Old Dominion Electric Cooperative, Inc. v. Federal Energy Regulatory Commission

518 F.3d 43, 380 U.S. App. D.C. 167, 2008 U.S. App. LEXIS 4382, 2008 WL 540228
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 29, 2008
Docket06-1326, 06-1331
StatusPublished
Cited by13 cases

This text of 518 F.3d 43 (Old Dominion Electric Cooperative, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Old Dominion Electric Cooperative, Inc. v. Federal Energy Regulatory Commission, 518 F.3d 43, 380 U.S. App. D.C. 167, 2008 U.S. App. LEXIS 4382, 2008 WL 540228 (D.C. Cir. 2008).

Opinion

Opinion for the Court filed by Chief Judge SENTELLE.

SENTELLE, Chief Judge:

CED Rock Springs, LLC (“Rock Springs”) and Old Dominion Electric Cooperative (“Old Dominion”) (together, “Petitioners”) petition for review of a Federal Energy Regulatory Commission (“FERC” or “the Commission”) order rejecting their rate filings under section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d. They also petition for review of FERC’s *46 order denying their request for rehearing. Because we conclude that the Commission adequately explained its decision to deny Petitioners’ rate filings and its decision was not unduly discriminatory, we deny their petition for review.

I. Background

In 1998, Petitioner Old Dominion began planning the construction and development of a natural gas-fired combustion turbine generating facility to be located in Rising Sun, Maryland. The facility is now complete and consists of four generation units- — two owned by Old Dominion and two by Petitioner Rock Springs — and transmission facilities consisting of a 500 kV substation and two 900-foot 500 kV transmission lines jointly owned by Petitioners. Petitioners connected their generators to the electrical grid first by running radial lines from their generators to the substation. They then looped their two 900-foot transmission lines from the substation to a 500 kV transmission line owned by PECO Energy Company (“PECO”). Electricity flows freely from other generation facilities through PECO’s transmission lines, and subsequently, through Petitioners’ substation and two 900-foot lines. Electricity produced by Petitioners’ generators only flows out from the generators onto the transmission grid via the radial lines that connect their generators to the substation. In other words, Petitioners’ substation and two looped 900-foot 500 kV lines are fully integrated in the electrical grid; Petitioners’ generators are not.

PJM Transmission System (“PJM”) is a regional, interconnected transmission grid composed of transmission and generation facilities owned by Petitioners, PECO, and others. All owners of generation and transmission facilities in the PJM Transmission System are parties to the PJM Interconnection L.L.C. Open Access Transmission Tariff (“Tariff’). The Tariff establishes the rates, terms, and conditions of service for transmission services over the PJM Transmission System. The Tariff also requires an Interconnection Customer, a generator that needs to connect to the PJM Transmission System,

to pay for 100 percent of the costs of the minimum amount of ... Network Upgrades necessary to accommodate its Interconnection Request and that would not have been incurred ... but for such Interconnection Request, net of benefits resulting from the construction of the upgrades, such cost not to be less than zero.

Tariff § 37.2.

During construction of the Rock Springs and Old Dominion generating facilities, Petitioners submitted an Interconnection Request as set forth in the Tariff for PECO to connect their generators to the PJM Transmission System. PECO indicated to Petitioners that it would be unable to build the interconnection facilities on the schedule that they preferred, so instead of waiting for PECO to build the facilities, they opted to build them themselves. Petitioners then began construction on the 500 kV substation and two 900-foot 500 kV lines that now connect their generators to the PJM Transmission System. If PECO had built the interconnection facilities, the Tariff would have allocated the cost to Petitioners minus any benefit to the PJM Transmission System, and PECO would have owned the interconnection facilities. Tariff § 37.2; id. § 40.1 (“Except to the extent otherwise provided in a Construction Service Agreement entered into pursuant to Subpart F below, the Transmission Owners shall own all Attachment Facilities, Local Upgrades, and Network Upgrades constructed to accommodate Interconnection Requests.”). *47 However, Petitioners built the interconnection facilities themselves, so they each own a one-half share in the substation and 1,800 feet of transmission line, making them Transmission Owners (“TOs”). Because Petitioners are TOs and not simply owners of generation facilities, in addition to being parties to the Tariff, they are also parties to the Transmission Owners’ Agreement (“TOA”).

Prior to signing the TOA, the relationship between PJM and Petitioners was governed by a Facilities Operation Agreement (“FOA”), a contract written to address Petitioners’ unique position as both generation owners and TOs. Because Petitioners wanted to preserve their status as Exempt Wholesale Generators (“EWGs”) under the Public Utility Holding Company Act of 1935 (“PUHCA”), 15 U.S.C. §§ 79a et seq., repealed by the Energy Policy Act of 2005, Pub.L. No. 109-58, 119 Stat. 594, the FOA included a provision that waived their right to receive any revenue that “PJM may collect for transmission services for which PJM may use the Facility....” FOA § 5.1.5. But other TOs were not satisfied with the FOA, so the parties modified the TOA to allow Rock Springs and Old Dominion to opt out of cost recovery. The modified TOA gives each party “the right at any time unilaterally to file pursuant to Section 205 of the Federal Power Act to change the revenue requirements underlying its rates for providing services under the PJM Tariff.” TOA § 2.2.1. The next sentence addresses Petitioners’ EWG concerns and gives each party “the unilateral right to adopt a revenue requirement of zero and to forgo any right or claim to compensation for providing transmission services under the PJM Tariff or any other document.” Id. (emphasis added). Section 2.2 of the TOA states that “[n]ot-withstanding any other provision of this Agreement, or any other agreement or amendment made in connection with the restructuring of PJM, each individual Party shall retain all of the rights set forth in this Section 2.2.... ”

Later FERC orders and the repeal of the Public Utility Holding Company Act of 1935 assuaged Petitioners’ concerns about their EWG status. As a result, Rock Springs and Old Dominion filed petitions with FERC to recover operating and management expenses, depreciation expenses, property taxes, and return on equity for their substation and 1,800 feet of transmission line. Old Dominion Elec. Coop., Filing of Transmission Revenue Requirement Rate Application and Tariff Revisions, at 6, Docket No. ER06-497-000 (Jan. 17, 2006). These figures represent “the portion of plant costs attributable to the two 900-foot transmission lines and related 500 kV substation,” along with operating expenses for these facilities. CED Rock Springs, LLC, Filing of Transmission Revenue Requirement Rate Application and Tariff Revisions, at 8, Docket No. ER06-497-000 (Jan. 17, 2006).

FERC rejected Petitioners’ rate filings in full. CED Rock Springs, LLC, et al., 114 FERC ¶ 61,285 (Mar. 17, 2006) (“Order Rejecting Rate Filings ”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
518 F.3d 43, 380 U.S. App. D.C. 167, 2008 U.S. App. LEXIS 4382, 2008 WL 540228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/old-dominion-electric-cooperative-inc-v-federal-energy-regulatory-cadc-2008.