Electricity Consumers Resource Council v. Federal Energy Regulatory Commission

407 F.3d 1232, 366 U.S. App. D.C. 36, 2005 U.S. App. LEXIS 8442
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 13, 2005
DocketNo. 03-1449
StatusPublished
Cited by15 cases

This text of 407 F.3d 1232 (Electricity Consumers Resource Council v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electricity Consumers Resource Council v. Federal Energy Regulatory Commission, 407 F.3d 1232, 366 U.S. App. D.C. 36, 2005 U.S. App. LEXIS 8442 (D.C. Cir. 2005).

Opinion

Opinion for the Court filed by

Circuit Judge ROGERS.

ROGERS, Circuit Judge.

The Electricity Consumers Resource Council (“ELCON”) challenges two orders of the Federal Energy Regulatory Commission approving a rate design for the installed capacity market administered by the New York Independent System Operator, Inc. (“NYISO”). See N.Y. Indep. Sys. Operator, Inc., 2003 WL 21155022, 103 F.E.R.C. ¶ 61,201 (2003) (“Initial Order”); NY Indep. Sys. Operator, Inc., 2003 WL 22422351, 105 F.E.R.C. ¶ 61,108 (2003) [38]*38(“Rehearing Order”). While maintaining that the Commission’s orders violate both the “just and reasonable” ratemaking standard of the Federal Power Act (“FPA”), 16 U.S.C. § 824d(a) (2000), and the arbitrary and capricious standard of the Administrative Procedure Act (“APA”), 5 U.S.C. § 706(2)(A) (2000), ELCON urges a heightened standard of review for “incentive ratemaking” requiring the Commission to demonstrate that the rate increase is no more than necessary to achieve its purpose of encouraging investment in new generation facilities in New York State. Because we conclude that the rate design does not impose an incremental rate increase above traditional cost-based rates but rather seeks to stabilize rates to promote the development and retention of installed capacity, there is no basis for applying a heightened standard of review. Upon applying the usual APA standard, we conclude that the Commission’s approval of the rate design is supported by substantial evidence in the record and is not otherwise arbitrary and capricious. Accordingly, we deny the petition for review.

I.

To prevent electricity shortages during periods of peak demand, the New York State Reliability Council required retail utilities, known as load serving entities (“LSEs”), to purchase installed capacity (“ICAP”) equal to 118% of their peak loads. See Initial Order, 103 F.E.R.C. ¶ 61,201, at 61,750. If an LSE failed to procure the required amount of ICAP through its own supply or through bilateral contracts, it was required to purchase the deficient quantity through NYISO auctions, at which the price equaled a “deficiency charge” of $255 per kilowatt-year, or three times the annualized cost of installing a new “peaker” power plant. See id. This rate design resulted in a vertical demand curve for ICAP, with the price equal to $255 for all quantities up to 118%, and $0 for all quantities exceeding 118%. See id. & fig.l. According to NYISO, the vertical demand curve caused extreme volatility in ICAP prices, thus discouraging investment in new generation facilities and creating “the potential for a capacity deficiency” in New York State. Id. at 61,751.

[[Image here]]

[39]*39To address this problem, NYISO applied to the Commission for approval of amendments to its tariff to incorporate a new rate design replacing the vertical demand curve with a sloped “ICAP Demand Curve,” which would be used in monthly-auctions to determine both the quantity and price of required ICAP. See id For 118% of peak load, the price would equal the annualized cost of a new peaker plant. See id As supply increased above 118%, the price would gradually decrease until it reached zero for 132% of peak load, and as supply decreased below 118%, the price would gradually increase until it reached a maximum of two times the annualized cost of a new peaker plant. See id & fig.2.

Figure 2: Sloped ICAP Demand Curve

Each month, capacity suppliers, including LSEs with excess capacity, would bid into an ICAP auction and create the supply curve; the point of intersection between the supply curve and the ICAP Demand Curve would determine the quantity and price of required ICAP. See id at 61,752. If the monthly auction yielded a quantity less than 118% of peak load, NYI-SO would purchase the deficient amount outside the auction market and charge each LSE a “supplemental supply fee” equal to 1.5 times the annualized cost of a new peaker plant. See id at 61,753. NY-ISO also proposed a “periodic independent review of the Demand Curve every three years to determine whether adjustments are warranted.” Id

ELCON, which represents industrial consumers of electricity, intervened and protested the new rate design, arguing that it would increase electricity prices for consumers without spurring investment in new generation capacity, and that it violated incentive ratemaking case law because the ICAP Demand Curve was not carefully calibrated to increase investment in new generation facilities without granting a windfall to existing capacity suppliers. The Commission approved NYISO’s rate design with modifications, finding that it would “benefit customers because it [would] provide better price signals to investors for construction of new generation, encourage the formation of long-term bilateral transactions, and reduce incentives to withhold capacity.” Id at 61,750. The [40]*40Commission agreed with NYISO that the ICAP Demand Curve would “encourage greater investment in generation capacity and thus improve reliability, by reducing the volatility of ICAP revenues,” and concluded that it would “provide net benefits especially compared with the existing vertical demand curve.” Id. at 61,753-54. The Commission eliminated the supplemental supply fee based on the concern that suppliers would withhold capacity from the monthly ICAP auction in order to sell capacity at the higher price of the supplemental supply fee. See id. at 61,-761. Characterizing the ICAP Demand Curve as “a novel proposal” requiring “some measure of judgment” in setting the specific parameters, and observing that it “will be important to evaluate and monitor the appropriateness of these parameters after some experience is gained,” the Commission required NYISO to file “a detailed evaluation of the Demand Curve and its implementation by December 1, 2003, and annually for two years thereafter.” Id. at 61,754. The Commission denied ELCON’s petition for rehearing and approved NYI-SO’s proposal to set the supplemental supply fee equal to the monthly ICAP auction price. See Rehearing Order, 105 F.E.R.C. ¶ 61,108, at 61,625. This petition for review followed.

II.

The court ordinarily reviews the Commission’s orders to determine whether they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); see Pub. Utils. Comm’n v. FERC, 254 F.3d 250, 253-54 (D.C.Cir.2001). Such review is limited to whether the Commission has “examine[d] the relevant data and ai'ticulate[d] a satisfactory explanation for its action, including a ‘rational connection between the facts found and the choice made.’ ” Motor Vehicle Mfrs. Ass’n v. State Farm Mutual Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (quoting Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168, 83 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
407 F.3d 1232, 366 U.S. App. D.C. 36, 2005 U.S. App. LEXIS 8442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electricity-consumers-resource-council-v-federal-energy-regulatory-cadc-2005.