Verso Corp. v. Fed. Energy Regulatory Comm'n
Opinion
Opinion for the Court filed by Circuit Judge WILKINS.
In
Louisiana Public Service Commission v. Federal Energy Regulatory Commission
, this Court affirmed FERC's denial of refunds in a cost-allocation case, upholding its discretion to deny refunds where a flaw in rate design caused the costs to be borne disproportionately among customers.
See
We conclude that the reallocation at issue here does not constitute an impermissible retroactive rate increase. FERC reasonably determined that the prior rate methodology was unjust and unreasonable, and its reliance on certain evidence in reaching this conclusion was appropriate. Having established that the existing rate was unjust and unreasonable, and having determined that a different methodology would comply with cost-causation principles, FERC had authority to order refunds and corresponding surcharges under Section 206 and its broad remedial authority under Section 309. Accordingly, we deny the Petitions for review.
I.
This case involves system support resource ("SSR") costs in the territory of the American Transmission Company ("ATC") under the Midcontinent Independent System Operator, Inc. ("MISO") Tariff. To ensure system stability, MISO requires energy producers in its territory to notify MISO prior to ceasing operation. MISO then evaluates the importance of the would-be retired facility and may require continued operation if necessary for the reliability of energy supply. Such providers are designated SSRs, and they are compensated for the cost of continued operation under SSR agreements with MISO.
For most of the MISO service area, SSR costs have long been shared by customers based on the load served.
Midwest Indep. Transmission Sys. Operator, Inc. Pub. Utils. with Grandfathered Agreements in the Midwest Iso Region
,
For the ATC area, however, the MISO Tariff allocated SSR costs pro rata among all customers.
See
*5
The instant Petitions arise from SSR agreements regarding three facilities in the ATC service area. MISO filed the first SSR agreement using the ATC pro rata allocation in October 2012, for the continued operation of a City of Escanaba, Michigan facility, which FERC accepted.
See
Midwest Indep. Transmission Sys. Operator, Inc.
,
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion for the Court filed by Circuit Judge WILKINS.
In
Louisiana Public Service Commission v. Federal Energy Regulatory Commission
, this Court affirmed FERC's denial of refunds in a cost-allocation case, upholding its discretion to deny refunds where a flaw in rate design caused the costs to be borne disproportionately among customers.
See
We conclude that the reallocation at issue here does not constitute an impermissible retroactive rate increase. FERC reasonably determined that the prior rate methodology was unjust and unreasonable, and its reliance on certain evidence in reaching this conclusion was appropriate. Having established that the existing rate was unjust and unreasonable, and having determined that a different methodology would comply with cost-causation principles, FERC had authority to order refunds and corresponding surcharges under Section 206 and its broad remedial authority under Section 309. Accordingly, we deny the Petitions for review.
I.
This case involves system support resource ("SSR") costs in the territory of the American Transmission Company ("ATC") under the Midcontinent Independent System Operator, Inc. ("MISO") Tariff. To ensure system stability, MISO requires energy producers in its territory to notify MISO prior to ceasing operation. MISO then evaluates the importance of the would-be retired facility and may require continued operation if necessary for the reliability of energy supply. Such providers are designated SSRs, and they are compensated for the cost of continued operation under SSR agreements with MISO.
For most of the MISO service area, SSR costs have long been shared by customers based on the load served.
Midwest Indep. Transmission Sys. Operator, Inc. Pub. Utils. with Grandfathered Agreements in the Midwest Iso Region
,
For the ATC area, however, the MISO Tariff allocated SSR costs pro rata among all customers.
See
*5
The instant Petitions arise from SSR agreements regarding three facilities in the ATC service area. MISO filed the first SSR agreement using the ATC pro rata allocation in October 2012, for the continued operation of a City of Escanaba, Michigan facility, which FERC accepted.
See
Midwest Indep. Transmission Sys. Operator, Inc.
,
On April 3, 2014, two days after FERC accepted the Presque Isle SSR Agreement, the Public Service Commission of Wisconsin ("Wisconsin Commission" or "PSCW") filed a complaint under Section 206 of the Federal Power Act, 16 U.S.C. § 824e, to challenge the allocation of the Presque Isle SSR costs as unjust and unreasonable. The Complaint relied on a study that MISO conducted, at the request of stakeholders, to assess which load-serving entities in the ATC footprint actually benefited from the continued operation of the Presque Isle facility. PSCW Complaint at 3 & n.8, FERC Docket No. EL14-34-000 (Apr. 3, 2014). The preliminary load-shed analysis showed that 42 percent of the benefiting load of the Presque Isle facility was in Wisconsin; however, the MISO Tariff assigned 92 percent of the SSR costs to Wisconsin ratepayers based on the pro rata allocation methodology.
On July 29, 2014, FERC granted the Wisconsin Commission's Complaint.
See
July 29, 2014 Order,
By way of remedy, the July 29, 2014 Order directed MISO to remove the pro rata provision from the Tariff, "thereby extending to the ATC footprint the general SSR cost allocation Tariff language, which requires MISO to allocate SSR costs to 'the LSE(s) which require(s) the operation of the SSR Unit for reliability purposes.' " July 29, 2014 Order,
Within weeks, FERC also addressed the Escanaba and White Pine SSR Agreements that similarly allocated costs on a pro rata basis.
See
Midcontinent Indep. Sys. Operator, Inc.
,
MISO completed a second load-shed study as directed by the July 29, 2014 Order and submitted compliance filings regarding each of the three SSR facilities.
Pub. Serv. Comm'n of Wis.
,
FERC reviewed the compliance filings, among other proceedings, in an order dated February 19, 2015.
See
Pub. Serv. Comm'n of Wis.
,
On September 22, 2016, FERC issued the final order under review in these Petitions.
See
Sept. 22, 2016 Order,
Petitioners-customers "that paid too little" and are now subject to surcharges-challenge FERC's authority to impose surcharges as part of its remedy, contending that it amounts to an impermissible retroactive rate increase. They also contend that FERC's decision was arbitrary and capricious because the difference between the allocation rejected and the allocation ultimately approved was insignificant.
II.
"Under the Federal Power Act, [FERC] must ensure that all rates charged for the transmission or sale of electric energy are 'just and reasonable.' "
Maine v. Fed. Energy Regulatory Comm'n
,
A.
Petitioners challenge FERC's determination that the pro rata methodology for distributing SSR costs was unjust and unreasonable, contending that there was no new evidence or change in circumstances to justify this conclusion, that the results of the final load-shed study undermined FERC's reasoning, and that FERC "fail[ed] to consider the historical basis" for that methodology, such that its orders *8 lacked reasoned decision-making. Pet'rs' Br. 48-55. None of these objections is persuasive.
FERC must undertake a two-step inquiry regarding a Section 206 challenge.
See
Maine
,
Petitioners contend that the preliminary load-shed study is not sufficient to support FERC's conclusion that the existing rate is unreasonable because the study merely confirmed the difference between a load-shed methodology and the pro rata methodology. Pet'rs' Br. 41-45.
Contrary to Petitioners' view, FERC's determination that the pro rata methodology was unjust and unreasonable relied on new information not previously before the Commission. In one sense, the eventuality that two different methodologies would yield different results was reasonably known to the parties and FERC during the initial decision that the pro rata methodology was just and reasonable. But just because some difference between the results of these two methodologies is predictable does not make the information actually collected any less telling.
See
OXY USA, Inc. v. Fed. Energy Regulatory Comm'n
,
We also are unpersuaded by Petitioners' argument that the final load-shed study defeats FERC's conclusion that the pro rata methodology was unjust and unreasonable. Petitioners point out that, according to the second study, the pro rata methodology was off by only about 6 percent with respect to the benefits received by Michigan and Wisconsin respectively. As an initial matter, the load-shed study that FERC actually accepted showed that the
*9
pro rata methodology was an order of magnitude more inaccurate than the second study had revealed: the pro rata methodology was off not by 6 percent, but by 91 percent. In any event, Petitioners' assertion that a 6 percent difference is insufficient to show that the pro rata methodology is unreasonable lacks support.
See
Pet'rs' Br. 46. And Petitioners failed to preserve this point, as they did not argue before the Commission that the final load-shed data undermined a finding that the pro rata methodology was outside of the zone of reasonableness.
See
16 U.S.C. § 825
l
(b). Moreover, since FERC did not rely on a zone-of-reasonableness analysis, this challenge is inapt: a rate may be shown to be unreasonable under Section 206 even without a showing that the rate is entirely outside the zone of reasonableness.
See
Maine
,
Finally, we reject Petitioners' contention that FERC failed to take into account the historical rationale for the ATC carve-out.
See
Pet'rs' Br. 48-53. To the contrary, FERC acknowledged the origins of the pro rata methodology as springing from ATC's cost-sharing philosophy and explained its conclusion that ATC's "original intent" in sharing costs was "not served by the
pro rata
sharing of SSR costs ... because decisions concerning the operational status of ... generation assets are not subject to the ATC transmission planning process." July 29, 2014 Order,
B.
Having concluded that FERC reasonably determined that the pro rata allocation was unjust and unreasonable under Section 206, we turn to Petitioners' challenge relating to remedy.
Petitioners posit that the ordered surcharges effect a retroactive rate increase, violating Section 206 and the filed-rate doctrine. The Commission argues that because "[t]his is a cost allocation case," the limitations surrounding retroactive rate changes do not come into play, and the remedy imposed here was otherwise within FERC's broad power to effectuate the FPA under Section 309. See Resp't's Br. 39-46. Because Section 206 contemplates surcharges in cost-allocation cases, FERC's orders here are within its remedial *10 authority. And because FERC explained valid reasons for departing from its usual policy of denying reallocation, that departure was not arbitrary or capricious.
i.
Section 206 defines FERC's authority when an existing rate is found unjust, unreasonable, unduly discriminatory, or preferential. 16 U.S.C. § 824e. This includes two main tools at FERC's disposal. First, Section 206(a) authorizes FERC to "fix" rates prospectively, after it concludes that a rate is inappropriate upon a complaint by a market participant or on FERC's own impetus.
See
While Section 206's limitations and the filed-rate doctrine thus restrict the remedies that FERC may order, FERC's remedial authority is otherwise expansive. Section 309 of the FPA provides that
The Commission shall have power to perform any and all acts, and to prescribe, issue, make, amend, and rescind such orders, rules, and regulations as it may find necessary or appropriate to carry out the provisions of this chapter.
16 U.S.C. § 825h. Section 309 accordingly permits FERC to advance remedies not expressly provided by the FPA, as long as they are consistent with the Act.
See
TNA Merch. Projects, Inc. v. Fed. Energy Regulatory Comm'n
,
The reallocation of SSR costs, including through surcharges, is well within *11 FERC's remedial authority under Section 309, read in harmony with Section 206 and the filed-rate doctrine. While the surcharges at issue here resulted in some customers paying more for past services than they were charged originally, that cost increase to a subgroup of ratepayers is not a "retroactive rate increase" as such: the aggregate rate remained the same, divided differently among the constituent payers. Although such a reallocation is not expressly contemplated under Section 206, subsection (c) confirms our interpretation by negative implication. Section 206(c) discusses "shifting costs" between utility companies within a registered holding company. The provision bars refunds in circumstances where "refunds ... might otherwise be payable" but where the refund order "is based upon a determination that the amount of such decrease should be paid through an increase in the costs to be paid by other electric utility companies of [the] registered holding company." 16 U.S.C. § 824e(c). This statement that surcharges to pay for refunds are impermissible in specific, limited circumstances contemplates that the converse is true in all other circumstances: surcharges to cover retroactive rate design changes are acceptable when those limited circumstances do not apply. Reading the Section 206(c) exception in conjunction with Section 206(b) and against the backdrop of Section 309, FERC's authority to order refunds thus must be understood to encompass surcharges to pay for ordered refunds where the result is a reallocation of an existing rate. Only that understanding gives meaning to the Section 206(c) carve-out prohibiting surcharge-funded refunds as between multiple utility companies within a single holding company. If FERC could not ordinarily order surcharge-funded refunds, the exception would be superfluous.
Petitioners rely heavily on this Court's decision in
City of Anaheim, California v. Federal Energy Regulatory Commission
to argue that surcharges are unlawful, but that decision is inapt.
See
Petitioners also argue that the Section 309 cases relied upon by FERC in its September 22, 2016 Order are distinguishable as involving error by the Commission. Pet'rs' Br. 38; Pet'rs' Reply Br. 7-8 (citing
TNA
,
*12
creates a reason to use it. The provision itself allows for "any and all acts" "necessary or appropriate" to carry out the FPA's statutory ends, 16 U.S.C. § 825h, not merely to fix mistakes by the Commission.
See
Niagara Mohawk
,
Finally, Petitioners invoke the
Chenery
doctrine. They claim that FERC's reliance on Section 309 in its brief "is an impermissible
post hoc
rationalization of counsel," since "FERC did not rely on FPA Section 309 below," and Intervenors' use of Section 206(c) to inform the interpretation of Section 206(a) and Section 309 similarly "is improper." Pet'rs' Reply Br. 2, 5-6, 11-12.
See
Sec. & Exch. Comm'n v. Chenery Corp.
,
ii.
Having established that FERC has the statutory authority to order a reallocation of SSR costs through refunds and surcharges, we next consider whether FERC acted within its discretion in doing so here. Petitioners argue that FERC previously "acknowledged that it has no authority to order retroactive surcharges," making this action a departure from its ordinary policy.
See
Pet'rs' Br. 36. However, as Petitioners note, FERC consistently has construed its refund authority to be equitable and flexible, with appropriate remedies dictated by the circumstances.
The circumstances here support FERC's decision to order refunds paid for by surcharges. In
Louisiana Public Service Commission v. Federal Energy Regulatory Commission
, a reallocation case like this one, this Court validated FERC's "previously muddled position" that "it has no generally applicable policy of granting refunds" where a rate has been unfairly allocated between multiple constituent payers, but "the utility has received no net over-recovery."
As FERC explained in the September 22, 2016 Order, neither of these circumstances are present here. First, there is no risk of "under-recovery" because "MISO has a record of the SSR costs paid by each LSE ... and [ ] can calculate the exact amount of SSR costs that should be assessed to each LSE that underpaid in order to refund LSEs that overpaid" based on the revised methodology. Sept. 22, 2016 Order,
FERC's rationale for distinguishing the reallocation at issue here is particularly compelling in light of the unique nature of the SSR agreements at issue. Reliability resources are so designated because they are essential to the reliability of the system's energy supply, and SSR agreements are accomplished in short order so as to avoid any gap in coverage. As the Commission explained in its September 22, 2016 Order, SSR agreements "must go into effect quickly to ensure that the resource continues to operate," and without an agreement in place, a designated unit "would otherwise have provided SSR service on an uncompensated basis while the required Tariff process took its course." Sept. 22, 2016 Order,
FERC's consideration of these "relevant, significant facts" distinguished its approach in this case from its usual policy and the precedent it set in other cases.
Cf.
PG&E Gas Transmission, Nw. Corp. v. Fed. Energy Regulatory Comm'n
,
* * *
*14 We thus deny the Petitions in full. FERC reasonably determined that the pro rata allocation of SSR costs in the ATC footprint was unjust and unreasonable, based upon substantial evidence. The ordered remedy of refunds funded by surcharges was within FERC's remedial authority under Sections 206 and 309 of the FPA, and FERC adequately explained its rationale in ordering that remedy here.
898 F.3d 1 (Verso Corp. v. Fed. Energy Regulatory Comm'n) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.