American Whitewater v. FERC

125 F.4th 1139
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 14, 2025
Docket23-1291
StatusPublished
Cited by1 cases

This text of 125 F.4th 1139 (American Whitewater v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Whitewater v. FERC, 125 F.4th 1139 (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued November 20, 2024 Decided January 14, 2025

No. 23-1291

AMERICAN WHITEWATER, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

CONSERVATION LAW FOUNDATION, ET AL., INTERVENORS

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Haley Nicholson argued the cause for petitioner. With her on the briefs were Robert A. Nasdor and Kevin Cassidy.

Sean Mahoney and Charles Owen Verrill, Jr. were on the brief for intervenors Conservation Law Foundation and Maine Rivers in support of petitioner.

Angela X. Gao, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and 2 Robert H. Solomon, Solicitor. Jared Fish, Attorney, entered an appearance.

Julia S. Wood and Sharon L. White were on the brief for intervenor Aclara Meters, LLC in support of respondent.

Before: HENDERSON and PAN, Circuit Judges, and EDWARDS, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge HENDERSON.

KAREN LECRAFT HENDERSON, Circuit Judge: This case arises from the surrender of a license for a hydroelectric project on the Salmon Falls River between New Hampshire and Maine. From 2016 to 2023, Aclara Meters LLC (Aclara) owned the license to the Somersworth Hydroelectric Project (the Project). Aclara sought to surrender its project license to the Federal Energy Regulatory Commission (FERC or the Commission) in 2019. After conducting an environmental assessment, the Commission authorized Aclara’s surrender in 2023. American Whitewater (Whitewater)—a conservation organization working to restore America’s whitewater rivers—requested rehearing and argued that two dams from the Project should be removed as a condition of surrender. After FERC denied that request, Whitewater petitioned this Court for relief, arguing that the Commission acted arbitrarily and capriciously under the Federal Power Act (the FPA) and the National Environmental Policy Act (NEPA).

FERC’s analysis was neither arbitrary nor capricious. It reasonably determined that dam removal was unfeasible because local municipalities relied on the reservoir for key water needs. Even if it were feasible, FERC appropriately considered dam removal as an alternative to surrender without removal and rejected it because the benefits to local municipalities of keeping the dams outweighed the benefits to 3 the environment and recreation from removal. The Commission also appropriately assessed the public interest and did not unreasonably depart from its situation-specific precedents. Accordingly, we deny Whitewater’s petition for review.

I.

A.

The Project is located on the Salmon Falls River, on the border between the City of Somersworth, New Hampshire and the Town of Berwick, Maine, and includes two dams—Stone Dam and Back Dam.1 The Project also includes a canal to divert water from Stone Dam’s reservoir (or impoundment), a gatehouse to control water flow from the reservoir to the canal,

1 Aclara disputes whether Back Dam is included in its project license. Intervenor for Resp’t’s Br. 20 n.9, 21. At oral argument, FERC and Whitewater agreed that Back Dam is not included in the project license. Oral Arg. Tr. 9:1–6 (Whitewater), 14:18–19 (FERC). When initially applying to the Commission for relicensing of the Project, Aclara referenced Back Dam as part of the project facilities, boundary, features and license. J.A. 64, 68, 73. “Figure 1” in the amended license identifies Back Dam as a “principal feature[]” of the Project but locates it just outside the “project boundary” and the license does not list it explicitly among the “project works,” although there is a residual clause for “appurtenant works.” J.A. 233, 239. The record is therefore unclear on whether Back Dam is part of the project license. Even if it is not, Aclara forfeited any argument that FERC lacks the authority to require removal of a structure that is not part of a project’s license as a condition of license surrender by not raising the issue in its brief. See, e.g., Wash. Legal Clinic for the Homeless v. Barry, 107 F.3d 32, 39 (D.C. Cir. 1997) (a litigant does not argue an issue by raising it only in “cursory fashion”). 4 a penstock to connect the canal to the powerhouse and a powerhouse containing turbines to generate electricity. The reservoir extends 0.8 miles upstream from Stone Dam and Back Dam is 0.3 miles downstream of Stone Dam. Water not diverted to the powerhouse is released into the river downstream of Stone Dam, known as the “bypass reach,” and water is released at around the same rates as the river’s natural flow to protect fish and wildlife. The Project has not generated power since a penstock failure in 2011 so that all water flows into the bypass reach.

There are fifteen functioning dams on the Salmon Falls River, and Stone and Back Dams are respectively the fifth and fourth from the mouth of the river. Three other FERC-licensed projects with dams are downstream of the Project: Lower Great Falls, Rollinsford and South Berwick. Green Mountain Power Corporation (Green Mountain) operates all three downstream projects. Relicensing of the Lower Great Falls and Rollinsford Projects in 2022 and 2023 included conditions for fish passage. Specifically, Green Mountain had to either construct permanent fishways at both projects—so fish can swim around the dams and migrate upstream—or build a “trap and truck” facility at South Berwick to transport fish for release upstream, bypassing the Rollinsford, Lower Great Falls and Somersworth Projects. Ultimately, on May 1, 2024 Green Mountain chose the trap-and-truck option and thus fishways will not be built at Rollinsford or Lower Great Falls in the foreseeable future.

Stone Dam was built in 1929 and Back Dam likely dates from around the same time. FERC licensed the Project to General Electric (GE) for 40 years in 1981 to power a manufacturing plant on site. In 2016, Aclara obtained the license after buying the plant and Project facilities from GE. Aclara initially intended to fix the penstock and restart the 5 Project but abandoned those plans after determining that it would be unprofitable to do so.

The FPA authorizes FERC to regulate the licensing of hydropower projects on “navigable waters of the United States.” 16 U.S.C. § 817(1); S.D. Warren Co. v. Me. Bd. of Env’t Prot., 547 U.S. 370, 373 (2006). An existing license may be “surrendered only upon mutual agreement between the licensee and the Commission.” 16 U.S.C. § 799; see also 18 C.F.R. § 6.2. To initiate surrender, a licensee must file an application stating the reasons for surrender, 18 C.F.R. § 6.1, and FERC may impose “conditions” that the licensee must fulfill before surrender is complete, including with respect to decommissioning any project works that have been built, id. § 6.2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
125 F.4th 1139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-whitewater-v-ferc-cadc-2025.