Delaware Division of the Public Advocate v. FERC

3 F.4th 461
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 9, 2021
Docket20-1212
StatusPublished
Cited by9 cases

This text of 3 F.4th 461 (Delaware Division of the Public Advocate v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaware Division of the Public Advocate v. FERC, 3 F.4th 461 (D.C. Cir. 2021).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued April 6, 2021 Decided July 9, 2021

No. 20-1212

DELAWARE DIVISION OF THE PUBLIC ADVOCATE, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

PJM INTERCONNECTION, L.L.C., INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Casey A. Roberts argued the cause for petitioners. With her on the briefs were Kim Smaczniak, Regina A. Iorii, Paula M. Carmody, William F. Fields, Joseph G. Cleaver, Karen R. Sistrunk, and Anjali G. Patel.

Carol J. Banta, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were David L. Morenoff, Acting General Counsel, and Robert H. Solomon, Solicitor. 2 Paul M. Flynn argued the cause for intervenor PJM Interconnection, LLC in support of respondent. With him on the brief was Ryan J. Collins.

Paul W. Hughes, David G. Tewksbury, and Matthew A. Waring were on the brief for amicus curiae PJM Power Providers Group in support of respondent.

Before: SRINIVASAN, Chief Judge, HENDERSON and PILLARD, Circuit Judges.

Opinion for the Court filed by Circuit Judge HENDERSON.

KAREN LECRAFT HENDERSON, Circuit Judge: The Federal Energy Regulatory Commission (Commission) approved PJM Interconnection, LLC’s (PJM) proposed revisions to its capacity market auction mechanism, which is designed to determine the price and amount of electric capacity. The Delaware Division of the Public Advocate, Maryland Office of People’s Counsel, the Office of the People’s Counsel for the District of Columbia and Sierra Club (Petitioners) challenge the Commission’s approval of two elements of that mechanism. We deny the petition in part, grant the petition in part and remand without vacatur.

I. BACKGROUND

The Federal Power Act (Act) gives the Commission jurisdiction of the transmission and wholesale of electric energy in interstate commerce. 16 U.S.C. § 824(b). The Act requires that “[a]ll rates and charges . . . for or in connection with” such transmission or sale be “just and reasonable.” Id. § 824d(a). Under Section 205 of the Act, if a utility seeks to change any rate or charge, it must file notice of the proposed changes with the Commission. Id. § 824d(d). 3 PJM is a regional transmission organization (RTO) that manages an electric grid covering all or part of thirteen Mid-Atlantic and Midwestern states and the District of Columbia. As an RTO, PJM “promot[es] efficiency and reliability in the operation and planning of the electric transmission grid.” 18 C.F.R. § 35.34(a). To promote reliability and prevent service interruptions, PJM must “ensur[e] that its system has sufficient generating capacity.” Md. Pub. Serv. Comm’n v. FERC, 632 F.3d 1283, 1284 (D.C. Cir. 2011) (per curiam).

PJM ensures sufficient generating capacity through its “capacity market.” Capacity is not “actual electricity” but instead “a commitment to produce electricity or forgo the consumption of electricity when required.” Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 659 (D.C. Cir. 2017) (per curiam). To establish the capacity market, PJM conducts a yearly auction in which electricity suppliers submit offers to be available to provide capacity during a one-year period, three years in the future. Suppliers offer a specific amount of capacity at a specific price and together the offers comprise the auction’s “supply curve.” The auction utilizes an administratively-set “demand curve”—the Variable Resource Requirement Curve (VRR Curve)—which represents the prices that consumers should pay for varying quantities of capacity. The intersection of the two curves dictates the amount of capacity committed and the price suppliers are paid.

The VRR Curve is set based on several inputs. The Reliability Requirement input is the amount of capacity that must be produced to meet peak demand, including a reserve margin, which together are intended to allow no more than one power outage every decade. The “net cost of new entry” input (net CONE) is how much revenue a hypothetical new generator—referred to as the “Reference Resource”—would 4 need to earn in the capacity market to justify construction. In other words, the net CONE is an estimate of the revenue the Reference Resource cannot recover from other markets1 and thus needs to recover from the capacity market to recoup its construction costs. To set the net CONE, PJM selects a type of electric generation technology to serve as the Reference Resource and estimates two values, one of which is subtracted from the other: (1) an estimate of the cost to install and operate a Reference Resource (i.e., the gross cost of new entry), minus (2) an estimate of revenues from PJM’s “energy and ancillary services” markets (EAS Revenue Estimate). The Reference Resource affects the net CONE estimate, which in turn positions the VRR Curve, whose intersection with the supply curve determines the price and amount of capacity.

PJM must review the VRR Curve every four years. For the 2018 review, PJM hired The Brattle Group (Brattle) to review the VRR Curve and Brattle eventually produced two reports. As relevant here, Brattle suggested PJM change its Reference Resource from a combustion turbine plant—the Reference Resource since the inception of the capacity market—to a combined cycle turbine plant. Despite making that

1 PJM operates several “‘markets’ for the wholesale sale of electricity and other related products.” Advanced Energy, 860 F.3d at 659. For example, the “electricity market” is the real-time supply of electricity “in which generators sell actual power to retailers.” TC Ravenswood, LLC v. FERC, 741 F.3d 112, 114 (D.C. Cir. 2013). A “capacity market,” on the other hand, is a market for the future supply of electricity. Id. The suppliers’ offers are commitments to provide future electricity and are utilized if utilities “need more electricity in order to meet consumer demand.” Advanced Energy, 860 F.3d at 660. When the utilities need more electricity to meet demand, “PJM calls on resources with a capacity commitment” and “[c]apacity resources must provide their committed share of the needed electricity.” Id. 5 recommendation, Brattle acknowledged the rationale for choosing a “[combustion turbine]-based curve if PJM and stakeholders are highly risk-averse about ever procuring less than the target reserve margin.” Joint Appendix (J.A.) 127 (Brattle Curve Report). On October 12, 2018, pursuant to Section 205 of the Federal Power Act, PJM filed several proposed revisions to the capacity market. Among the revisions, PJM proposed keeping a combustion turbine plant as its Reference Resource2 and proposed an update to the EAS Revenue Estimate by increasing the value of the Reference Resource’s estimated offer to supply energy in the energy market by 10% (10% adder). The Petitioners intervened to oppose these two proposals. On April 15, 2019, the Commission accepted PJM’s proposed revisions as just and reasonable. PJM Interconnection, LLC, 167 FERC ¶ 61,029 (2019). The Petitioners requested rehearing but, on April 16, 2020, the Commission denied rehearing and affirmed its order in all relevant respects. PJM Interconnection, LLC, 171 FERC ¶ 61,040 (2020).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Energy Consumers of America v. FERC
125 F.4th 1156 (D.C. Circuit, 2025)
PJM Power Providers Group v. FERC
96 F.4th 390 (Third Circuit, 2024)
Vistra Corp. v. FERC
80 F.4th 302 (D.C. Circuit, 2023)
Constellation Mystic Power v. FERC
45 F.4th 1028 (D.C. Circuit, 2022)
LSP Transmission Holdings II, LLC v. FERC
45 F.4th 979 (D.C. Circuit, 2022)
Xcel Energy Services Inc. v. FERC
41 F.4th 548 (D.C. Circuit, 2022)
California Public Utilities Commission v. FERC
20 F.4th 795 (D.C. Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
3 F.4th 461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-division-of-the-public-advocate-v-ferc-cadc-2021.