Cage Ranch Solar, LLC v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedMay 19, 2026
Docket23-1227
StatusUnpublished

This text of Cage Ranch Solar, LLC v. FERC (Cage Ranch Solar, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cage Ranch Solar, LLC v. FERC, (D.C. Cir. 2026).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 23-1227 September Term, 2025 FILED ON: MAY 19, 2026

CAGE RANCH SOLAR, LLC AND CAGE RANCH SOLAR II, LLC, PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

SOUTHWEST POWER POOL, INC., INTERVENOR

Consolidated with 23-1304

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Before: KATSAS and PAN, Circuit Judges, and GINSBURG, Senior Circuit Judge.

JUDGMENT

These petitions for review were considered on the record from the Federal Energy Regulatory Commission and on the briefs and oral arguments of the parties. The Court has accorded the issues full consideration and has determined that they do not warrant a published opinion. See D.C. Cir. R. 36(d). It is now

ORDERED AND ADJUDGED that the petitions for review be DISMISSED.

* * *

Cage Ranch Solar, LLC and Cage Ranch Solar II, LLC (collectively, “Cage Ranch”) petition for review of orders of the Federal Energy Regulatory Commission denying Cage Ranch’s complaint and request for a waiver. Before the FERC, Cage Ranch argued that Intervenor Southwest Power Pool, Inc. used a fundamentally flawed study model to assign network upgrade costs to Cage Ranch. Cage Ranch also argued the FERC should waive the deadline by which Southwest required Cage Ranch to post financial security to maintain its position in Southwest’s interconnection queue. Before us, Cage Ranch argues the FERC failed to ensure the costs assigned to it were just and reasonable and was otherwise arbitrary and capricious. We conclude that Cage Ranch has failed to show it suffered an injury necessary to establish its standing, and we accordingly dismiss the petitions.

I

Cage Ranch is the developer of a 900 MW solar generation project in Texas. In 2017, in order to connect its project to the electrical grid, Cage Ranch submitted interconnection requests to Southwest, a regional transmission organization. Southwest’s interconnection study process is cluster-based and involves three phases. Following Phase 1 and Phase 2 is a “decision point,” during which an interconnection customer must decide whether to post the required financial security. Failure to do so within 15 business days results in withdrawal of the customer’s interconnection request and loss of its position in the interconnection queue. At Decision Point 2, the amount of financial security an interconnection customer must post is 20% of the network upgrade costs assigned to that customer by the interconnection study, less the amount of any security that customer has already provided.

Southwest assigned Cage Ranch’s interconnection requests to Group 5 of the 2017-002 study cluster. Southwest posted Phase 1 results for this group in February 2022, preliminarily assigning $302 million in network upgrade costs to Cage Ranch. As required by Southwest’s Tariff, Cage Ranch paid $4.19 million in financial security and proceeded to Phase 2. In August 2022, Southwest posted Phase 2 results, which allocated $311 million in network upgrade costs to Cage Ranch. Cage Ranch would have had to post approximately $60 million by September 20, 2022 to proceed to Phase 3.

Rather than post the $60 million, on September 20, 2022 Cage Ranch filed a complaint with the FERC challenging Southwest’s Phase 2 cost-allocation model as defective. Because Southwest’s Tariff treats the failure timely to post financial security as a withdrawal, Cage Ranch also sought a waiver of the deadline and withdrawal provisions in the Tariff while the FERC considered its challenge. The FERC denied both Cage Ranch’s complaint and its request for a waiver of the deadline and withdrawal provisions in the Tariff, and confirmed that result in an order addressing Cage Ranch’s arguments raised on rehearing.

II

Under the Federal Power Act, a party “aggrieved” by an order of the FERC may seek judicial review of that order. 16 U.S.C. § 825l(b). “A party is aggrieved if it makes the same showing of injury that suffices to establish standing under Article III of the Constitution of the

2 United States.” Mich. Elec. Transmission Co. v. FERC, 141 F.4th 1296, 1302 (D.C. Cir. 2025) (cleaned up). In order to establish its standing, “A plaintiff must show (1) an injury in fact, (2) fairly traceable to the challenged conduct of the defendant, (3) that is likely to be redressed by the requested relief.” FEC v. Cruz, 596 U.S. 289, 296 (2022).

In a case involving direct review of agency action, the petitioner’s “burden of production” to establish its standing “is the same as that of a plaintiff moving for summary judgment.” Entergy Ark., LLC v. FERC, 134 F.4th 576, 580 (D.C. Cir. 2025) (cleaned up). “The petitioner must therefore either point to record evidence sufficient to support its standing or submit additional evidence making that showing”; failure to do so “requires dismissal of the action.” Id. (cleaned up). If, however, a petitioner’s standing to seek review is self-evident from the administrative record, then that obviates the need for separate proof of standing. See Sierra Club v. EPA, 292 F.3d 895, 899–900 (D.C. Cir. 2002); see also Sorenson Commc’ns, LLC v. FCC, 897 F.3d 214, 226 (D.C. Cir. 2018).

III

Our standing inquiry begins, and in this case ends, with the injury-in-fact requirement. In its opening brief, Cage Ranch suggests it suffered economic harm because a favorable ruling would “reduce the costs Cage Ranch was originally assigned by millions of dollars.” In fact, however, Cage Ranch has not shown that it incurred any monetary loss, nor does it face imminent costs because it has no active interconnection request before Southwest. ∗ The only potentially cognizable injury Cage Ranch can claim, therefore, is the loss of its position in the queue.

Neither the FERC nor Southwest challenged Cage Ranch’s standing in their principal briefs. During oral argument, however, the court explored both standing and mootness at length. In particular, counsel for Cage Ranch fielded questions regarding whether Cage Ranch’s claimed injury was self-inflicted when it decided not to post the financial security required by Southwest’s Tariff in order to maintain its queue position. See Nat’l Fam. Plan. & Reprod. Health Ass’n v. Gonzales, 468 F.3d 826, 831 (D.C. Cir. 2006) (“[S]elf-inflicted harm doesn’t satisfy the basic requirements for standing. Such harm does not amount to an ‘injury’ cognizable under Article III”). We ordered supplemental briefing on these jurisdictional issues.

In its opening supplemental brief, Cage Ranch argued only that it was injured by its loss of position in the queue. Cage Ranch asserts that, because of the substantial backlog in interconnection requests, “losing a queue position effectively kills a project.” Additionally, citing Orangeburg v. FERC, 862 F.3d 1071, 1077–78 (D.C. Cir. 2017), it claims it was denied the opportunity “to connect to the grid ‘on its desired terms’ — i.e., based on the queue position it

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Cage Ranch Solar, LLC v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cage-ranch-solar-llc-v-ferc-cadc-2026.