San Diego Gas & Elec. Co. v. Fed. Energy Regulatory Comm'n

913 F.3d 127
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 15, 2019
Docket16-1433
StatusPublished
Cited by11 cases

This text of 913 F.3d 127 (San Diego Gas & Elec. Co. v. Fed. Energy Regulatory Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Diego Gas & Elec. Co. v. Fed. Energy Regulatory Comm'n, 913 F.3d 127 (D.C. Cir. 2019).

Opinion

Dissenting opinion filed by Senior Circuit Judge Randolph.

Pillard, Circuit Judge:

*130 Petitioner San Diego Gas & Electric Company (SDG&E) seeks review of a Federal Energy Regulatory Commission (FERC or Commission) declaratory order applying FERC's cancelled or abandoned electricity transmission facilities incentive, 18 C.F.R. § 35.35 (d)(1)(vi) (Abandonment Incentive), only prospectively, to investment that had yet to occur. FERC grants the Abandonment Incentive to qualifying transmission infrastructure projects to facilitate financing by assuring that ratepayers may be charged for the project if it is abandoned for reasons beyond the utility's control. Id . SDG&E's application acknowledged that the utility had already obtained needed investment and proceeded with the project for four years "without assurance of cost recovery for these development costs." Pet. for Declaratory Order of San Diego Gas & Electric Company 16 (Sept. 23, 2015), Joint App'x (J.A.) 44. Reasoning that the role of the Abandonment Incentive is to facilitate investment by hedging abandonment risk, rather than to reward investments that would happen in any event, the Commission found that SDG&E had failed to establish the requisite nexus between the Abandonment Incentive and costs it already incurred before it obtained the declaratory order. SDG&E claims that the order's limitation to future costs is contrary to the Abandonment Incentive's terms and arbitrary and capricious. For the reasons that follow, we deny the petition.

I.

A. Regulatory Context

In an effort to bolster investment in "reliable and economically efficient" energy transmission infrastructure, Congress in 2005 amended the Federal Power Act (FPA), 16 U.S.C. § 792 et seq ., to require FERC to promulgate a rule to establish "incentive-based" rate treatments in order to "promot[e] capital investment" in projects to upgrade the electricity grid. Id. § 824s(a), (b)(1); see Energy Policy Act of 2005, Pub. L. No. 109-58, § 1241, 119 Stat. 961 (2005) (codified as amended at 16 U.S.C. § 824s ). Congress's express purpose in calling for such a rule was to "benefit[ ] consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion." 16 U.S.C. § 824s(a). In Congress's view, because such a rate-treatment rule would enable needed upgrades to infrastructure on which reliable and efficient electric service depends, it would ultimately benefit consumers, even as it also cost them. See id. Any rate FERC approves under the rule, Congress stipulated, must be "just and reasonable and not unduly discriminatory or preferential." Id . § 824s(d).

*131 The Commission adopted its Incentive Rule the following year, see Transmission Infrastructure Investment (Incentive Rule), 18 C.F.R. § 35.35 (2006), and refined it through two rehearing orders and a policy statement, see Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 (2006), order on reh'g , Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh'g , Order No. 679-B, 119 FERC ¶ 61,062 (2007) ; Promoting Transmission Investment Through Pricing Reform, 141 FERC ¶ 61,129 (2012) ( Policy Statement ).

The Incentive Rule establishes eight categories of incentive-based rate treatments for public utilities. 18 C.F.R. § 35.35 (d). Three prerequisites must be met by each applicant seeking any of those treatments:

The applicant must demonstrate [1] that the facilities for which it seeks incentives either ensure reliability or reduce the cost of delivered power by reducing transmission congestion consistent with the requirements of section 219 [of the Federal Power Act], [2] that the total package of incentives is tailored to address the demonstrable risks or challenges faced by the applicant in undertaking the project, and [3] that resulting rates are just and reasonable.

Id. The Rule invites an applicant to request a "package of incentives ... tailored" to its particular needs. Id. In so doing, the applicant must make its case for including in its rates each of the incentive-based rate treatments it requests. The Rule defines "incentive-based rate treatment" to mean any of the following:

(i) A rate of return on equity sufficient to attract new investment in transmission facilities;
(ii) 100 percent of prudently incurred Construction Work in Progress (CWIP) in rate base;
(iii) Recovery of prudently incurred pre-commercial operations costs;
(iv) Hypothetical capital structure;
(v) Accelerated depreciation used for rate recovery;
(vi) Recovery of 100 percent of prudently incurred costs of transmission facilities that are cancelled or abandoned due to factors beyond the control of the public utility;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michigan Electric Transmission Company, LLC v. FERC
141 F.4th 1296 (D.C. Circuit, 2025)
Industrial Energy Consumers of America v. FERC
125 F.4th 1156 (D.C. Circuit, 2025)
Hall v. Putnam County Commission
S.D. West Virginia, 2024
Citadel FNGE Ltd. v. FERC
77 F.4th 842 (D.C. Circuit, 2023)
Belmont Municipal Light Department v. FERC
38 F.4th 173 (D.C. Circuit, 2022)
International Transmission Company v. FERC
988 F.3d 471 (D.C. Circuit, 2021)
Williams v. Ross
District of Columbia, 2021
Baltimore Gas and Electric Company v. FERC
954 F.3d 279 (D.C. Circuit, 2020)
Kisor v. Wilkie
588 U.S. 558 (Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
913 F.3d 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-diego-gas-elec-co-v-fed-energy-regulatory-commn-cadc-2019.