New Jersey Board of Public Utilities v. Federal Energy Regulatory Commission

744 F.3d 74
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 20, 2014
Docket11-4245, 11-4405, 11-4486, 11-4487, 12-1085, 12-1086, 12-1764
StatusPublished
Cited by22 cases

This text of 744 F.3d 74 (New Jersey Board of Public Utilities v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Jersey Board of Public Utilities v. Federal Energy Regulatory Commission, 744 F.3d 74 (3d Cir. 2014).

Opinion

OPINION

RENDELL, Circuit Judge:

In what is a relatively unusual task for our court, we are asked to review a ruling of the Federal Energy Regulatory Commission (“FERC”) approving a revised tariff submitted by PJM Interconnection, LLC, that effectively changes several aspects of PJM’s tariff as approved in a prior FERC order. FERC is the independent federal agency tasked under the Federal Power Act (the “FPA”) with, among other things, ensuring that rates charged by public utilities for the transmission and sale of energy in interstate commerce, and the “rules and regulations affecting or pertaining to such rates”, are “just and reasonable.” 16 U.S.C. § 824d.

In 2006, FERC issued an order (the “2006 Order”) approving a new tariff — a set of rules and policies governing the interstate sale of electricity and electric capacity — for the PJM market, a vast region covering thirteen states and the District of Columbia. The terms and policies embodied in the 2006 Order — the result of an extensively negotiated settlement between power providers, utility companies, state and local authorities and other stakeholders in the region — sought to ensure the existence of sufficient power generation facilities to meet the needs of the PJM market. To this end, the order required that load serving entities (LSEs) in the PJM market procure a certain amount of energy capacity — that is, additional generation resources that the market may access during times of peak load. The 2006 Order also contained rules designed to curb the ability of market participants to distort wholesale prices through the exercise of market power. A chief means to that end was the rule that offers for the sale of capacity in the PJM markets at artificially low prices would, with some notable exceptions, be required to be “mitigated”, or raised to a competitive level, based on their costs.

Beginning in April 2011, FERC issued three orders (the “2011 Orders”) that altered the terms of the 2006 Order in several ways, some substantial. Among other things, the 2011 Orders eliminated an exemption from mitigation for resources built pursuant to a state mandate. In addition, the 2011 Orders eliminated a provision that had guaranteed that LSEs that owned their own generation resources, or had procured capacity through bilateral contracts, would be able to use this “self-supply” to satisfy their own capacity obligations. The 2011 Orders also changed several factors used in determining whether a particular offer was subject to mitigation.

As discussed infra, multiple parties have timely filed Petitions for Review of the 2011 Orders. 1 Petitioners New Jersey and *80 Maryland contend that the 2011 Orders amount to direct regulation of power facilities in violation of the FPA, and that FERC acted arbitrarily and capriciously in eliminating the exemption from mitigation for state-mandated resources. Similarly, several municipal and cooperative electric utilities challenge FERC’s elimination of the assurance that LSEs could uge their own self-supply to satisfy their capacity obligations. Finally, various energy providers take issue with new rules governing the calculation of a resource’s net cost of new entry, which is used in determining whether an offer for the sale of capacity will be mitigated, and with FERC’s determination that a new generation resource must clear only one capacity auction in order to avoid further mitigation. We have considered these arguments and find them without merit. Accordingly, we deny the petitions for review.

I.

At the time the FPA was passed in 1935, “most electricity was sold by vertically integrated utilities that had constructed their own power plants, transmission lines, and local delivery systems. Although there were some interconnections among utilities, most operated as separate, local monopolies subject to state or local regulation.” New York v. FERC, 585 U.S. 1, 5, 122 S.Ct. 1012, 152 L.Ed.2d 47 (2002). In 1927 the Supreme Court held in Public Utilities Commission v. Attleboro Steam & Electric Co., 273 U.S. 83, 47 S.Ct. 294, 71 L.Ed. 549 (1927), that only Congress, and not the states, could regulate the sale of electrical power in interstate commerce. To meet this charge, Congress enacted the FPA, which authorized federal regulation of the interstate sale of electricity, and created a new independent agency, the Federal Power Commission (precursor to FERC), to administer the statute. New York, 535 U.S. at 6-7, 122 S.Ct. 1012. Section 201 of the FPA defined the Commission’s jurisdiction as “the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce.... ” 16 U.S.C. § 824(a). The statute gave the Commission regulatory power over “all facilities for such transmission or sale of electric energy”, but withheld jurisdiction over “facilities used for the generation of electric energy” which remained subject to state and local regulation. § 824(b)(1). Section 205 tasked the Commission with ensuring that “[a]ll rates and charges made, demanded or received by any public utility for or in connection with the transmission or sale of electric energy ... and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable,” and prohibited utilities engaged in the transmission or sale of energy in interstate commerce from “mak[ingj or granting] any undue preference or advantage to any person or subjecting] any person to any undue prejudice or disadvantage, or [ ] maintaining] any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.” § 824d. Section 206 gave the Commission the power to correct rates, or “any rule, regulation, practice, or contract *81 affecting such rate[s]” that it deemed unjust and unreasonable. § 824e(a).

In the nearly eight decades since the FPA was enacted, technological advances have revolutionized the way electric power is generated and transmitted. Transmission grids are now largely interconnected, which means that “any electricity that enters the grid immediately becomes a part of a vast pool of energy that is constantly moving in interstate commerce.” New York, 535 U.S. at 7, 122 S.Ct. 1012. In addition to making the transfer of electricity over long distances more efficient, the development of a national, interconnected grid has made it possible for a generator in one state to serve customers in another, thus opening the door to potential competition that did not previously exist. Id. at 8, 122 S.Ct. 1012. Public utilities still retain ownership over transmission lines, however, and so, until recently, had the ability to stifle competition from new generators by “refus[ing] to deliver energy produced by competitors or [by] delivering] competitors’ power on terms and conditions less favorable than those they apply to their own transmissions.” Id. at 8-9, 122 S.Ct. 1012.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vistra Corp. v. FERC
80 F.4th 302 (D.C. Circuit, 2023)
DuPage v. Butler
C.D. Illinois, 2023
Delaware Division of the Public Advocate v. FERC
3 F.4th 461 (D.C. Circuit, 2021)
Dishman v. King
C.D. Illinois, 2019
Maine v. Federal Energy Regulatory Commission
854 F.3d 9 (D.C. Circuit, 2017)
Hughes v. Talen Energy Marketing, LLC
578 U.S. 150 (Supreme Court, 2016)
PPL EnergyPlus, LLC v. Lee Solomon
766 F.3d 241 (Third Circuit, 2014)
PPL EnergyPlus, LLC v. Nazarian
753 F.3d 467 (Fourth Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
744 F.3d 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-jersey-board-of-public-utilities-v-federal-energy-regulatory-ca3-2014.