Pioneer Trail Wind Farm, LLC v. Federal Energy Regulatory Commission

798 F.3d 603, 2015 U.S. App. LEXIS 14552, 2015 WL 4927002
CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 19, 2015
Docket13-2326, 14-3023
StatusPublished
Cited by9 cases

This text of 798 F.3d 603 (Pioneer Trail Wind Farm, LLC v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pioneer Trail Wind Farm, LLC v. Federal Energy Regulatory Commission, 798 F.3d 603, 2015 U.S. App. LEXIS 14552, 2015 WL 4927002 (7th Cir. 2015).

Opinion

WOOD, Chief Judge.

Before deciding to build a power plant, energy companies and the system operator of an electrical grid must calculate the anticipated cost of connecting the proposed plant to the grid. These determinations occur in a highly regulated environment. Not surprisingly, sometimes the calculations need to be corrected. This case deals with who should bear the costs of additional upgrades to the grid when the initial studies of the costs of connection contained an error. Two wind-farm companies argue that the Federal Energy Regulatory Commission (FERC or the Commission) issued unreasoned orders when it assigned the corrected costs of connection to the wind farms that wanted to connect to the grid rather than to the grid’s system operator, which was the party that made the mistake. Our task is to decide whether the Commission’s decisions to impose the costs on the connecting parties and to require a certain methodology were arbitrary and capricious under Section 706(2)(A) of the Administrative Procedure Act, 5 U.S.C. § 706(2)(A). We conclude that the Commission’s decisions pass muster, and thus we deny the petitions for review. ^

I

Pioneer Trail Wind Farm, LLC (Pioneer), owns and operates a 150-m.egawatt wind-powered electric generation facility in Illinois. Settlers Trail Wind Farm, LLC (Settlers), owns a similarly sized facility, also in Illinois. Both Pioneer and Settlers are owned by companies that are in turn owned by a German company called E.ON SE. (The “SE” stands for “societas europaea,” which is the term given to companies that register under the European Union’s European Company Statute rather than under national law. See EUROPEAN COMM’N, The European Company— Your Business Opportunity?, http://ec. europa.eu/internal_market/company/ societas-europaea/index_en.htm, (all websites last visited Aug. 12, 2015).) Accord *606 ing to E.ON’s website, its power companies serve 33 million customers worldwide. See E.ON, Who We Are. An Overview., http://www.eon.com/en/about-us/profile. html. We often refer to Pioneer and Settlers collectively as the Generators in this opinion.

Midcontinent Independent System Operator, Inc. (MISO), was formed in 1998 by several independent transmission-owning utilities. Since its creation, MISO has linked up the transmission lines of the member utilities into a single interconnected grid that stretches across 11 states. The Generators wish to be connected to the transmission system of Ameren Illinois Company (Ameren), which is run by MISO. Ameren oversees 4,500 miles of electric transmission lines and approximately 45,400 miles of distribution lines in downstate Illinois; it serves roughly 1.2 million customers in Illinois.

In order to put the questions before us in context, some background on the interconnection process is essential. In layman’s terms, we are talking about the regulatory hoops that a power plant must jump through in order to hook up to a grid. The Federal Power Act grants FERC jurisdiction to oversee “matters relating to generation ... and ... the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce” because Congress has found such oversight to be “necessary in the public interest.” 16 U.S.C. § 824(a). In 2003, FERC standardized the generation interconnection process, to which we reluctantly refer as the GIP, following the industry jargon. Under the GIP, the interconnection customers, such as Pioneer and Settlers, submit requests to the grid operator — in this case, MISO. MISO then produces studies to assess the impact of the projects on the grid. These studies identify what additional upgrades are needed to ensure that those additional connections do not adversely affect the grid. These studies also inform interconnection customers what the cost of the upgrades will be. This step is supposed to enable the customers to decide if, in fact, they want to be connected to the grid or perhaps even build the plants at all. The interconnection customers cover the cost of MISO’s studies.

Each case involves three separate studies. First, the grid operator prepares and sends to the interconnection customers the “base case,” which gives them an overview of the system conditions. Second, the grid operator prepares a “system impact study,” which includes a preliminary list (with non-binding cost estimates) of network upgrades required by the proposed project. At this point, the customers may choose whether to proceed. If they go forward, MISO performs the third study, called an “interconnection facilities study.” This sets out the nature and cost of the necessary network upgrades, as well as any information about pending upgrades that are entered into MISO’s interconnection queue. If another project is entered before the customer’s project, then the second customer could end up bearing the costs of the earlier project. That is because projects higher in the queue are included in the baseline against which the lower-queued project is assessed.

If the interconnection customer chooses to proceed in light of these studies, the grid operator provides the customer and the interconnecting transmission system owner with a Generator Interconnection Agreement (Agreement), which the parties must execute. The Agreement contains the specific upgrades and estimated costs identified in the studies. Once the parties execute the Agreement, it is effective under Section 205 of the Federal Power Act. See 16 U.S.C. § 824d.

*607 With that background, we detail the specific process that took place here between the interconnection customers — the Generators — and the grid’s system operator, MISO. In February 2009, MISO and Ameren entered a “study services agreement” in which Ameren agreed to perform the studies of the impact of the Generators’ interconnection requests. Pioneer and Settlers signed their Agreements on February 5, 2010, with projects scheduled to begin in June and September of 2011. The Settlers Agreement included roughly $6 million in network upgrades, while Pioneer’s Agreement required no network upgrades.

Everything was apparently proceeding smoothly until April 29, 2010, when MISO notified the Generators that the studies included a “significant error” that failed to include upgrades to a higher-queued project in the vicinity of the two companies’ proposed wind farms. The inadvertently omitted project was a 30-megawatt upgrade to another wind farm in Benton County. MISO told the Generators that something had to give: they would either have to agree to fewer megawatts (120 megawatts each) or pay for additional network upgrades estimated to cost $11.5 million. On May 11, 2010, the Generators informed MISO that they rejected both options: the additional network upgrades, they asserted, were not their responsibility, and so they claimed they were entitled to proceed with their 150-megawatt wind farms.

MISO did not acquiesce in their position. Instead, in November 2010, it informed both companies that they would need to pay for $10 million in additional network upgrades and $1.5 million in common use upgrades before they could interconnect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
798 F.3d 603, 2015 U.S. App. LEXIS 14552, 2015 WL 4927002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pioneer-trail-wind-farm-llc-v-federal-energy-regulatory-commission-ca7-2015.