Sacramento Municipal Utility District v. Federal Energy Regulatory Commission

616 F.3d 520, 392 U.S. App. D.C. 339, 2010 U.S. App. LEXIS 15179, 2010 WL 2870645
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 23, 2010
Docket07-1208, 07-1216, 07-1217, 07-1513, 08-1298, 08-1311
StatusPublished
Cited by38 cases

This text of 616 F.3d 520 (Sacramento Municipal Utility District v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sacramento Municipal Utility District v. Federal Energy Regulatory Commission, 616 F.3d 520, 392 U.S. App. D.C. 339, 2010 U.S. App. LEXIS 15179, 2010 WL 2870645 (D.C. Cir. 2010).

Opinion

PER CURIAM:

Following the California energy crisis of 2000-01, the California Independent System Operator (California ISO or the ISO) began the process of redesigning California’s electricity market. The Federal Energy Regulatory Commission (FERC or the Commission) issued a series of orders providing guidance on California ISO’s proposals. Ultimately, in four orders issued between 2006 and 2008, the Commission approved the ISO’s new market design, rejecting the numerous objections lodged by at least sixty-seven intervenors. Four parties — the Sacramento Municipal Utility District (Sacramento), the Imperial Irrigation District (Imperial), the City and *523 County of San Francisco (San Francisco), and the San Diego Gas & Electric Company (San Diego) — now petition for review of these orders. Sacramento and Imperial challenge California ISO’s “locational marginal pricing” rate design, arguing in particular that it is unreasonable and unlawful to charge customers for the marginal cost of transmission losses. San Francisco challenges the “local resource adequacy requirement” imposed by California ISO, claiming it deprives San Francisco of the value of a preexisting contract. Finally, San Diego and Sacramento challenge aspects of the financial mechanism California ISO devised to allow customers to hedge against congestion costs. We find no merit to these arguments and therefore deny the petitions for review.

I. Background

A. The Parties

“In 1996, the Commission ordered the national deregulation of electricity transmission services. Order No. 888 required utilities to ‘unbundle’ their electricity generation and transmission services and to file new ‘open access’ tariffs — modeled on a pro forma tariff included in the rulemaking-guaranteeing non-discriminatory access to their transmission facilities by competing generators.” Sacramento Mun. Util. Dist. v. FERC, 428 F.3d 294, 295-96 (D.C.Cir.2005) (“Sacramento I”) (citing Promoting Wholesale Competition Through Open Access Nom-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, 61 Fed.Reg. 21,540 (Apr. 24, 1996) (“Order 888”)). 1 Order 888 also encouraged public utilities “to participate in Independent System Operators (‘ISOs’).” Cal. Indep. Sys. Operator Corp. v. FERC, 372 F.3d 395, 397 (D.C.Cir.2004). “An ISO conducts the transmission services and ancillary services for all users of such a system, replacing the conduct of such services by the system owners.... FERC deems it crucial that an ISO be independent of the market participants so that decisions of policy, operation, and dispute resolution be free of the discriminatory impetus inherent in the old system.” Id. (citing Order 888 at 31,731).

Thus, in 1996, the California legislature chartered California ISO, “a non-profit organization that took over operation (but not ownership) of many transmission facilities” in the state. Sacramento Mun. Utility Dist. v. FERC, 474 F.3d 797, 798 (D.C.Cir.2007). California ISO maintains a tariff, subject to approval by the Commission, setting forth the terms, conditions, and rates under which it provides electricity service to customers. Sacramento, Imperial, San Francisco, and San Diego are all “load-serving entities,” meaning they acquire electricity from California ISO for delivery to end-use consumers. The wholesale rates they pay are dictated by the ISO’s tariff.

However, these four petitioners are not all alike. San Diego is a privately-owned utility that became a “participating transmission owner” in California ISO by turning over operational control of its transmission facilities to the ISO. See W. Area Power Admin. v. FERC, 525 F.3d 40, 44 (D.C.Cir.2008). Thus, California ISO assumed the obligation to honor San Diego’s preexisting transmission contracts. By contrast, Sacramento, Imperial, and San Francisco are publicly-owned “non-juris *524 dictional” utilities that opted not to become participating transmission owners of California ISO. (They are called “non-jurisdictional” because, as governmental entities, they are not subject to FERC’s jurisdiction under §§ 205 and 206 of the Federal Power Act, see 16 U.S.C. § 824(f).) Accordingly, they own or co-own certain transmission facilities that are within California ISO’s “balancing authority area” 2 but are not part of the ISO’s grid. These entities retain “transmission ownership rights” — contractual entitlements to use such facilities.

B. The Market Redesign and Technology Upgrade Proposal

“In 2000, wholesale prices for electricity in California increased dramatically and resulted in the now-infamous California energy crisis.” Pac. Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1317 (D.C.Cir.2004). This prompted California ISO, at the behest of the Commission, to begin redesigning California’s electricity market to avoid any repetition of the 2000-01 crisis. California ISO’s “market redesign and technology upgrade” proposal followed. Over the course of six years, the Commission issued more than thirty orders providing guidance to California ISO and its market participants on the various contours of the proposed changes. The Commission ultimately approved California ISO’s revised tariff in four orders issued between 2006 and 2008. 3 Three features of this tariff are challenged here: its incorporation of marginal loss charges into locational marginal prices, its local resource adequacy requirement, and its congestion revenue rights mechanism.

1. Locational Marginal Pricing

California ISO proposed to use “locational marginal pricing” (LMP) to set wholesale electricity prices. With an LMP-based rate structure, prices are designed to reflect the least-cost of meeting an incremental megawatt-hour of demand at each location on the grid, and thus prices vary based on location and time. Each LMP consists of three components: (i) the cost of generation; (ii) the cost of congestion; and (iii) the cost of transmission losses. See First Market Redesign Order ¶ 50. The first component refers basically to the baseline cost of serving load 4 anywhere on the system in the absence of congestion and transmission losses. Id. With respect to the second component, we have explained:

LMP ... incorporates the cost of congestion into the price of energy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Appalachian Voices v. FERC
139 F.4th 903 (D.C. Circuit, 2025)
Pacific Gas and Electric Company v. FERC
113 F.4th 943 (D.C. Circuit, 2024)
Sierra Club v. FERC
97 F.4th 16 (D.C. Circuit, 2024)
Seia v. Ferc
Ninth Circuit, 2023
El Paso Electric v. FERC
76 F.4th 352 (Fifth Circuit, 2023)
XO Energy MA, LP v. FERC
77 F.4th 710 (D.C. Circuit, 2023)
Advanced Energy United, Inc. v. FERC
82 F.4th 1095 (D.C. Circuit, 2023)
LSP Transmission Holdings II, LLC v. FERC
45 F.4th 979 (D.C. Circuit, 2022)
Xcel Energy Services Inc. v. FERC
41 F.4th 548 (D.C. Circuit, 2022)
NextEra Energy Resources, LLC v. Department of Public Utilities
Massachusetts Supreme Judicial Court, 2020
Esi Energy, LLC v. Fed. Energy Regulatory Comm'n
892 F.3d 321 (D.C. Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
616 F.3d 520, 392 U.S. App. D.C. 339, 2010 U.S. App. LEXIS 15179, 2010 WL 2870645, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sacramento-municipal-utility-district-v-federal-energy-regulatory-cadc-2010.