Citadel FNGE Ltd. v. FERC

77 F.4th 842
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 21, 2023
Docket22-1090
StatusPublished
Cited by2 cases

This text of 77 F.4th 842 (Citadel FNGE Ltd. v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citadel FNGE Ltd. v. FERC, 77 F.4th 842 (D.C. Cir. 2023).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued April 12, 2023 Decided July 21, 2023

No. 22-1090

CITADEL FNGE LTD., PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

MONITORING ANALYTICS, LLC AND PJM INTERCONNECTION, L.L.C., INTERVENORS

Consolidated with 22-1106

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Brian P. Morrissey argued the cause for petitioner. With him on the briefs were Carter G. Phillips, Kenneth W. Irvin, and Peter A. Bruland.

Matthew J. Glover, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on 2 the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. Susanna Y. Chu, Attorney, entered an appearance.

Paul M. Flynn argued the cause for intervenors in support of respondent. With him on the brief were Jeffrey W. Mayes, Ryan J. Collins, and Elizabeth P. Trinkle.

Before: SRINIVASAN, Chief Judge, MILLETT, and WALKER, Circuit Judges.

Opinion for the Court filed by Circuit Judge MILLETT.

Dissenting opinion filed by Circuit Judge WALKER.

MILLETT, Circuit Judge: This case concerns how PJM, the manager of a large, multi-state electrical grid, prices the flow of electricity to utilities in times of congestion. Such congestion arises when energy is scarce in a particular location on the grid due to, for example, extreme weather conditions or a fire at a transmission station. That scarcity causes the dispatch of more expensive generation and can trigger the Transmission Constraint Penalty Factor (“Penalty Factor”) when such alternative generation is unavailable. The Penalty Factor imposes an upper bound on the costs PJM will incur to control a transmission constraint, and it is designed to send transparent price signals to the market and incentivize investment that will resolve the congestion and prevent it from recurring.

In early 2022, PJM temporarily removed one of three electric transmission lines that served consumers in Virginia’s Northern Neck peninsula as part of planned upgrades. Because the Northern Neck lacked additional generation sources to make up for the outage, the other two transmission 3 lines serving the Northern Neck experienced congestion that PJM could not resolve with low-cost generation. As a result, the Penalty Factor frequently set the congestion cost in the Northern Neck.

After PJM filed a complaint with the Federal Energy Regulatory Commission, the Commission found that application of the Penalty Factor to the Northern Neck during the transmission-line outage was unjust and unreasonable under the Federal Power Act and temporarily suspended its application at the Northern Neck for the duration of the transmission line’s outage. 16 U.S.C. § 791a et seq.

Petitioner Citadel FNGE Ltd. is an energy trading firm. It challenges the Commission’s suspension of the Penalty Factor as arbitrary and capricious.

We deny the petitions for review. Substantial evidence supported the Commission’s decision that the Penalty Factor, as applied to the unique Northern Neck circumstances, could not work as designed because it increased costs without incentivizing supply or demand responses. Because application of the Penalty Factor increased costs for consumers without a commensurate benefit, the Commission reasonably found that its application in this context was unjust and unreasonable.

I

A

The Federal Power Act grants the Commission the authority to regulate “the transmission of electric energy * * * and the sale of such energy at wholesale in interstate commerce[.]” 16 U.S.C. § 824(a). Under Section 206 of the 4 Act, the Commission must ensure that any rates charged for energy are “just and reasonable[.]” Id. § 824e(a); see also id. § 824d(a). One way the Commission can enforce that requirement is by initiating enforcement proceedings on its own or in response to a third-party complaint. Id. § 824e(a). If the Commission finds that a rate is “unjust, unreasonable, unduly discriminatory or preferential,” the Commission must overturn that rate and impose a new just and reasonable rate. Id.

B

In many parts of the United States, the electrical generation and transmission system is managed by Regional Transmission Organizations. Regional Transmission Organizations serve several functions, including operating the electrical grid in a defined geographic area, balancing energy supply and demand, establishing markets for the sale and purchase of electricity, and ensuring the reliable transmission of electricity. See Public Citizen, Inc. v. FERC, 7 F.4th 1177, 1186 (D.C. Cir. 2021) (citing FERC, ENERGY PRIMER: A HANDBOOK FOR ENERGY MARKET BASICS, at 61 (April 2020), https://perma.cc/7UN6-6TR8 (“ENERGY PRIMER”)).

PJM Interconnection, L.L.C. (“PJM”) is the Regional Transmission Organization that oversees the electric grid covering thirteen Mid-Atlantic and Midwestern States and the District of Columbia. Power generators—such as natural-gas fired or nuclear power plants and renewable energy resources—produce electricity. Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 659 (D.C. Cir. 2017). Power generators sell electricity at wholesale rates to utilities that then deliver the electricity to consumers. Id. PJM coordinates the 5 dispatch of generation and demand resources by operating markets for the supply and purchase of energy. Id. The markets reflect the availability and need for electricity and set price signals that indicate to market participants the value of the electricity. FERC v. Electric Power Supply Ass’n, 577 U.S. 260, 268 (2016).

PJM operates two energy markets. The first is the day- ahead market, which allows market participants to bid on selling or purchasing electricity that will be dispatched the next day. See ENERGY PRIMER, at 87. The day-ahead market produces the schedule and financial terms of energy production for the day. But various risk factors may alter the actual supply of and demand for electricity—for example, a sudden outage at a power plant. Black Oak Energy, LLC v. FERC, 725 F.3d 230, 233 (D.C. Cir. 2013). To adjust for such changes, PJM operates a second market, known as the real-time market. That market is used to meet immediate demand for electricity by trading electricity at prices quoted for sale and delivery within five-minute intervals based on the then-current grid operating conditions. Id.; see ENERGY PRIMER, at 87–88.

PJM outlines its market rules, rates, and operating procedures in a document called the Open Access Transmission Tariff. Most relevant here, that tariff contains rules that establish the wholesale price of electricity. PJM calculates the wholesale price using a method called locational marginal pricing. See Black Oak Energy, LLC, 725 F.3d at 233–234. Under this method, prices are designed to reflect the lowest cost of meeting an incremental megawatt-hour of demand at each location on the grid. Id. Prices vary based on time and location. Id. The local marginal price is the bottom-line wholesale price at a particular place, which may be 6 the price at which wholesale transactions actually settle or otherwise a component of an average price used for settlement. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
77 F.4th 842, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citadel-fnge-ltd-v-ferc-cadc-2023.