Public Citizen, Inc. v. Federal Energy Regulatory Commission

839 F.3d 1165, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20170, 2016 U.S. App. LEXIS 19225, 2016 WL 6210707
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 25, 2016
Docket14-1244; 14-1246
StatusPublished
Cited by24 cases

This text of 839 F.3d 1165 (Public Citizen, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Citizen, Inc. v. Federal Energy Regulatory Commission, 839 F.3d 1165, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20170, 2016 U.S. App. LEXIS 19225, 2016 WL 6210707 (D.C. Cir. 2016).

Opinion

BROWN, Circuit Judge:

In this consolidated case, Petitioners Public Citizen and Connecticut seek review of two Notices issued by the Federal Energy Regulatory Commission as part of ISO New England’s eighth forward-capacity market. They contend we have jurisdiction because the Notices constitute either orders under the Federal Power Act or action unlawfully withheld under the Administrative' Procedure Act. We disagree and dismiss for lack of jurisdiction.

I.

ISO New England (“ISO-NE”) is a private, nonprofit entity that, among other things, administers New England’s energy markets. The Federal Energy Regulatory Commission (“FERC” or “the Commission”) is an independent agency composed of up to five members appointed by the President. See 42 U.S.C. § 7171(a)-(b). Among other responsibilities, FERC has the authority under the Federal Power Act (“the FPA”) to regulate rates for wholesale electricity. See 16 U.S.C. §§ 824d-824e. A forward-capacity market (“FCM”) is a particular type of wholesale market for electricity.

This case concerns whether FERC’s response to ISO-NE’s 2014 FCM auction (“FCA 8”) ran afoul of its FPA obligations. We therefore begin by surveying the relevant FPA provisions and describing the mechanics of an FCM auction.

A.

FPA Section 205(a) states all rates and charges—including those for wholesale electric energy—“shall be just and reasonable, and any such rate or charge that is not just and reasonable is hereby declared to be unlawful.” 16 U.S.C. § 824d(a).

Sections 205 and 206 provide two mechanisms through which FERC can fulfill its statutory charge of ensuring the justness and reasonableness of rates. Section 205 governs the lawfulness of proposed rates; Section 205(d) requires utilities to file all proposed changes with FERC, and, “unless the Commission otherwise orders^” filed rates cannot go into effect without “sixty days’ notice to the Commission and to the public.” Id. § 824d(d). Section 205(e) further authorizes FERC, “either upon complaint br upon its own initiative[,]” to hold hearings on the lawfulness of proposed rates. Id § 824d(e). “[Pjending such hearing,” it “may” also suspend the rates for up to “five months beyond the time when [they] would otherwise go into effect.” Id. Section 206 permits FERC to review—and third parties to challenge— rates that have already become effective. Id § 824e(a).

B.

In 2006, FERC approved a Settlement Agreement and Tariff permitting ISO-NE to conduct annual FCM auctions. See Devon Power LLC, 117 F.E.R.C. ¶ 61,133 (2006). The Settlement Agreement provides for “thorough review of the final auction clearing prices by the Commission” and any interested parties. Id. at P 93. It further states “[P]arties may challenge [proposed rates] under the ‘just and reasonable standard’ and the Commission will address such challenges under that standard.” Id

FCMs differ from other energy markets because “ ‘[c]apacity’ is not electricity itself but the ability to produce it when necessary. It amounts to a kind of call option that electricity transmitters purchase from parties—generally, generators—who can either produce more or consume less when required.” Conn. Dep’t of Pub. Util. Con *1168 trol v. Fed. Energy Regulatory Comm’n, 569 F.3d 477, 479 (D.C. Cir. 2009). ISO-NE’s FCMs are conducted three years in advance so as to encourage competition and market entry. See Blumenthal v. Fed. Energy Regulatory Comm’n, 552 F.3d 875, 879 (D.C. Cir. 2009). Thus, in an FCM, electricity providers do not purchase energy itself, but the option to buy a quantity of energy three years hence. See id.

In the annual FCM auctions—which set capacity prices—ISO-NE first determines the net amount of capacity required by the region. ISO New England, Inc,, 148 F.E.R.C. ¶ 61,201 at P 2 (2014). Suppliers willing to provide capacity submit bids reflecting the lowest price they will accept before exiting the market for that year. Id. In the ensuing “descending clock” auction, the price continues to fall and bidders continue to exit “until the amount of capacity remaining in the auction is equal to the net Installed Capacity Requirement,” Id. At this point, the auction terminates, and “all resources remaining in the auction receive capacity obligations at the auction clearing price.” Id. However, “[u]nder some circumstances relating primarily to the sufficiency of competition within the auction, [capacity prices] may be administratively determined by ISO-NE.” Id. at P 2 n.4.

ISO-NE conducted FCA 8 on February 3, 2014, On February 28, pursuant to its Tariff obligations, it filed the auction results with FERC for review under FPA Section 205, See Devon Power LLC, 117 F.E.R.C. ¶ 61,133 at P 78. Due to insufficient competition, the auction defaulted to administrative pricing rules, and it resulted in regional capacity price increases from approximately $1.2 billion to approximately $3 billion over one year.

On April 14, Petitioners filed a timely objection to the rates, 1 arguing they resulted from the unilateral exercise of market power. Subsequently, Petitioners each requested FERC affirmatively determine whether FCA 8’s rates were just and reasonable and assess whether the market was unduly manipulated during the auction. In response, on June 27, FERC issued ISO-NE a deficiency letter requesting additional information concerning the auction. ISO-NE provided the information on July 17.

Sixty-one days later, on September 16, 2014, FERC’s Secretary issued a Notice acknowledging the FCA 8 rates had become effective by operation of law pursuant to FPA Section 205. 2 Individual statements released by the Commissioners revealed FERC—which at the time was composed of only four Commissioners—had deadlocked about whether to approve the rates or set them for hearing. In a joint statement, two Commissioners concluded the Settlement Agreement required FERC to examine the reasonableness of the auction rates because evidence suggested FCA 8 had been influenced by the exercise of market power. The other two—one of whom was FERC’s current Chairperson—would have approved the rates. According to the Chairperson, as long as ISO-NE had conducted the auction in accordance with a FERC-approved tariff, the Commission lacked authority to assess justness or reasonableness.

*1169 Petitioners separately filed for rehearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

End Citizens United PAC v. FEC
90 F.4th 1172 (D.C. Circuit, 2024)
Campaign Legal Center v. Iowa Values
District of Columbia, 2023
Advanced Energy United, Inc. v. FERC
82 F.4th 1095 (D.C. Circuit, 2023)
Constellation Mystic Power v. FERC
45 F.4th 1028 (D.C. Circuit, 2022)
Public Citizen, Inc. v. FERC
7 F.4th 1177 (D.C. Circuit, 2021)
Shawnee Tribe v. Yellen
District of Columbia, 2021
Patel v. Cuccinelli
E.D. Kentucky, 2021
Pacific Maritime Association v. NLRB
967 F.3d 878 (D.C. Circuit, 2020)
Baltimore Gas and Electric Company v. FERC
954 F.3d 279 (D.C. Circuit, 2020)
Wagdy v. Kerry
District of Columbia, 2018
Wagdy v. Sullivan
316 F. Supp. 3d 257 (D.C. Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
839 F.3d 1165, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20170, 2016 U.S. App. LEXIS 19225, 2016 WL 6210707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-citizen-inc-v-federal-energy-regulatory-commission-cadc-2016.