117 FERC ¶ 61,129 at P 5 (2006), order on reh’g, 122 FERC ¶ 61,265 (2008), order granting clarification, 124 FERC ¶ 61,136 (2008), aff'd sub nom. Conn. Dep’t of Pub. Util. Control v. FERC, 593 F.3d 30 (D.C. Cir. 2010). In 2006, FERC established the base ROE for Transmission Owners at 11.14 percent. In establishing the base ROE, FERC relied on a zone of reasonableness, determined in a discounted cash flow analysis, of 7.3 percent to 13.1 percent.

FERC also approved a number of ROE incentive adders applicable to Transmission Owners. Citing section 219 of the FPA, 16 U.S.C. § 824s, FERC established “incentive-based rate treatments to further encourage the construction of transmission facilities and replacement of aging transmission infrastructure.” S. Cal. Edison Co. v. FERC, 717 F.3d 177, 179 (D.C. Cir. *17 2013) (citing Promoting Transmission Inv. Through Pricing Reform, 116 FERC ¶ 61,057 (2006), order on reh’g, 117 FERC ¶ 61,345 (2006), order on reh’g, 119 FERC ¶ 61,062 (2007)). Ail rates approved under section 219 must meet the FPA’s just-and-reasonable standard. 16 U.S.C. § 824s(d). In Transmission Owners’ section 205 proceeding, FERC approved a 100-basis-point adder for certain transmission projects, which we affirmed. See Conn. Dep’t of Pub. Util., 593 F.3d at 33-37. Most of Transmission Owners’ incentives were approved in separate proceedings. See, e.g., Ne. Utils. Serv. Co., 125 FERC ¶ 61,183 (2008), reh’g denied, 135 FERC. ¶ 61,270 (2011); Cent. Me. Power Co., 125 FERC ¶ 61,079 (2008), reh’g denied, 135 FERC ¶ 61,136 (2011).

Section 206 Proceedings Before the Commission

This case concerns FERC’s determination of Customers’ section 206 challenge to Transmission Owners’ base ROE set in the section 205 proceedings. See Coakley v. Bangor Hydro-Elec. Co., 144 FERC ¶ 63,-012 (2013) (“ALJ Decision”), aff'd in part, rev’d in part, Opinion No. 531, 147 FERC ¶ 61,234 (2014) (“Opinion No. 531”), order on paper hearing, Opinion No. 531-A, 149 FERC ¶ 61,032 (2014) (“Opinion No. 531-A”),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green Development, LLC v. FERC
77 F.4th 997 (D.C. Circuit, 2023)
Citadel FNGE Ltd. v. FERC
77 F.4th 842 (D.C. Circuit, 2023)
Advanced Energy United, Inc. v. FERC
82 F.4th 1095 (D.C. Circuit, 2023)
Murphy v. Madden
S.D. California, 2023
In re: LA Pub Svc Comm
58 F.4th 191 (Fifth Circuit, 2023)
American Clean Power Assoc v. FERC
54 F.4th 722 (D.C. Circuit, 2022)
Constellation Mystic Power v. FERC
45 F.4th 1028 (D.C. Circuit, 2022)
MISO Transmission Owners v. FERC
45 F.4th 248 (D.C. Circuit, 2022)
Wabash Valley Power Association, Inc. v. FERC
45 F.4th 115 (D.C. Circuit, 2022)
Xcel Energy Services Inc. v. FERC
41 F.4th 548 (D.C. Circuit, 2022)
Sierra Club v. FERC
38 F.4th 220 (D.C. Circuit, 2022)
Belmont Municipal Light Department v. FERC
38 F.4th 173 (D.C. Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
854 F.3d 9, 2017 WL 1364988, 2017 U.S. App. LEXIS 6406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maine-v-federal-energy-regulatory-commission-cadc-2017.