Opinion for the Court filed by Circuit Judge HENDERSON.
KAREN LeCRAFT HENDERSON, Circuit Judge:
Petitioners Jackson County, N.C., Town of Franklin, N.C. and the Friends of Lake Glenville Association, Inc. challenge orders of the Federal Energy Regulatory Commission (FERC or Commission) which granted the application of Duke Energy Carolinas, LLC (Duke) to surrender its license to operate the Dillsboro, N.C. hydroelectric project (Dillsboro Project) and to remove the project’s dam and powerhouse.
See Duke Energy Carolinas, LLC,
120 F.E.R.C. ¶ 61,054, 2007 WL 2064626 (July 19, 2007)
(Surrender Order), reh’g granted in part,
123 F.E.R.C. ¶ 61,069, 2008 WL 1808190 (Apr. 22, 2008)
(Rehearing Order).
We deny the petition for review because the challenged decisions are not “arbitrary and capricious or otherwise contrary to law.”
Transmission Agency of N. Cal. v. FERC,
495 F.3d 663, 671 (D.C.Cir.2007) (internal quotation omitted).
I.
The Dillsboro Project, one of seven hydroelectric projects Duke operates in North Carolina’s Nantahala and Tuckase-gee River Basins, consists of a concrete masonry dam and a powerhouse with two generating units on the Tuckasegee River in Jackson County. In July 2003, Duke applied to FERC to renew its license to operate the Dillsboro Project after its then-effective license expired on July 31, 2005. In the application cover letter, however, Duke advised FERC that it might thereafter apply to surrender its license instead. In May 2004, Duke filed an application to surrender the license, proposing to remove the project’s dam and powerhouse pursuant to two settlement agreements — the Nantahala Cooperative Stakeholder Team’s Settlement Agreement (Nantahala Agreement) and the Tuckase-gee Cooperative Stakeholder Team’s Settlement Agreement (Tuckasegee Agreement). Each settlement agreement had been approved by a majority of “stakeholders” in the respective river basin (Nantahala or Tuckasegee), including various resident and property associations, environmental and wildlife organizations, North Carolina environmental agencies, the U.S. Fish and Wildlife Service (FWS) and the U.S. Forest Service. The Tucka-segee Agreement provided for the surrender of the Dillsboro license (and removal of the dam and powerhouse), while Duke’s relicensing applications for three other Tuckasegee River hydroelectric projects— the Bryson, East Fork and West Fork Projects — would proceed. The Nantahala Agreement covered the Franklin, Mission and Nantahala Projects in the Nantahala River Basin and provided that all three should be relicensed and remain in operation.
Attached to the Dillsboro surrender application was an “Environmental Assessment and Biological Assessment” analyzing the effects of various alternative actions Duke could take with regard to the Dillsboro dam (no action, partial dam re
moval or full dam removal) and the powerhouse (no action, powerhouse closure or powerhouse removal).
On June 16, 2005, a group of 12 stakeholders (the petitioners among them) submitted an “Offer of Preferred Settlement Agreement.” The accompanying “Tucka-segee River and Nantahala Area Preferred Settlement Agreement” (Preferred Settlement Agreement) proposed that the Tuck-asegee Agreement be revised to provide that the Dillsboro Project be relicensed, that Duke transfer its license, its equipment and all interests in the Project to Jackson County (or its designee) as a charitable contribution and that Duke contribute $500,000 to state agencies “for river, stream and lakeshore restoration” and take measures to safeguard the River, the Project and local wildlife. Preferred Settlement Agreement,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, - 007, at 11-12 (June 16, 2005).
The Commission issued a final Environmental Assessment (EA) on July 14, 2006, setting out as its “recommended alternative” the complete removal of the Dillsboro dam and powerhouse, as Duke had proposed. Final Environmental Assessment for Hydropower Licenses — Nantahala East Projects,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, -007, at 352-54 (July 2006). The EA determined that, despite “significant short-term effects” — including effects “on habitat for the Appalachian elktoe mussel, a federally endangered species” — removing the dam and powerhouse would not cause resources (“including geology, water quantity and quality, fisheries, terrestrial, aesthetic, cultural, and recreational” resources) — to experience “significant long-term adverse effects.”
Id.
at 389. In particular, the EA found that the action, as proposed, would (1) “restore the river to free-flowing rive-rine conditions and allow continuous access to 9.5 miles of upstream river habitat previously blocked by Dillsboro Dam,”
id.
at 146; and (2) “benefit the populations of the Appalachian elktoe in the Tuckasegee River” because the “increase in available habitat would improve [the elktoe’s] overall abundance ... and contribute to the FWS recovery efforts for the species,”
id.
at 191, 193. Accordingly, the EA concluded the license surrender and dam/powerhouse removal “would not constitute a major federal action significantly affecting the quality of the human environment.”
Id.
at 389.
In August 2006, the FWS filed its “Biological Opinion” (BiOp) concluding that the “incidental take” that “may occur ... as a result of demolition activities associated with the decommissioning of the Dillsboro Dam” is “not likely to result in jeopardy to the Appalachian elktoe.” Biological Opinion,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, -007 (Aug. 20, 2006), at 43, 45.
On July 19, 2007, FERC issued the
Surrender Order
which granted Duke’s surrender application, approving removal of the dam and powerhouse, and dismissed Duke’s mooted application for relicensure.
See Surrender Order,
120 F.E.R.C. at 1 ¶ 1. In the order, FERC concluded that, notwithstanding “short-term environmental impacts and ... a loss of 0.225 MW of capacity,” surrender “will benefit environmental resources in the Tuckasegee River, and is in the public interest” because it “will result in greater upstream and downstream fish movement, wider distribution of Appalachian elktoe mussels, as well as improvement of recreational opportunities in the Tuckasegee River.”
Id.
at 20 ¶ 50. The Commission also imposed measures to safeguard the Appalachian elktoe and to minimize the downstream transport of sediments and directed that Duke construct a new public boat launch and parking area.
Various parties filed requests for rehearing and clarification, among them a group of entities that included the petitioners. Requests for Rehearing of Jackson County, N.C. et al.,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, - 007 (Aug. 20, 2007) (Jackson County Rehearing Request). The petitioners’ request asked that the Commission rescind the
Surrender Order
on various grounds and reinstate the Dillsboro Project license.
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion for the Court filed by Circuit Judge HENDERSON.
KAREN LeCRAFT HENDERSON, Circuit Judge:
Petitioners Jackson County, N.C., Town of Franklin, N.C. and the Friends of Lake Glenville Association, Inc. challenge orders of the Federal Energy Regulatory Commission (FERC or Commission) which granted the application of Duke Energy Carolinas, LLC (Duke) to surrender its license to operate the Dillsboro, N.C. hydroelectric project (Dillsboro Project) and to remove the project’s dam and powerhouse.
See Duke Energy Carolinas, LLC,
120 F.E.R.C. ¶ 61,054, 2007 WL 2064626 (July 19, 2007)
(Surrender Order), reh’g granted in part,
123 F.E.R.C. ¶ 61,069, 2008 WL 1808190 (Apr. 22, 2008)
(Rehearing Order).
We deny the petition for review because the challenged decisions are not “arbitrary and capricious or otherwise contrary to law.”
Transmission Agency of N. Cal. v. FERC,
495 F.3d 663, 671 (D.C.Cir.2007) (internal quotation omitted).
I.
The Dillsboro Project, one of seven hydroelectric projects Duke operates in North Carolina’s Nantahala and Tuckase-gee River Basins, consists of a concrete masonry dam and a powerhouse with two generating units on the Tuckasegee River in Jackson County. In July 2003, Duke applied to FERC to renew its license to operate the Dillsboro Project after its then-effective license expired on July 31, 2005. In the application cover letter, however, Duke advised FERC that it might thereafter apply to surrender its license instead. In May 2004, Duke filed an application to surrender the license, proposing to remove the project’s dam and powerhouse pursuant to two settlement agreements — the Nantahala Cooperative Stakeholder Team’s Settlement Agreement (Nantahala Agreement) and the Tuckase-gee Cooperative Stakeholder Team’s Settlement Agreement (Tuckasegee Agreement). Each settlement agreement had been approved by a majority of “stakeholders” in the respective river basin (Nantahala or Tuckasegee), including various resident and property associations, environmental and wildlife organizations, North Carolina environmental agencies, the U.S. Fish and Wildlife Service (FWS) and the U.S. Forest Service. The Tucka-segee Agreement provided for the surrender of the Dillsboro license (and removal of the dam and powerhouse), while Duke’s relicensing applications for three other Tuckasegee River hydroelectric projects— the Bryson, East Fork and West Fork Projects — would proceed. The Nantahala Agreement covered the Franklin, Mission and Nantahala Projects in the Nantahala River Basin and provided that all three should be relicensed and remain in operation.
Attached to the Dillsboro surrender application was an “Environmental Assessment and Biological Assessment” analyzing the effects of various alternative actions Duke could take with regard to the Dillsboro dam (no action, partial dam re
moval or full dam removal) and the powerhouse (no action, powerhouse closure or powerhouse removal).
On June 16, 2005, a group of 12 stakeholders (the petitioners among them) submitted an “Offer of Preferred Settlement Agreement.” The accompanying “Tucka-segee River and Nantahala Area Preferred Settlement Agreement” (Preferred Settlement Agreement) proposed that the Tuck-asegee Agreement be revised to provide that the Dillsboro Project be relicensed, that Duke transfer its license, its equipment and all interests in the Project to Jackson County (or its designee) as a charitable contribution and that Duke contribute $500,000 to state agencies “for river, stream and lakeshore restoration” and take measures to safeguard the River, the Project and local wildlife. Preferred Settlement Agreement,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, - 007, at 11-12 (June 16, 2005).
The Commission issued a final Environmental Assessment (EA) on July 14, 2006, setting out as its “recommended alternative” the complete removal of the Dillsboro dam and powerhouse, as Duke had proposed. Final Environmental Assessment for Hydropower Licenses — Nantahala East Projects,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, -007, at 352-54 (July 2006). The EA determined that, despite “significant short-term effects” — including effects “on habitat for the Appalachian elktoe mussel, a federally endangered species” — removing the dam and powerhouse would not cause resources (“including geology, water quantity and quality, fisheries, terrestrial, aesthetic, cultural, and recreational” resources) — to experience “significant long-term adverse effects.”
Id.
at 389. In particular, the EA found that the action, as proposed, would (1) “restore the river to free-flowing rive-rine conditions and allow continuous access to 9.5 miles of upstream river habitat previously blocked by Dillsboro Dam,”
id.
at 146; and (2) “benefit the populations of the Appalachian elktoe in the Tuckasegee River” because the “increase in available habitat would improve [the elktoe’s] overall abundance ... and contribute to the FWS recovery efforts for the species,”
id.
at 191, 193. Accordingly, the EA concluded the license surrender and dam/powerhouse removal “would not constitute a major federal action significantly affecting the quality of the human environment.”
Id.
at 389.
In August 2006, the FWS filed its “Biological Opinion” (BiOp) concluding that the “incidental take” that “may occur ... as a result of demolition activities associated with the decommissioning of the Dillsboro Dam” is “not likely to result in jeopardy to the Appalachian elktoe.” Biological Opinion,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, -007 (Aug. 20, 2006), at 43, 45.
On July 19, 2007, FERC issued the
Surrender Order
which granted Duke’s surrender application, approving removal of the dam and powerhouse, and dismissed Duke’s mooted application for relicensure.
See Surrender Order,
120 F.E.R.C. at 1 ¶ 1. In the order, FERC concluded that, notwithstanding “short-term environmental impacts and ... a loss of 0.225 MW of capacity,” surrender “will benefit environmental resources in the Tuckasegee River, and is in the public interest” because it “will result in greater upstream and downstream fish movement, wider distribution of Appalachian elktoe mussels, as well as improvement of recreational opportunities in the Tuckasegee River.”
Id.
at 20 ¶ 50. The Commission also imposed measures to safeguard the Appalachian elktoe and to minimize the downstream transport of sediments and directed that Duke construct a new public boat launch and parking area.
Various parties filed requests for rehearing and clarification, among them a group of entities that included the petitioners. Requests for Rehearing of Jackson County, N.C. et al.,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, - 007 (Aug. 20, 2007) (Jackson County Rehearing Request). The petitioners’ request asked that the Commission rescind the
Surrender Order
on various grounds and reinstate the Dillsboro Project license. FERC rejected the request in its April 22, 2008
Rehearing Order.
The petitioners filed a timely petition for review of FERC’s orders.
II.
As a preliminary matter Duke challenges the petitioners’ standing under Article III of the U.S. Constitution to bring this action. “The ‘irreducible constitutional minimum of standing contains three elements’: (1) injury-in-fact, (2) causation, and (3) redressability.”
Ass’n of Flight Attendants
—CWA
v. U.S. Dep’t of Transp.,
564 F.3d 462, 464 (D.C.Cir.2009) (quoting
Lujan v. Defenders of Wildlife,
504 U.S. 555, 560-61, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992)) (internal quotation omitted). To establish injury, a petitioner “ ‘must[, inter alia,] show ... it has suffered an injury in fact that is (a) concrete and particularized and (b) actual or imminent, not conjectural or hypothetical.’ ”
Dominion Transmission, Inc. v. FERC,
533 F.3d 845, 852 (D.C.Cir.2008) (quoting
Friends of the Earth, Inc. v. Laidlaw Envtl. Servs. (TOC) Inc.,
528 U.S. 167, 180, 120 S.Ct. 693, 145 L.Ed.2d 610 (2000)) (internal quotations omitted) (alterations in original). Duke contends Jackson County lacks standing because it has not produced “any rigorous data or studies demonstrating the required ‘substantial probability,’ ” Intervenor Duke’s Br. 24 (quoting
GrassRoots Recycling Network, Inc. v. EPA
429 F.3d 1109, 1112 (D.C.Cir.2005)), to support its “assert[ions] that [the Dillsboro Project] plays a ‘significant socio-economic role in the Town of Dillsboro’ and in the County and ... is important to tourism and has aesthetic value significant to tourism,”
id.
(quoting Pet’rs’ Br. 2) (citing
id.
at 8). We conclude, however, that Jackson County has alleged a sufficient injury-in-fact, namely “the threatened physical destruction of property within its borders,” which will substantially alter Jackson County’s geography by converting a dammed lake into a free flowing river and eliminate a possible power source. Because Jackson County has standing to bring this action, we need not inquire into the standing of the other two petitioners as all three parties make the same arguments in joint briefs.
See Comcast Corp. v. FCC,
579 F.3d 1, 6 (D.C.Cir.2009) (“ ‘[I]f one party has standing in an action, a court need not reach the issue of the standing of other parties when it makes no difference to the merits of the case.’ ”
(quoting
Ry. Labor Executives’ Ass’n v. United States,
987 F.2d 806, 810 (D.C.Cir.1993))). Accordingly, we address the merits of the petitioners’ arguments.
A. State Water Quality Certiñcation
First, the petitioners contend FERC issued the
Surrender Order
based on an invalid section 401 certification issued by the North Carolina Division of Water Quality (NCDWQ). Section 401 of the Clean Water Act (CWA), 33 U.S.C. § 1341, requires that an “applicant for a Federal license or permit to conduct any activity ... which may result in any discharge into the navigable waters, shall provide the licensing or permitting agency a certification from the State in which the discharge originates or will originate, that any such discharge will comply with the applicable provisions of [33 U.S.C.] sections 1311, 1312, 1313, 1316, and 1317.” 33 U.S.C. § 1341(a)(1).
Section 401 further directs that each State must “establish procedures for public notice in the case of all applications for certification by it and, to the extent it deems appropriate, procedures for public hearings in connection with specific applications,” 33 U.S.C. § 1341(a)(1) — a provision we have interpreted to “also require[ ] states to
comply
with their public notice procedures, and therefore [to] require[] FERC to obtain some minimal confirmation of such compliance, at least in a case where compliance has been called into question.”
City of Tacoma, Wash. v. FERC,
460 F.3d 53, 68 (D.C.Cir.2006). North Carolina has established a certification procedure which generally requires notice by publication in a local newspaper of “each pending application for an individual certification” at least 15 days before NCDWQ final action and not more than 20 days after the application is accepted. 15A N.C. Admin. Code § 2H.0503(a).
Duke applied for section 401 certification as required but NCDWQ apparently failed to publish the required notice of the application. Jackson County argues, as it did on rehearing, that the lack of notice rendered the 2005 certification invalid. We disagree.
Duke filed its “Application for 401 Water Quality Certification for License Surrender” with NCDWQ, attached to a cover letter dated March 11, 2005. Duke filed copies of the application with FERC on March 17, 2005 and on March 28, 2005, mailed copies of the cover letter — stamped as “received” by NCDWQ on March 17, 2005 — to FERC and to all parties to the FERC surrender proceeding, including Jackson County.
See
Letter from Garry S. Rice, Duke Associate General Counsel to FERC,
Duke Energy Carolinas, LLC,
Project Nos. P-2602-005, -007 (Mar. 29, 2005); Pet’rs’ Br. 30 n. 23 (acknowledging Jackson County was served with stamped copy on March 29, 2005). Thus, Jackson County had timely actual notice of the state certification application upon its receipt of same and the purpose of section 401’s notice by publication requirement was thereby fulfilled. Accordingly, we conclude that NCDWQ’s failure to comply
with the statutory notice requirement was harmless.
Cf. Nat’l Mining Ass’n v. Mine Safety & Health Admin.,
116 F.3d 520, 531 (D.C.Cir.1997) (“ ‘[E]ven if [an] agency has not given notice in the statutorily prescribed fashion, actual notice will render the error harmless.’ ” (quoting
Small Refiner Lead Phase-Down Task Force v. EPA,
705 F.2d 506, 549 (D.C.Cir.1983))) (first alteration added);
Nat’l Ass’n of Home Builders v. Defenders of Wildlife,
551 U.S. 644, 659-60, 127 S.Ct. 2518, 168 L.Ed.2d 467 (2007) (“ ‘In administrative law, as in federal and criminal litigation, there is a harmless error rule.’ ” (quoting
PDK Labs., Inc. v. U.S. Drug Enforcement Admin.,
362 F.3d 786, 799 (D.C.Cir.2004))).
B. Environmental Assessment
Jackson County raises several objections to FERC’s EA. We address the objections seriatim.
First, Jackson County asserts that FERC improperly “segmented” its review of the four Tuckasegee projects from the three Nantahala projects and from each other. We believe the Commission appropriately limited the scope of its review. It is true that “[a]gencies may not evade their responsibilities under NEPA by artificially dividing a major federal aetion into smaller components, each without ‘significant’ impact.’ ”
Coal. on Sensible Transp., Inc. v. Dole,
826 F.2d 60, 68 (D.C.Cir.1987) (citing
Taxpayers Watchdog, Inc. v. Stanley,
819 F.2d 294, 298 (D.C.Cir.1987)). “The rule against segmentation, however, is not required to be applied in every situation. To determine the appropriate scope for an EIS, courts have considered such factors as whether the proposed segment (1) has logical termini; (2) has substantial independent utility; (3) does not foreclose the opportunity to consider alternatives, and (4) does not irretrievably commit federal funds for closely related projects.”
Taxpayers Watchdog, Inc.,
819 F.2d at 298. In this case, FERC did not “segment” the individual Tuckasegee projects but instead considered all four in a single EA and, as the petitioners acknowledge, did indeed address the cumulative effects of the four projects — if not with the result the petitioners desired.
See
EA at 44-45 (setting out scope of cumulative effects analysis);
id.
at 105-06, 156-57, 284-85 (analyzing cumulative effects on water quantity and quality, aquatic resources and recreational resources); Jackson County Reh’g Req. at 53 (asserting
Surrender Order
“ignores the associated cumulative impacts to which the EA devoted considerable ink (though little wisdom)”). Throughout, FERC not
ed in particular the interconnectedness of the East and West Fork Projects with the Dillsboro dam because the flow from the former projects largely determined the capacity of the latter project as a “run-of-the-river” project.
See, e.g., Surrender Order
at 2 ¶ 4;
Rehearing Order
at 2 ¶ 4, at 23 ¶ 65 n. 73. That FERC treated the two Nantahala River projects and the Tuckasegee River projects separately was reasonable under
Taxpayers Watchdog, Inc.,
819 F.2d at 298. The Nantahala projects are geographically distinct from the Tuckasegee projects, located on a separate river and covered by a separate, albeit related, settlement agreement. Nor is it true, as Jackson County seems to suggest, that approving the license surrender and dam removal for the Dillsboro Project— the so-called “linchpin” of the two settlement agreements,
see, e.g.,
Pet’rs’ Br. 49— will automatically trigger FERC approval of the other features of the two settlements. Each project’s relieensing application requires separate approval by FERC based on an analysis thereof.
See
16 U.S.C. § 797(e) (“Issue of licenses for construction, etc., of dams, conduits, reservoirs, etc.”);
see generally
18 C.F.R. ch. I, subch. A, pt. 4 (“Licenses, Permits, Exemptions, and Determination of Project Costs”).
Second, Jackson County asserts FERC failed to consider alternatives to license surrender and dam/powerhouse removal — in particular, alternatives to licen-sure surrender which would keep the project licensed and operating in some form, such as the proposal in the Preferred Settlement Agreement to relicense the Dills-boro Project and transfer it to Jackson County.
See also
Pet’rs’ Br. 60 (suggesting “relicensing the Dillsboro Project by the current licensee” and “commencing a new round of competition”);
id.
at 63 (“alternative of
enhancing
renewable energy generation at the site”) (emphasis in original). FERC dismissed such alternatives, however, in reliance on its long-held policy that it lacks authority to relicense or transfer a license and facilities without the licensee’s consent.
See Surrender Order
at 13 ¶ 28 (“A licensee cannot be required to retain or renew its license if it wishes to surrender. Likewise, the Commission cannot compel a transfer, and in any case, no entity developed a transfer proposal, nor has Duke expressed any interest in one.”) (footnotes omitted) (citing Ariz.
Pub. Serv. Co.,
109 F.E.R.C. ¶ 61,036 at ¶ 39 & n. 34 (2004));
Wellesley Rosewood Maynard Mills, L.P.,
108 F.E.R.C. ¶ 61,-048 (2004);
Rehearing Order
at 12, ¶ 31 n. 41 (“[W]e cannot force a licensee to seek a new license for its project upon expiration of the existing license. Thus, given Duke’s express desire to surrender its license, any alternative predicated on the company’s receiving a new license is not feasible and merits no further consideration.”). While Jackson County offered before the Commission to assume responsibility for the dam and powerhouse, and thereby save Duke the costs of removal and mitigation, it did not then challenge FERC’s transfer policy itself and is therefore foreclosed from doing so now.
See Save Our Sebasticook v. FERC,
431 F.3d 379, 381-82 (D.C.Cir.2005) (petitioner forfeited challenge not raised before FERC to Commission’s “legal principle” that it “may not compel” licensee that applies to surrender license “to continue operating the project”) (citing 16 U.S.C. § 825i(b)). Jackson County also contends FERC improperly ignored “alternatives regarding fish passage proposed by Jackson County.” Pet’rs’ Br. 63. FERC reasonably rejected this alternative, however, concluding that “while the Commission may have the authority to order the construction of such facilities as a condition of license surrender, [it] would have no jurisdiction to re
quire ongoing maintenance and monitoring to ensure their effectiveness.”
Rehearing Order
at 12 ¶ 32.
Finally, Jackson County argues, summarily, that FERC violated 18 C.F.R. § 385.602 which “provides that an offer of settlement may be submitted by any party to a proceeding” as well as FERC’s (unidentified) “prior cases” when it “fail[ed] to review [the ‘Offer of Preferred Settlement Agreement’] as a legitimate offer of settlement.” Pet’rs’ Br. 69. FERC considered the Preferred Settlement Agreement but rejected it as “simply a recitation of the filer’s position” and “a settlement agreement in name only” because “[n]either Duke, the licensee, nor any of the federal and state resource agencies that have played a major role in the Dillsboro surrender are parties to it.”
Surrender Order
at 6 ¶ 12 n. 14. This characterization of the document was not arbitrary or capricious.
For the foregoing reasons, the petition for review is denied. We emphasize that nothing in this opinion should be construed to affect the relicensing proceedings for the other six Nantahala and Tuckasegee River projects currently pending before the Commission.
See supra
at 1286 n. 1.
So ordered.