Western Area Power Administration v. Federal Energy Regulatory Commission

525 F.3d 40, 381 U.S. App. D.C. 108, 2008 U.S. App. LEXIS 9528, 2008 WL 1932780
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 2, 2008
Docket04-1090
StatusPublished
Cited by8 cases

This text of 525 F.3d 40 (Western Area Power Administration v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Area Power Administration v. Federal Energy Regulatory Commission, 525 F.3d 40, 381 U.S. App. D.C. 108, 2008 U.S. App. LEXIS 9528, 2008 WL 1932780 (D.C. Cir. 2008).

Opinion

Opinion for the Court filed by Senior Circuit Judge EDWARDS.

EDWARDS, Senior Circuit Judge:

This case arises from the reorganization of the electric transmission grid in the state of California, the subsequent imposition of administrative fees by the California Independent Systems Operator (“ISO”), and the pass-through of those fees by Pacific Gas and Electric (“PG & E”) to its customers. The decision of the Federal Energy Regulatory Commission (“FERC” or “Commission”) to approve the fees and pass-through has been challenged by several large customers of PG & E — the Western Area Power Administration, Northern California Power Agency, Sacramento Municipal Utility District (“SMUD”), City of Santa Clara, and Modesto Irrigation District (together “Existing Customers”) — as well as the Cogener-ation Association of California and the Energy Producers and Users Coalition (together “CoGen”). The petitioners argue that the Commission acted arbitrarily and capriciously in approving fees that violated FERC cost/eausation principles and imposed new fees for existing services, in violation of the Mobile-Sierra doctrine.

We uphold the Commission’s Order against both sets of challenges. CoGen’s petition to this court was untimely. Subject matter jurisdiction over challenges to a FERC order is limited to petitions that are filed within 60 days of the challenged order. 16 U.S.C. § 825Z(b). Because Co-Gen did not file its petition within that time frame, we cannot review its merits. While we have jurisdiction over the petition of the Existing Customers, we find that the Commission did not act arbitrarily or capriciously in its approval of the California ISO’s fees or the PG & E pass-through. We therefore uphold the decision of the Commission.

I. Background

In 1996, FERC inaugurated a “brave new regulatory world” with Order No. 888. East Kentucky Power Coop., Inc. v. FERC, 489 F.3d 1299, 1301-02 (D.C.Cir.2007). This Order was “[p]romulgated in response to the anticompetitive effects of vertical integration” where generation of electricity and transmission of electricity was controlled by the same entity. Id at 1302. The Order attempted to increase competition in the electricity business by “requiring] the functional unbundling of wholesale generation and transmission services.” Id (quotation marks omitted). We have described Order No. 888 as follows:

If vertical integration (the predecessor to functional unbundling) offered a prix fixe menu of utility services, functional unbundling required the a la carte alternative: Under the new system, previously integrated utilities were now required to maintain a wholesale marketing function separate from their transmission functions....
*44 In addition to the unbundling requirements that it imposed, Order No. 888 encouraged, but did not demand, the formation of Regional Transmission Organizations (“RTOs”): multi-utility entities that could manage all transmission services for a particular region.... FERC suggested a further improvement to the novel system it envisioned[:] The multi-utility RTO would cede operational control of its collectively run transmission facilities to an [ISO], which would have no financial interest in generation services and therefore no incentive to thwart FERC’s goals of efficiency, competition, and improved reliability.

Id.

As the Commission was implementing Order No. 888, the State of California chartered the California ISO as “an independent entity that would take over transmission operations from California utilities.” Sacramento Mun. Util. Dist. v. FERC, 428 F.3d 294, 296-97 (D.C.Cir.2005). Upon taking over the transmission grid, the California ISO would provide transmission services on a nondiscriminatory basis. Prior to the transition to the ISO, the three major privately-owned utilities — PG & E, Southern California Edison, and San Diego Gas & Electric — each had operated its own control area, performing the coordination, administrative, and maintenance duties needed to operate a reliable power system. Contracts between PG & E and the Existing Customers, collectively referred to as the Control Area Agreements, date to the time when PG & E held responsibility for its control area. Upon the creation of the California ISO, the privately-owned utilities became participating transmission owners in the new system by turning over control of their transmission facilities to the ISO. After that transition, certain services contracted for by the Existing Customers in the Control Area Agreements with PG & E were provided by the California ISO.

In 1997, the California ISO filed its original proposed Grid Management Charge which was designed to recover its start-up, administrative, and operating costs. Letter from Charles Robinson, General Counsel, California ISO, and Edward Berlin, Swidler Berlin Shereff & Friedman, to David P. Boergers, Secretary, FERC (Nov. 1, 2000) at 1, reprinted in Joint Appendix (“JA”) 86. This charge was assessed on a monthly basis against all ISO Scheduling Coordinators — the entities that are responsible for scheduling electricity deliveries through the ISO. Id. Under the new system, PG & E has been the Scheduling Coordinator for the Existing Customers for all relevant time periods.

In November 2000, the California ISO proposed a new Grid Management Charge for the period from January 1, 2001 to January 1, 2004. The revised Grid Management Charge “unbundled” the earlier charge in order to “allocate costs fairly among all ISO system users, and minimize cost subsidization among” participants in California’s electrical market. Id. at 6, JA 91. The ISO believed that unbundling the Grid Management Charge would better reflect “the principle of cost causation” which it defined as meaning that “the ISO’s costs, to the extent possible, should be attributed to those entities that caused them to be incurred.” Id. Tying fees closely to cost causation facilitates market efficiency because more accurate “price signals direct[] market behavior towards optimum results.” Id.

The Grid Management Charge was unbundled according to three categories of services that the ISO provides: Control Area Services, Inter-Zonal Scheduling, and Market Operations. Control Area Services are the services that the ISO provides as a Control Area operator to *45 ensure “reliable, safe operation of the transmission grid.” Id. at 8, JA 93. The ISO’s responsibilities as a Control Area operator include

scheduling generation, imports, exports, and wheeling transactions ...; insuring adherence to regional and national reliability standards; monitoring and developing transmission maintenance standards; performing operational studies and system security analyses; dispatching bulk power supplies; conducting system planning to ensure overall reliability; ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
525 F.3d 40, 381 U.S. App. D.C. 108, 2008 U.S. App. LEXIS 9528, 2008 WL 1932780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-area-power-administration-v-federal-energy-regulatory-commission-cadc-2008.