PJM Power Providers Group v. Federal Energy Regulatory Commission

880 F.3d 559
Court of Appeals for the D.C. Circuit·Decided January 26, 2018·No. 15-1453 Consolidated with 15-1455·Published·Cited by 3 cases

Opinion

GARLAND,. Chief Judge:

Congress has given the Federal Energy Regulatory Commission (FERC) authority to regulate the transmission and sale at wholesale of.electric energy in interstate commerce. 16 U.S.C. § 824 (a), (b). FERC tasks certain non-profit entities, known as regional transmission organizations, with managing the transmission of electricity over the electric grid and ensuring that energy is reliably available for consumers. 18 C.F.R. § 35.34 ; see Advanced Energy Mgmt. Alliance v. FERC, 860 F.3d 656 , 659 (D.C. Cir. 2017). One such regional transmission organization is PJM Interconnection, LLC, which has responsibility for administering a tariff that determines the rates paid to energy providers for providing electric capacity- in the broad mid-Atlantic region. 1 See Advanced Energy, 860 F.3d at 659-60 . FERC, in turn, must ensure that PJM Interconnection’s tariff is “just and reasonable.” 16 U.S.C. § 824d(a).

This case concerns one element of PJM Interconnection’s 2014 tariff revisions: the estimated cost of new entry, which approximates .the revenue that a newly constructed power generator would need to recoup its costs. Through a complicated methodology, which we fortunately, need not test the reader’s patience by explaining again, the cost of new entry affects the prices paid to energy providers for electric capacity. See TC Ravenswood, LLC v. FERC, 741 F.3d 112 , 114-15. (D.C. Cir. 2013); see also N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74 , 84-87 (3d Cir. 2014). The petitioners in this .case—PJM Power Providers Group, a coalition of energy providers, and the PSEG Companies, a public *562 utility holding company and its subsidiaries—challenge FERC’s orders approving PJM Interconnection’s tariff. See 149 FERC ¶ 61 , 183 (Nov. 28, 2014) (Initial Order); 153 FERC ¶ 61,035 (Oct. 15, 2015) (Rehearing Order). In- the petitioners’ view, the cost of new entry submitted by PJM Interconnection and approved by FERC is too low. Consequently, they argue, the resulting price that they are paid for wholesale capacity is also too low. And this, they say, means that the PJM Interconnection tariff that FERC- approved is not just and reasonable.

I

We -review FERC’s orders under the Administrative Procedure Act, asking whether they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” Braintree Elec. Light Dep’t v. FERC, 667 F.3d 1284 , 1288 (D.C. Cir. 2012) (quoting 5 U.S.C. § 706 (2)(A)). The Commission’s factual findings) “if supported by substantial evidence,” are “conclusive;” 16 U.S.C. § 8251 (b).

The petitioners acknowledge that “[t]he questions posed here are purely factual issues,” and they challenge FERC’s orders solely oh the ground that they are unsupported by substantial evidence.' Petitioners’ Reply Br. 4. Our review in these circumstances is “highly deferential, as issues of rate design are fairly technical and, insofar as they are not technical, involve policy judgments that lie at the core of the regulatory mission.” Alcoa Inc. v. FERC, 564 F.3d 1342 , 1347 (D.C. Cir. 2009) (internal quotation marks and citation omitted).As the Supreme Court has made clear, our role is “not to ask whether a regulatory decision is the best one possible or even whether it is better than the alternatives.” FERC v. Elec. Power Supply Ass’n, — U.S.-, 136 S.Ct. 760 , 782, 193 L.Ed.2d 661 (2016). Instead,- we must “affirm the Commission’s orders so long as FERC examined the relevant data and articulated a rational connection between the facts found and the. choice made.” Alcoa, 564 F.3d at 1347 (internal quotation marks and citation omitted); see Elec. Power Supply Ass’n, 136 S.Ct. at 782 .

Having examined them in detail, we conclude that none of the petitioners’ objections to the cost-of-new-entry figure'that FERC approved can overcome our deferential standard of review.

Free access — add to your briefcase to read the full text and ask questions with AI

PJM Power Providers Group v. Federal Energy Regulatory Commission, 880 F.3d 559 (D.C. Cir. 2018).

880 F.3d 559 (PJM Power Providers Group v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Entergy Arkansas, LLC v. FERC
134 F.4th 576 (D.C. Circuit, 2025)
Delaware Division of the Public Advocate v. FERC
3 F.4th 461 (D.C. Circuit, 2021)
El Paso Natural Gas Company, LLC v. FERC
966 F.3d 842 (D.C. Circuit, 2020)