Rio Grande Pipeline Co. v. Federal Energy Regulatory Commission

178 F.3d 533, 336 U.S. App. D.C. 229, 1999 U.S. App. LEXIS 11775, 1999 WL 362832
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 8, 1999
Docket98-1194
StatusPublished
Cited by48 cases

This text of 178 F.3d 533 (Rio Grande Pipeline Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rio Grande Pipeline Co. v. Federal Energy Regulatory Commission, 178 F.3d 533, 336 U.S. App. D.C. 229, 1999 U.S. App. LEXIS 11775, 1999 WL 362832 (D.C. Cir. 1999).

Opinion

Opinion for the Court filed by Chief Judge HARRY T. EDWARDS.

HARRY T. EDWARDS, Chief Judge:

Rio Grande Pipeline Company (“Rio Grande”) purchased 194 miles of an existing refined products pipeline from the Na *535 vajo Pipeline Company (“Navajo”) to deliver natural gas liquids (“NGLs”) from the United States to Mexico. In exchange for the pipeline, Rio Grande paid Navajo an agreed sum of money and granted Navajo Southern, Inc., a wholly owned subsidiary of Navajo, a minority interest in Rio Grande. In the proceeding under review, Rio Grande sought to include the purchase price of the pipeline in its rate base. Normally, a purchaser such as Rio Grande is only permitted to include the seller’s depreciated original cost in its eost-of-ser-vice calculations; however, Rio Grande pointed out that this transaction was different, because the pipeline was purchased for a new use and the purchase price was less than the cost of constructing a comparable facility. Rio Grande therefore contended that it should be permitted to include the full purchase price of the pipeline in its rate base under the so-called “benefits exception” to the original cost rule. The Federal Energy Regulatory Commission (“FERC” or “Commission”)' denied Rio Grande’s request, holding that the benefits exception can never be employed when the seller acquires an equity interest in the purchasing entity. Rio Grande petitions for review of this ruling, claiming that FERC’s decision is flatly at odds with the benefits rule and that the agency’s judgment defies reason.

Before turning to the merits, we must first resolve three threshold issues: (1) whether Longhorn Partners Pipeline (“Longhorn”) is a proper intervenor in the matter now before the court, (2) whether Rio Grande has been “aggrieved” by the contested orders, and (3) whether the contested orders are ripe for review. With these threshold issues resolved, we then reach the question of whether FERC’s rejection of Rio Grande’s request to include the full purchase price of the pipeline in its rate base was arbitrary and capricious.

On the record at hand, we conclude that Longhorn is not a proper intervenor in this action, because it does not have standing. Indeed, it appears that Longhorn is really seeking to participate as an amicus. Pursuant to our discretion under Rule 29(a) of the Federal Rules of Appellate Procedure, we will accord Longhorn amicus status so that its views on the common issues can be considered. We also conclude that Rio Grande is an aggrieved party, because it faces real and present economic injury as a result of the orders here in dispute. Likewise, because FERC’s disputed policy is fully crystallized and raises a concrete legal question, we find that petitioner’s claim is ripe for review by this court. Finally, on the merits, we conclude that FERC’s refusal to apply the benefits exception in the present case was arbitrary and capricious for lack of an adequate justification. Accordingly, we grant Rio Grande’s petition for review.

I. BACKGROUND

Rio Grande is a partnership formed by two pipeline companies, Juarez Pipeline Company and Amoco Rio Grande Pipeline Company, to construct and maintain an integrated common carrier pipeline to deliver NGLs from the United States to Mexico. As a part of this project, Rio Grande sought to purchase 194 miles of an existing refined products pipeline from Navajo, which would then be converted to NGL service. According to Rio Grande, Navajo’s willingness to sell this segment of pipeline “at a reasonable price was directly dependent on its ability to acquire a partnership interest in our project.” Statement of William C. Lawson, Management Committee Chairman, Rio Grande, reprinted in Joint Appendix (“J.A.”) 61. Accordingly, in exchange for the pipeline, Rio Grande agreed to pay an agreed sum of money to Navajo as well as grant Navajo Southern, Inc., a wholly owned subsidiary of Navajo, a minority partnership interest in Rio Grande. Rio Grande asserts, without contradiction, that the price paid for the pipeline, including the value of the partnership interest and the cost of converting and integrating the acquired line, *536 is at least $8 million less than the cost of constructing a comparable new line. See id.

Rio Grande then sought to justify the rates for its new service. Under 18 C.F.R. § 342.2, pipelines may justify an initial rate for new service using one of two methods: the carrier may either (1) file cost, revenue, and throughput data supporting the proposed rate pursuant to § 342.2(a), or (2) file.a sworn statement that the proposed rate is agreed to by at least one non-affiliated person who intends to use the service, pursuant to § 342.2(b). Rates justified under § 342.2(b) are simple to put into place, and often become effective without a FERC order addressing them. However, these rates are ineffective if a protest to the initial rate is filed, in which case the carrier must seek a § 342.2(a) justification. Moreover, if a negotiated rate is challenged and a lower rate is found appropriate, the pipeline may have to pay reparations for the amount overcharged. In contrast, a cost supported rate approved under § 342.2(a) is entitled to greater protection. For example, if á challenge is brought to a cost-supported, Commission-approved rate and a reduction is required, that reduction is given only prospective effect. See generally Arizona Grocery Co. v. Atchison, Topeka & Santa Fe Ry. Co., 284 U.S. 370, 387-89, 52 S.Ct. 183, 76 L.Ed. 348 (1932).

In this case, Rio Grande filed a petition for a declaratory order, requesting approval of its initial rates. In its petition, Rio Grande noted that a non-affiliated party, Petróleos Mexicanos (“PEMEX”), had agreed to the proposed initial rate of $1.26 per barrel and, thus, the rates could be justified under § 342.2(b). However, Rio Grande made clear that it was not requesting FERC approval of a negotiated rate under § 342.2(b):

[WJhether one or twenty “non-affiliated persons” agree to its to-be-filed rate, [Rio Grande] is not assured that it will be able to justify its “initial rate,” if challenged, unless it has the Commission’s approval to include its acquisition costs. Regardless of a consignee or shipper’s prior agreement to the rate, [Rio Grande’s] proposed tariff may be protested. In the event of a protest to a negotiated rate, [Rio Grande] would have to submit “cost, revenue and throughput data supporting such rate” and incur the cost of a lengthy rate proceeding. 18 C.F.R. § 342.2(a) (1995). Accordingly, [Rio Grande] also submits this Petition to establish its rate base and prejustify its rates.

In re Rio Grande Pipeline Co., Verified Petition for Declaratory Order (Oct. 7, 1996), reprinted in J.A. 8 (footnote omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Whitewater v. FERC
125 F.4th 1139 (D.C. Circuit, 2025)
Abd Al-Rahim Hussein Al-Nashiri
47 F.4th 820 (D.C. Circuit, 2022)
Natural Res. Def. Council v. Envtl. Prot. Agency
896 F.3d 459 (D.C. Circuit, 2018)
Lower E. Side People's Fed. Credit Union v. Trump
289 F. Supp. 3d 568 (S.D. Illinois, 2018)
King v. Christie
981 F. Supp. 2d 296 (D. New Jersey, 2013)
State National Bank of Big Spring v. Geithner
958 F. Supp. 2d 127 (District of Columbia, 2013)
Canning v. National Labor Relations Board
705 F.3d 490 (D.C. Circuit, 2013)
North Dakota v. Heydinger
288 F.R.D. 423 (D. Minnesota, 2012)
Gon v. Gonzales
534 F. Supp. 2d 118 (District of Columbia, 2008)
Cnstltn Engy v. FERC
D.C. Circuit, 2006

Cite This Page — Counsel Stack

Bluebook (online)
178 F.3d 533, 336 U.S. App. D.C. 229, 1999 U.S. App. LEXIS 11775, 1999 WL 362832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rio-grande-pipeline-co-v-federal-energy-regulatory-commission-cadc-1999.