Black Oak Energy, LLC v. Federal Energy Regulatory Commission

725 F.3d 230, 406 U.S. App. D.C. 357, 2013 WL 3988709, 2013 U.S. App. LEXIS 16201
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 6, 2013
Docket08-1386, 11-1275, 12-1286
StatusPublished
Cited by42 cases

This text of 725 F.3d 230 (Black Oak Energy, LLC v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black Oak Energy, LLC v. Federal Energy Regulatory Commission, 725 F.3d 230, 406 U.S. App. D.C. 357, 2013 WL 3988709, 2013 U.S. App. LEXIS 16201 (D.C. Cir. 2013).

Opinion

Opinion for the Court filed by Circuit Judge GRIFFITH.

GRIFFITH, Circuit Judge:

By statute, the Federal Energy Regulatory Commission (FERC) regulates trading in energy markets. This case concerns the markets operated by PJM Interconnection LLC, a Regional Transmission Organization (RTO) 1 covering the East Coast, Appalachia, and parts of the Midwest. Some PJM market participants are known as “virtual marketers.” Unlike participants who actually traffic in electricity, the virtual marketers never deliver or take delivery of electricity; they trade in order to profit from price fluctuations.

The petitioners and petitioner-intervenors in this case—all virtual marketers— petition for review of two sets of FERC orders. The first orders approved PJM’s method for disbursing a monetary surplus that results from the way it operates its markets. The virtual marketers do not receive any of this large pool of money, but they believe they should. To that end, they argue that FERC’s orders violate the Federal Power Act (FPA) and the Administrative Procedure Act (APA). In Part I, we set forth the facts relevant to this petition for review, and in Part II, we set forth our reasons for denying it.

The second petition—also brought by a group of virtual marketers, albeit a larger *233 set of them—seeks review of FERC’s orders requiring PJM to recoup money refunded to the virtual marketers in connection with the administrative dispute over the surplus. The petitioners and petitioner-intervenors argue that these orders also violated the FPA and the APA. In Part III, we set forth the facts relevant to this petition and explain our reasons for remanding the orders in question to FERC for reconsideration.

I

In the mid-1990s, federal electricity policy took a competitive turn. Prior to that time, “utilities were vertically integrated monopolies; electricity generation, transmission, and distribution for a particular geographic area were generally provided by and under the control of a single regulated entity.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1363-64 (D.C.Cir.2004). Since then, those vertical monopolies have broken apart and, in many regions, systems utilizing electricity trading markets have sprung up in their place. Generators sit at one end of the regional transmission process; at the other end sit local utility companies. The markets help coordinate and allocate electricity from the generators to the local utilities. The market operator involved in this case, PJM Interconnection, LLC, is an RTO that uses markets to determine pricing and to schedule the transmission of electricity across the massive territory in which it operates. See Atl. City Elec. Co. v. PJM Interconnection, LLC, 115 FERC ¶ 61,132, 61,473 (2006). PJM operates two markets relevant to this portion of the case: a “Day-Ahead Market” and a “Real-Time Market.”

The vast majority of electricity traded in the PJM markets is traded in the Day-Ahead Market, in which traders bid on electricity to be transmitted the next day.

See Black Oak Energy, LLC v. PJM Interconnection, LLC, 125 FERC ¶ 61,042, 61,-146 (2008). (Since electricity cannot be effectively stored, delivery must be timely.) The Day-Ahead, market “derives a market-clearing price from the sellers’ and buyers’ price and quantity indications for the next day; sales are then made at the market-clearing price.” Edison Mission Energy, Inc. v. FERC, 394 F.3d 964, 965 (D.C.Cir.2005). PJM then produces a transaction schedule in advance of actual production and distribution. See FERC Office of Enforcement, Energy Primer: A Handbook of Energy Basics 101 (2012) [hereinafter Energy Primer]. “The day-ahead market allows market participants to ... hedge against price fluctuations that can occur in real-time” due to problems such as generator outages, weather events, and unforeseen congestion. Id.

Not all electricity is purchased in advance, however. Various risk factors upset sellers’ and buyers’ projections of supply and demand as manifested in the Day-Ahead schedule. In PJM’s Real-Time Market, participants correct for these changes by trading electricity at prices quoted for sale and delivery within five-minute intervals. See id. at 102. PJM calculates these prices based on grid operating conditions and submitted bids. See id. PJM then coordinates the supply and distribution chain “to meet the instantaneous demand for electricity.” Id.

In the Day-Ahead and Real-Time markets, PJM calculates prices according to the method of Locational Marginal Pricing (LMP), which is used by electricity market operators across the country. See Sacramento Mun. Util. Dist. v. Cal. Indep. Sys. Operator Corp., 616 F.3d 520, 524-26 (D.C.Cir.2010) (per curiam); Wis. Pub. Power, Inc. v. FERC, 493 F.3d 239, 250-51 (D.C.Cir.2007) (per curiam). Under LMP, the price any given buyer pays for electric *234 ity reflects a collection of costs attendant to moving a megawatt of electricity through the system to a buyer’s specific location on the grid.

As we have explained in the past,

[w]ith an LMP-based rate structure, prices are designed to reflect the least-cost of meeting an incremental megawatt-hour of demand at each location on the grid, and thus prices vary based on location and time. [In an LMP system, each price] consists of three components: (i) the cost of generation; (ii) the cost of congestion; and (iii) the cost of transmission losses.

Sacramento Mun. Util. Dist., 616 F.3d at 524 (citation omitted). The cost of generation can be thought of as the “baseline cost” of serving electricity (known in the industry as “load”) to another location on the system in a hypothetical, congestion-free environment. Id. Congestion, in turn, drives up costs because it requires PJM to dispatch more expensive generators to meet demand. See Energy Primer at 65. The cost of congestion results in different prices at different nodes of the system, depending on how congested the wires leading to those nodes are. Wis. Pub. Power, Inc., 493 F.3d at 250-51. At issue in this case is the cost of “transmission losses,” which refers to “the amount of electric energy lost when electricity flows across a transmission system....” Sithe/Independence Power Partners, L.P. v. FERC, 285 F.3d 1, 2 (D.C.Cir.2002). The losses are a function of “the amount of the current flowing on the wire[,] ... the resistance it encounters,” and the distance it travels. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Jersey Conservation Foundation v. FERC
111 F.4th 42 (D.C. Circuit, 2024)
Healthy Gulf v. FERC
107 F.4th 1033 (D.C. Circuit, 2024)
Friends of Animals v. Williams
District of Columbia, 2024
Eagle County, Colorado v. STB
82 F.4th 1152 (D.C. Circuit, 2023)
Citadel FNGE Ltd. v. FERC
77 F.4th 842 (D.C. Circuit, 2023)
XO Energy MA, LP v. FERC
77 F.4th 710 (D.C. Circuit, 2023)
Advanced Energy United, Inc. v. FERC
82 F.4th 1095 (D.C. Circuit, 2023)
American Public Gas Association v. DOE
72 F.4th 1324 (D.C. Circuit, 2023)
Sierra Club v. FERC
68 F.4th 630 (D.C. Circuit, 2023)
American Hospital Association
District of Columbia, 2023
Constellation Mystic Power v. FERC
45 F.4th 1028 (D.C. Circuit, 2022)
Bloomberg L.P. v. SEC
45 F.4th 462 (D.C. Circuit, 2022)
Food & Water Watch v. FERC
28 F.4th 277 (D.C. Circuit, 2022)
Friends of the Earth v. Haaland
District of Columbia, 2022

Cite This Page — Counsel Stack

Bluebook (online)
725 F.3d 230, 406 U.S. App. D.C. 357, 2013 WL 3988709, 2013 U.S. App. LEXIS 16201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-oak-energy-llc-v-federal-energy-regulatory-commission-cadc-2013.