Baltimore Gas and Electric Company v. FERC

954 F.3d 279
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 27, 2020
Docket18-1298
StatusPublished
Cited by12 cases

This text of 954 F.3d 279 (Baltimore Gas and Electric Company v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Gas and Electric Company v. FERC, 954 F.3d 279 (D.C. Cir. 2020).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued October 17, 2019 Decided March 27, 2020

No. 18-1298

BALTIMORE GAS AND ELECTRIC COMPANY, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

MARYLAND OFFICE OF PEOPLE’S COUNSEL AND MARYLAND PUBLIC SERVICE COMMISSION, INTERVENORS

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Matthew E. Price argued the cause and filed the briefs for petitioner.

Jared B. Fish, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were James P. Danly, General Counsel, and Robert H. Solomon, Solicitor.

Stephen C. Pearson argued the cause for intervenors. With him on the brief were Miles H. Mitchell, Ransom E. Davis, 2

Paula M. Carmody, William F. Fields, Joseph G. Cleaver, and Scott H. Strauss.

Before: HENDERSON and RAO, Circuit Judges, and WILLIAMS, Senior Circuit Judge.

Opinion for the Court filed by Senior Circuit Judge WILLIAMS with respect to Parts I, II, and IV.

Opinion for the Court filed by Circuit Judge RAO with respect to Part III.

Dissenting Opinion filed by Senior Circuit Judge WILLIAMS with respect to Part III.

WILLIAMS, Senior Circuit Judge: This case arises out of the Federal Energy Regulatory Commission’s effort to apply its “matching” principles to divergences between the timing of deductions for tax purposes and timing for purposes of allocating costs to ratepayers. While Congress and other bodies imposing taxes may want to allow early depreciation of an asset (to encourage investment), for example, the Commission wants a cost (less offsetting tax benefits) to be charged in the period over which the resulting asset provides services to the utility’s customers.

I.

In December 2016, Baltimore Gas and Electric Company (“BGE”) filed a new rate proposal with the Commission under § 205 of the Federal Power Act, 16 U.S.C. § 824d. The proposal sought a net recovery of approximately $38 million from future ratepayers relating to various costs incurred by BGE dating back to 2005. It is undisputed that consumers had not been charged for these costs between 2005 and the 2016 filing. 3

The relevant items are in fact a good deal more complicated than the accelerated depreciation example used above, but their details do not affect the issues before us. They arise from (1) a transition problem posed by a switch in Commission handling of such matters, (2) a change in tax rates, and (3) differences between ratemaking and tax treatments of the equity component of construction costs. The sums involved in the first and third categories totaled about $42 million, offset by about $4 million in the second (which BGE proposed to return to the ratepayers). FERC expects utilities to track these amounts according to Financial Accounting Standard 109 (“FAS 109”), a financial accounting and reporting standard promulgated by the not-for-profit Financial Accounting Standards Bureau intended to set forth recording requirements to facilitate “tax normalization,” i.e., resolution of timing differences exemplified by the matters discussed above. See FERC Br. 12; Accounting for Income Taxes, FERC Docket No. AI93-5-000 (Apr. 23, 1993) (“1993 Guidance”).

FERC denied BGE’s request to recover these amounts, declining to find BGE’s proposed rate “just and reasonable,” as required by § 205(a). Specifically, it found BGE’s request in violation of the procedural requirements that it had developed for implementation of the matching principle in this context and had stated in its order, Regulations Implementing Tax Normalization for Certain Items Reflecting Timing Differences in the Recognition of Expenses or Revenues for Ratemaking and Income Tax Purposes, Order No. 144, FERC Stats. & Regs. ¶ 30,254 (1981). Order No. 144 requires that any such adjustment “be made in the applicant’s next rate case following applicability of the rule.” Id. at ¶ 31,519. It also requires applicants “to begin the process of making up deficiencies in or eliminating excesses in their deferred tax reserves so that, within a reasonable period of time to be determined on a case- 4

by-case basis, they will be operating under a full normalization policy.” Id. at ¶ 31,560.

FERC concluded that BGE had breached the requirements of Order No. 144 by failing to file for recovery of these amounts in its “next rate case,” which, according to FERC, was BGE’s 2005 rate filing. Order Rejecting Proposed Tariff Revisions, PJM Interconnection, LLC, 161 FERC ¶ 61,163 (2017) (“Order”). On requests for clarification and rehearing, the Commission made clear its position that the “reasonable period of time” requirement of Order No. 144 “was intended to work in conjunction with the ‘next rate case’ requirement,” so that it does not “negate the requirement that applicants must seek recovery in their next rate case.” Order on Rehearing and Clarification, PJM Interconnection, LLC, 164 FERC ¶ 61,173, at P 18 (2018) (“Rehearing Order”).

Although neither party speaks directly to the issue, we take it that, for purposes of this case anyway, the “next rate case following applicability of the rule” is the “next rate case” after the utility has incurred an item (including either a cost or a benefit) requiring “normalization” under Order No. 144 and the 1993 Guidance, not counting periods in which a rate case or settlement had itself normalized the treatment of the item (or adequately addressed its normalization). Indeed, even though FERC denied recovery of such amounts for years past, its denial was without prejudice to BGE’s recovery of FAS 109 amounts properly allocable to future years, leaving open BGE’s opportunity to achieve normalization prospectively. See Rehearing Order at PP 37–38; see also FERC Br. 15.

BGE petitioned for review and claims that FERC’s application of Order No. 144 was arbitrary and capricious under the Administrative Procedure Act, 5 U.S.C. § 706(2)(A), misapplying the “next rate case” and “reasonable period of time” requirements. BGE also asserts that FERC erred in 5

failing to recognize BGE’s 2006 settlement of the 2005 rate case as an example of the sort of settlement briefly discussed in Order No. 144. That order had said that it left “undisturbed the ability of the parties to reach a settlement on any of the issues covered by the rule.” Order No. 144 at ¶ 31,519. BGE argues the settlement qualified under Order No. 144 and as a result preserved BGE’s ability to recover the FAS 109 amounts here at issue.

For the reasons developed below we find that FERC’s orders were not arbitrary and capricious and therefore deny the petition for review.

II.

We begin with the 2006 settlement agreement, which BGE claims preserved its right to recover FAS 109 amounts dating back to 2005. As BGE acknowledges, BGE Br. 32 n.5, we have long applied Chevron deference to FERC’s reasonable interpretations of settlement agreements it approves, Nat’l Fuel Gas Supply Corp. v. FERC, 811 F.2d 1563, 1569 (D.C. Cir. 1987), and we do so here. The question before us is whether FERC’s determination that BGE’s settlement agreement did not preserve FAS 109 amounts for recovery in a later rate case filing is “reasonable and reasonably explained,” Nw. Corp. v. FERC, 884 F.3d 1176, 1179 (D.C. Cir. 2018), which we answer in the affirmative. BGE’s arguments that FERC is wrong in its application of Order No. 144’s settlement provision are not convincing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
954 F.3d 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-gas-and-electric-company-v-ferc-cadc-2020.