Michigan Electric Transmission Company, LLC v. FERC

141 F.4th 1296
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 1, 2025
Docket24-1039
StatusPublished

This text of 141 F.4th 1296 (Michigan Electric Transmission Company, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Electric Transmission Company, LLC v. FERC, 141 F.4th 1296 (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 17, 2025 Decided July 1, 2025

No. 24-1039

MICHIGAN ELECTRIC TRANSMISSION COMPANY, LLC, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

MICHIGAN PUBLIC POWER AGENCY, ET AL., INTERVENORS

Consolidated with 24-1084

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Aaron M. Streett argued the cause for petitioner. With him on the briefs were Jay Ryan, J. Mark Little, and Christopher E. Tutunjian.

Robert M. Kennedy, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General 2 Counsel, at the time the brief was filed, and Robert H. Solomon, Solicitor. Angela X. Gao, Trial Attorney, entered an appearance.

Debra D. Roby argued the cause for intervenors for respondent. With her on the brief were Michael J. Rustum, Alan I. Robbins, and Thomas B. Steiger III. Neil H. Koslowe entered an appearance.

Before: WALKER, Circuit Judge, and EDWARDS and GINSBURG, Senior Circuit Judges.

Opinion for the Court filed by Senior Circuit Judge GINSBURG.

GINSBURG, Senior Circuit Judge: Petitioner Michigan Electric Transmission Company (METC) owns a high-voltage transmission line jointly with two other transmission companies, the Michigan Public Power Agency (MPPA) and the Wolverine Power Supply Cooperative. This case involves ownership of new transmission facilities — referred to as “network upgrades” — that will connect a new solar generation park to the transmission line. The question is which company will own the new facilities, and whether certain existing agreements with the operator of the regional transmission system or among the companies provide the answer. METC claims each agreement grants it exclusive ownership of the network upgrades; MPPA and Wolverine claim no agreement grants METC that exclusive ownership.

The Federal Energy Regulatory Commission held no agreement identified by METC conclusively determined ownership rights and therefore declined to decide the question of ownership. Because we agree with the Commission’s inter- 3 pretation of the relevant agreements, we deny METC’s peti- tions for review.

I. Background

The Midcontinent Independent System Operator (MISO) runs the electricity transmission system in portions of 15 midwestern and southern states. METC, Wolverine, and MPPA are “Transmission Owners” (TOs) in the MISO system, which means they have conveyed functional control of their transmission facilities (in whole or in part) to MISO. See Midcontinent Open Access Transmission Tariff (MISO Tariff), § 1.T, https://perma.cc/8MPS-HWVB. MISO TOs sign a Transmission Owners Agreement (TOA) under which the TO “retains ownership and physical control over [its] facilities, but operates them according to MISO’s instructions.” Wis. Pub. Power, Inc. v. FERC, 493 F.3d 239, 248 (D.C. Cir. 2007) (cleaned up).

Under MISO’s tariff, all customers pay a “single rate to use the entire MISO transmission system, based upon the volume of power the customer carries on the system.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1365 (D.C. Cir. 2004) (cleaned up). MISO’s TOA and tariff operate alongside certain contracts signed prior to the creation of MISO — referred to as Grandfathered Agreements (GFAs) — between TOs and other utilities. See MISO Tariff, Attach. P (listing the GFAs). Certain of those agreements, including the GFAs relevant to this case, are “carved out” of the tariff, meaning they are not subject to most tariff requirements. See id. §§ 1.C, 1.G (defining “Carved Out GFA(s)” and “Grandfathered Agreement(s)”); §§ 38.8.4–38.8.4.7 (setting out the terms by which carved-out GFAs must abide); Wis. Pub. Power, Inc., 493 F.3d at 253–55. 4 A. The Network Upgrade Process

When a generator of electricity (referred to as an Interconnection Customer) in MISO’s service area seeks to bring its power to market, it submits a request to interconnect to the MISO transmission grid. MISO then analyzes the request and determines whether any network upgrades are needed to ensure that the new connection does not harm the grid. MISO sends to the Interconnection Customer and the affected TO(s) a pro forma Generator Interconnection Agreement (GIA) that identifies the specific upgrades required and their estimated cost. See Pioneer Trail Wind Farm, LLC v. FERC, 798 F.3d 603, 606 (7th Cir. 2015).

The parties negotiate over the appendices to the pro forma GIA, which in this case address, among other issues, the ownership of the network upgrades and the reimbursement of construction costs. Once executed, the GIA becomes effective. If negotiations reach an impasse, however, then any party “may request to end negotiations,” after which MISO will submit the unexecuted GIA to the Commission to resolve the disputed issues. MISO Tariff, Attach. X, § 11.2; see also Standardization of Generator Interconnection Agreements and Procedures, 104 FERC ¶ 61,103, at ¶¶ 233–235, 296 (2003).

In this case, Eagle Creek Solar Park LLC is developing a 120-megawatt (MW) solar generation facility that will provide power to MISO’s grid. MISO determined that interconnection with the grid will require the construction of network upgrades, which will connect the solar park to the grid by way of an existing line known as Styx-Murphy. See Figure 1 (denoting the solar park in green and the Styx-Murphy line in fuschia). 5 Figure 1: Network Upgrades for Palomino Line

The Styx-Murphy line is jointly owned by METC (1%), MPPA (35%), and Wolverine (64%). MPPA and Wolverine acquired their ownership interests in 1992 through separate GFAs with Consumers Energy Company as part of an antitrust settlement to remedy Consumers’s market power in the supply of bulk power in Lower Michigan. See Belle River Transmission Ownership and Operating Agreement Between Consumers Power Company and the Michigan Public Power Agency (MPPA Agreement), Dec. 1, 1982, App. 197–362; Wolverine Transmission Ownership and Operating Agreement Between Consumers Power Company and Wolverine Power Supply Cooperative, Inc. (Wolverine Agreement), July 27, 1992, App. 364–412. In 2020 METC acquired its ownership interest in the line from Consumers. We shall refer to the agreements collectively as the Styx-Murphy Agreements. 6 B. The Ownership Provisions

Negotiations over the proposed GIA for the Eagle Creek solar park include determining which of METC, MPPA, and Wolverine will own what network upgrades, if any. Per METC, three pre-existing agreements purportedly govern those negotiations. The first is the TOA: Appendix B, § VI (herein- after “§ VI”) provides that

(i) ownership and the responsibility to construct facilities which are connected to a single Owner’s system belong to that Owner . . . (ii) ownership and the responsibilities to construct facilities which are connected between two (2) or more Owners’ facilities belong equally to each Owner, . . . and (iii) ownership and the responsibility to construct facilities which are connected between an Owner(s)’ system and a system or systems that are not part of MISO belong to such Owner(s) unless the Owner(s) and the non- MISO party or parties otherwise agree[.]

The meaning of this provision is at the core of the parties’ dispute.

The other two are the Styx-Murphy Agreements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Zahn v. KROGER CO. OF MICHIGAN
764 N.W.2d 207 (Michigan Supreme Court, 2009)
WO BARNES CO., INC. v. Folsinski
60 N.W.2d 302 (Michigan Supreme Court, 1953)
El Paso Natural Gas Company v. United States
750 F.3d 863 (D.C. Circuit, 2014)
Oklahoma Gas and Electric Company v. FERC
11 F.4th 821 (D.C. Circuit, 2021)
In re Shorenstein Hays-Nederlander Theatres LLC
213 A.3d 39 (Supreme Court of Delaware, 2019)
Loper Bright Enterprises v. Raimondo
603 U.S. 369 (Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
141 F.4th 1296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-electric-transmission-company-llc-v-ferc-cadc-2025.