Wisconsin Public Power Inc. v. Federal Energy Regulatory Commission

493 F.3d 239, 377 U.S. App. D.C. 266, 2007 U.S. App. LEXIS 17257
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 20, 2007
Docket04-1414, 05-1006, 05-1007, 05-1198, 05-1203, 05-1358, 05-1427, 05-1428, 05-1429
StatusPublished
Cited by46 cases

This text of 493 F.3d 239 (Wisconsin Public Power Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Public Power Inc. v. Federal Energy Regulatory Commission, 493 F.3d 239, 377 U.S. App. D.C. 266, 2007 U.S. App. LEXIS 17257 (D.C. Cir. 2007).

Opinion

Opinion for the Court filed PER CURIAM.

PER CURIAM:

The Midwest Independent System Operator, known as MISO, is a nonprofit corporation that controls the transmission of electricity over a grid spanning 15 Mid-western states. Its original tariff was approved by-the Federal Energy Regulatory Commission and went into effect in 2002. Under that tariffs terms, MISO approved transmission requests, scheduled service, monitored the grid to manage congestion, and provided various ancillary services to support the regional electricity market.

On March 24, 2004, MISO filed a revised tariff with FERC. Under the new tariff, MISO administers two competitive wholesale power markets: a “day-ahead” market that allows transmission to be scheduled in advance, and a real-time or “spot” market. Among other improvements over MISO’s original operations, these markets incorporate more sophisticated pricing and congestion-management mechanisms that *246 increase the efficiency and reliability of the transmission grid. In a series of orders issued between May 2004 and September 2005, the Commission accepted the proposed tariff with modifications, and MISO’s new market began operating on April 1, 2005. Three groups of petitioners now seek review of various aspects of the Commission’s orders: the Transmission Dependent Utilities, who rely on MISO’s transmission system and markets to buy and sell electric power to retail customers; the Transmission Owners, who are electricity sellers in MISO’s markets subject to the new tariffs rules and liabilities; and the Cooperatives, who are electricity buyers under contracts predating the establishment of MISO. For the reasons that follow, we deny the petitions of the Transmission Dependents and the Transmission Owners, and we dismiss those of the Cooperatives for lack of standing.

I

Section 201(b) of the Federal Power Act (FPA) grants the Federal Energy Regulatory Commission exclusive jurisdiction over the transmission and wholesale salé of electricity in interstate commerce. See 16 U.S.C. § 824(b). Section 205 of the FPA provides that “[a]ll rates and charges made, demanded, or received by any public utility for or in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission ... shall be just and reasonable, and any such rate or charge that is not just and reasonable is hereby declared to be unlawful.” Id. § 824d(a). Section 205 also prohibits undue discrimination in rates, charges, or terms of service. See id. § 824d(b). To enforce these requirements, Section 205 requires that utilities file tariffs reflecting their rates and service terms with the Commission, which must in turn ensure that those rates and terms are just and reasonable and not unduly discriminatory. Id. § 824d(c).

A

In the mid-1990s, FERC determined that longstanding structural barriers to competition in the wholesale power market constituted undue discrimination. Since then, it has been the Commission’s policy to eliminate those barriers and promote competition. This policy required a significant shift in the Commission’s regulatory approach, which has in turn produced dramatic changes in the electricity • industry. Because the tariff at issue in these petitions is part of that transformation, we begin with some background on the development of FERC’s policy. Rather than reinventing the wheel, we borrow the following account from our opinion in Midwest ISO Transmission Owners v. FERC:

In the bad old days, utilities were vertically integrated monopolies; electricity generation, transmission, and distribution for a particular geographic area were generally provided by and under the control of a single regulated utility. Sales of those services were “bundled,” meaning consumers paid a single price for generation, transmission, and distribution. As the Supreme Court observed, with blithe understatement, “[c]ompetition among utilities was not prevalent.” New York v. FERC, 535 U.S. 1, 5, 122 S.Ct. 1012, 152 L.Ed.2d 47 (2002).
In its pathmarking Order No. 888, FERC required utilities that owned transmission facilities to guarantee all market participants non-discriminatory access to those facilities. See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities, FERC Stats. & Regs. ¶ 31,036, 31,-635-36 (1996) (Order No. 888). That is, FERC required all transmission-owning utilities to provide transmission service for electricity generated by others on *247 the same basis that they provided transmission service for the electricity they themselves generated. To effectuate this introduction of competition, FERC required public utilities to “functionally unbundle” their wholesale generation and transmission services by stating separate rates for each service in a single tariff and offering transmission service under that tariff on an open-access, non-discriminatory basis. See New York, 535 U.S. at 11, 122 S.Ct. 1012; see generally California Indep. Sys. Operator Corp. v. FERC, 372 F.3d 395, 397 (D.C.Cir.2004).
As the next step toward the goal of a more competitive electricity marketplace, Order No. 888 encouraged — but did not require — the development of multi-utility regional transmission organizations (RTOs). The concern was that the segmentation of the transmission grid among different utilities, even if each had functionally unbundled transmission, contributed to inefficiencies that impeded free competition in the market for electric power. Combining the different segments and placing control of the grid in one entity — an RTO — was expected to overcome these inefficiencies and promote competition. Order No. 888 at 31,730-32; see also Public Util. Dist. No. 1 of Snohomish County v. FERC, 272 F.3d 607, 610-11 (D.C.Cir. 2001). Better still if the RTO were run by an independent system operator — an ISO. As envisioned by FERC, an ISO would assume operational control — but not ownership — of the transmission facilities owned by its member utilities, thereby “separating] operation of the transmission grid and access to it from economic interests in generation.” Order No. 888 at 31,654; see also id. at 31,730-32. The ISO would then provide open access to the regional transmission system to all electricity generators at rates established in “a single, unbundled, grid-wide tariff that applies to all eligible users in a non-discriminatory manner.” Id. at 31,731; see also California Indep. Sys. Operator Corp., 372 F.3d at 397. FERC called this type of separation of generation and transmission “operational unbundling,” a step beyond “functional unbundling.” Order No. 888 at 31,654. Although several parties to the 1996 rulemaking had requested that FERC require “operational unbundling” or even divestiture of transmission assets, it was FERC’s considered judgment that “the less intrusive functional unbundling approach ... is all that we must require at this time.” Id. at 31,655.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michigan Electric Transmission Company, LLC v. FERC
141 F.4th 1296 (D.C. Circuit, 2025)
Central Hudson Gas & Electric Corporation v. FERC
138 F.4th 531 (D.C. Circuit, 2025)
Glen Bahr v. American Transmission Company LLC
Court of Appeals of Wisconsin, 2023
Citadel FNGE Ltd. v. FERC
77 F.4th 842 (D.C. Circuit, 2023)
Coalition of MISO Transmission v. FERC
45 F.4th 1004 (D.C. Circuit, 2022)
State of California v. Alex Azar, II
950 F.3d 1067 (Ninth Circuit, 2020)
Missouri River Energy Services v. F.E.R.C.
918 F.3d 954 (D.C. Circuit, 2019)
Verso Corp. v. Fed. Energy Regulatory Comm'n
898 F.3d 1 (D.C. Circuit, 2018)
Residential Credit Opportunities Trust v. Poblete
245 F. Supp. 3d 91 (District of Columbia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
493 F.3d 239, 377 U.S. App. D.C. 266, 2007 U.S. App. LEXIS 17257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-public-power-inc-v-federal-energy-regulatory-commission-cadc-2007.