Gas Transmission Northwest Corp. v. Federal Energy Regulatory Commission

504 F.3d 1318, 378 U.S. App. D.C. 267, 171 Oil & Gas Rep. 232, 2007 U.S. App. LEXIS 24188
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 16, 2007
Docket03-1257, 04-1065, 04-1066
StatusPublished
Cited by6 cases

This text of 504 F.3d 1318 (Gas Transmission Northwest Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gas Transmission Northwest Corp. v. Federal Energy Regulatory Commission, 504 F.3d 1318, 378 U.S. App. D.C. 267, 171 Oil & Gas Rep. 232, 2007 U.S. App. LEXIS 24188 (D.C. Cir. 2007).

Opinion

SILBERMAN, Senior Circuit Judge:

Two interstate natural gas pipelines seek review of Federal Energy Regulatory Commission (“FERC”) orders that limit the amount of collateral pipelines may require from non-creditworthy shippers. Petitioners assert that the orders under review are an unexplained departure from FERC precedent and, in any event, are unreasonable (arbitrary and capricious). *1319 We disagree, and we deny the petitions for review.

I.

Although we encounter a series of FERC orders, 1 including three orders on rehearing, then a joint request to hold petitions in abeyance pending a rulemak-ing (which FERC terminated, relying instead on a policy statement), and finally a remand of the record at FERC’s request to allow FERC to more fully consider petitioners’ arguments, the issue before us is rather simple. Petitioners, apparently stung by recent shipper defaults, wished to amend their tariffs to require non-creditworthy shippers (those who have below investment grade bond ratings) to post twelve months’ reservation charges as collateral. The Commission determined that petitioners’ proposed tariffs were “unjust and unreasonable”; that as a matter of policy FERC would ordinarily permit only a requirement of three months’ reservation charges. The Commission acknowledged that certain pipelines had filed tariffs requiring twelve months’ collateral, but those exceptions to its policy fell into two categories: either the tariffs had been filed without protests that caused FERC to focus on the issue, or the longer collateral requirements were explicitly permitted for newly constructed facilities.

Besides asserting that these exceptions were actually inconsistencies in its policy, petitioners contended that a three-month reservation charge was inadequate collateral to cover their “remarketing risk” — the ability to resell the contracted-for pipeline capacity (at the same price). FERC recognized that a three-month collateral requirement might not fully cover petitioners’ remarketing risk, but it determined that this risk is a normal cost of doing business and could be addressed as a factor in petitioners’ rate of return.

Finally, petitioners contended that their particular situations — both having suffered defaults in recent years — justified a deviation from FERC’s policy. The Commission determined, however, that the difficulties petitioners had faced were transitory, caused by unusual events such as the Western energy crisis.

II.

Petitioners make a half-hearted attempt to suggest that FERC’s decision to abandon a rulemaking on the collateral issue somehow suggests that its policy is really an illegal substantive rule, but there is nothing to their argument. FERC simply decided that a general policy statement would suffice, leaving open case by case determinations. But the Commission was, and is, prepared to defend the application of its policy in individual cases as it has done here, and an agency’s policy can just as well be articulated in adjudications as in rulemaking. SEC v. Chenery Corp., 332 U.S. 194, 202-03, 67 S.Ct. 1575, 91 L.Ed. 1995 (1947). In short, FERC has not sought to rely on the policy statement, but rather to defend its policy in the challenged orders. Guardian Fed. S & L Ass’n v. Fed. S & L Ins. Corp., 589 F.2d 658, 666 (D.C.Cir.1978).

*1320 Petitioners’ alleged inconsistencies in FERC’s decision are, in our view, adequately explained. With regard to the unchallenged filings, FERC said:

[I]n the absence of protests, the Commission may simply have accepted these provisions without examining whether they conformed to Commission policy and precedent. Under such circumstances, accepting another pipeline’s provisions does not necessarily establish a generic Commission policy or precedent regarding similar tariff provisions.

Remand Order, 117 FERC ¶ 61,146 at 61,-786 (2006). We think that position is eminently reasonable. FERC’s acceptance of a pipeline’s tariff sheets does not turn every provision of the tariff into “policy” or “precedent.” See, e.g., Alabama Power v. FERC, 993 F.2d 1557, 1565 n. 4 (D.C.Cir.1993); Nevada Power Co., 113 FERC ¶ 61,007 at 61,013-14 (2005) (refusing to treat a rate calculation from a prior tariff as precedent because “the issue was not raised, and the Commission did not discuss it or rule on it”). When a proposed tariff with more than a three-month collateral requirement has been challenged by shippers, FERC has required pipelines to amend their filing to comply with its policy. See Valero Interstate Trans. Co., 62 FERC ¶ 61,197 at 62,397 (1993).

Petitioners nevertheless contend that FERC’s practice puts them at a competitive disadvantage vis-a-vis pipelines whose nonconforming collateral provisions in their tariffs escaped scrutiny. But as FERC’s counsel assured us at oral argument, if petitioners, or anyone filing a complaint, challenged those tariff provisions, the Commission would apply its three-month policy.

Apparently, however, two pipelines in direct competition with petitioners (Alliance Pipeline and Northern Border Pipeline) have twelve-month collateral requirements that are not subject to challenge. That is because they fall within another exception to FERC’s policy. The Commission, as we noted, permits pipelines to impose a twelve-month collateral requirement on newly constructed facilities, and those pipelines are such. Petitioners contend that this policy is arbitrary and capricious because the Commission has not adequately explained its differential treatment of new pipelines and existing pipelines. To be sure, FERC’s initial explanation for treating tariffs on new facilities differently is, as petitioners recognized, economically faulty. FERC said, “[Ojnee the pipeline is in service, the construction costs are sunk (have already been expended), so the ongoing financial risk to the pipeline is less_” PG & E Gas Trans., 103 FERC ¶ 61,137 at 61,472 (2003). Actually the financial risk is the same whether the pipeline is already built or not. But in its rehearing order, FERC explained reasonably that pipelines and their financing institutions’ reliance interests for new investment justify the longer collateral requirement. “[T]he pipeline is under no obligation to construct facilities, and the pipeline as well as its lenders have an interest in ensuring a reasonable amount of collateral from the initial shippers supporting the project before committing funds to the project.” PG & E Gas Trans., 105 FERC ¶ 61,382 at 62,700 (2003).

* * *

Alternatively, petitioners re-argue before us that the Commission’s policy ordinarily limiting collateral to three months’ reservation charges is unreasonable because it does not cover the remarketing risk.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baltimore Gas and Electric Company v. FERC
954 F.3d 279 (D.C. Circuit, 2020)
Mozilla Corporation v. FCC
940 F.3d 1 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
504 F.3d 1318, 378 U.S. App. D.C. 267, 171 Oil & Gas Rep. 232, 2007 U.S. App. LEXIS 24188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gas-transmission-northwest-corp-v-federal-energy-regulatory-commission-cadc-2007.