Industrial Energy Consumers of America v. FERC

125 F.4th 1156
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 14, 2025
Docket23-1334
StatusPublished
Cited by3 cases

This text of 125 F.4th 1156 (Industrial Energy Consumers of America v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Energy Consumers of America v. FERC, 125 F.4th 1156 (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued November 14, 2024 Decided January 14, 2025

No. 23-1334

INDUSTRIAL ENERGY CONSUMERS OF AMERICA, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

ITC MIDWEST LLC, INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Kenneth R. Stark argued the cause for petitioners. With him on the briefs were Robert A. Weishaar, Jr., James Harrison Holt, and Katherine Ann Wade.

Jason T. Perkins, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. 2 Aaron M. Streett argued the cause for intervenor ITC Midwest LLC in support of respondent. With him on the brief were Jay Ryan, J. Mark Little, and Christopher E. Tutunjian.

Before: HENDERSON and PAN, Circuit Judges, and ROGERS, Senior Circuit Judge.

Opinion for the Court by Senior Circuit Judge ROGERS.

Concurring opinion by Circuit Judge HENDERSON.

ROGERS, Senior Circuit Judge: Petitioners seek review of the grant of an abandonment incentive to ITC Midwest, LLC (“ITC”). The Federal Energy Regulatory Commission approved the first of two stages of the rate incentive in the event a planned transmission project is abandoned for reasons beyond ITC’s control. Because petitioners fail to show imminent injury as a result of this action, they lack Article III standing and the court must dismiss the petition for lack of jurisdiction.

I.

To induce new investment in energy infrastructure, Congress enacted the Energy Policy Act of 2005, which amended the Federal Power Act (“FPA”) and required the Commission to adopt rules for “incentive-based . . . rate treatments for the transmission of electric energy.” 16 U.S.C. § 824s(a). In 2006 the Commission adopted Order No. 679, which establishes eight categories of incentives for public utilities. Promoting Transmission Inv. Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 at PP 76–77, 163– 67 (2006) (“Order 679”), on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006) (“Order 679-A”). To qualify for an incentive, the utility first must show (1) “the facilities for which 3 it seeks incentives either ensure reliability or reduce the cost of delivered power by reducing transmission congestion,” (2) there is a nexus between the total package of incentives and the utility’s ability to address the risks or challenges it faces, and (3) “the resulting rates are just and reasonable.” Order 679 at P 76; Order 679-A at P 27.

One incentive is the abandonment incentive that allows a utility to recover 100% of its prudently incurred costs in transmission rates for projects abandoned due to factors beyond the utility’s control. Order 679 at PP 155, 163, 166; San Diego Gas & Elec. Co. v. FERC, 913 F.3d 127, 132 (D.C. Cir. 2019). A utility must first obtain a declaratory order from the Commission establishing its eligibility for the incentive and then obtain the Commission’s approval for a specific rate increase to recover those costs “prudently incurred . . . after the effective date of the order.” San Diego Gas & Elec., 913 F.3d at 133, 137–39. Only then may a utility increase its rates. “[T]o ensure that rate cases are manageable, the Commission presumes that all expenditures are prudent so the utility need not justify in its case-in-chief the prudence of all of its costs.” Potomac-Appalachian Transmission Highline, LLC, 158 FERC ¶ 61,050 at P 100 (2017). Of course, the incentives must be “tailored to address the demonstrable risks or challenges faced by the applicant.” 18 C.F.R. § 35.35(d). The Commission proceeds by case-by-case adjudication. Order 679 at PP 43, 164; Promoting Transmission Inv. Through Pricing Reform, Policy Statement, 141 FERC ¶ 61,129 at PP 6–10 (2012) (“Policy Statement”).

ITC submitted a request for an abandonment incentive on May 30, 2023, for the Iowa portion of the Skunk River-Ipava 345 kV Long-Range Transmission Plan Project. Request 1; see 16 U.S.C. § 824d; Order 679; Policy Statement. This is one portion of a transmission project crossing several states that 4 was approved by Midcontinent Independent System Operator, Inc. (“MISO”). Pursuant to its open access tariff and the Iowa Right of First Refusal statute (“Iowa ROFR”), MISO assigned the Iowa portion of the project (“Project”) to ITC. ITC is to own and construct the Project, which is to become operational in 2029.

In requesting an abandonment incentive, ITC stated that the Project would satisfy each of Order 679’s requirements. The Project would “enhance reliability” and “reduce congestion” because it is one of several transmission projects that together would “address 600 thermal violations associated with 77 unique monitored facilities.” Request 4–5. It also would “[i]ncrease transfer capability” and “[e]nhance the resilience of the grid” while “[r]educ[ing] loading.” Id. at 5. Further, the Project “satisfies the Commission’s nexus test because the challenges faced . . . are significant and the Abandonment Incentive sought is appropriately tailored to address” regulatory and environmental, financial, and construction risks. Id. at 6; see Test. of Jeffrey W. Eddy, Dir. of Plan., ITC Holdings Corp. 8–11 (May 30, 2023). And ITC stated that its rates “will be just and reasonable” because it cannot collect abandonment costs until it makes a filing “demonstrating the prudence of the costs for which recovery is sought.” Request 8.

Petitioners are the Resale Power Group of Iowa, the Industrial Energy Consumers of America, the Coalition of MISO Transmission Customers, and the Wisconsin Industrial Energy Group. They are a collection of organizations whose members purchase electricity at rates that could be affected by the disputed incentive. They filed a protest opposing the abandonment incentive on the ground that ITC’s ownership of the Project was “uncertain” and likely “void” due to ongoing litigation challenging the Iowa ROFR. Protest 11. 5

On August 8, 2023, the Commission granted ITC’s request for the abandonment incentive. Order on Transmission Rate Incentive, ITC Midwest, LLC, 184 FERC ¶ 61,083 at P 43 (2023) (“Incentive Order”). Finding that the Project is entitled to the rebuttable presumption that it will “enhance reliability and/or reduce congestion,” id. at P 16, the Commission concluded that ITC had “demonstrated that the Project faces certain regulatory, environmental, and siting risks that are beyond ITC[’s] control . . . and that approval of the . . . Incentive will address those risks,” id. at P 43. The Commission rejected petitioners’ protest that ongoing state court litigation called into question ITC’s ability to proceed with the Project “free and clear of any legal impediments.” Protest 12. The litigation challenged the Iowa ROFR under which MISO assigned the Project to ITC. The Commission, citing its precedent, stated that “[t]he presence of regulatory or litigation uncertainty does not preclude . . . granting” an abandonment incentive in an adjudication. Incentive Order at P 44 & n.77 (citing Order 679 at PP 163–65; NextEra Energy Transmission Sw., LLC, 180 FERC ¶ 61,032 at PP 8, 18–19 (2022); Pioneer Transmission, LLC, 126 FERC ¶ 61,281 at P 49 (2009), order on reh’g & clarification, 130 FERC ¶ 61,044 at P 58 (2010)). The Commission also stated that it “will address the prudence of any costs incurred if and when ITC . . . makes a filing under section 205 seeking recovery of such costs, and . . . any . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
125 F.4th 1156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-energy-consumers-of-america-v-ferc-cadc-2025.