Nw. Corp. v. Fed. Energy Regulatory Comm'n

884 F.3d 1176
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 16, 2018
DocketNo. 16-1176
StatusPublished
Cited by13 cases

This text of 884 F.3d 1176 (Nw. Corp. v. Fed. Energy Regulatory Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nw. Corp. v. Fed. Energy Regulatory Comm'n, 884 F.3d 1176 (D.C. Cir. 2018).

Opinion

Kavanaugh, Circuit Judge:

The Federal Energy Regulatory Commission requires utilities that transmit electricity to supply extra power generation in order to balance moment-to-moment variations in demand for electricity. Utilities must add power to, or withdraw power from, the grid in real time as actual demand for electricity exceeds or falls short of projected demand. That extra power generation is known as regulation service.

FERC allows utilities to recover costs associated with the provision of regulation service. Utilities may recover those costs *1179by charging them to customers, as long as the utilities charge rates that are "just and reasonable." 16 U.S.C. § 824d(a).

NorthWestern is an electric utility that is subject to FERC's regulation-service requirement. Before 2011, NorthWestern lacked the generating capacity to provide its own regulation service, so it met the requirement by purchasing regulation service from other utilities. With FERC's approval, NorthWestern then passed on the cost of that purchased regulation service to its wholesale and retail customers. But purchasing regulation service from other utilities eventually became too expensive, so NorthWestern built a new generating station dedicated to providing regulation service. NorthWestern then proposed to revise the rate that it charges customers for regulation service in order to recover the costs of providing that service from the new station.

FERC determined that NorthWestern's proposed rate was not just and reasonable. FERC therefore modified NorthWestern's proposed rate and ordered NorthWestern to refund its customers the difference between the proposed rate and the modified rate. NorthWestern challenges FERC's decision as arbitrary and capricious under the Administrative Procedure Act. The arbitrary and capricious standard requires that an agency's decision be reasonable and reasonably explained. We conclude that FERC's decision in this case was reasonable and reasonably explained, and we therefore deny the petition for review.

I

In 1996, FERC issued Order 888. 61 Fed. Reg. 21,540 (May 10, 1996). Among other things, Order 888 requires electric utilities to provide their customers with certain ancillary services-services that supplement the basic service of transmitting electricity. Id. at 21,579 -80. One such ancillary service is "regulation service." Regulation service is extra power generation that responds to "moment-to-moment variations" in demand for electricity in a given area. Id. at 21,582. In other words, regulation service is "the injection or withdrawal of real power" into or from the electric grid in response to fluctuations in demand for electricity. Order No. 755, 76 Fed. Reg. 67,260, 67,260 -61 (Oct. 31, 2011). Regulation service helps to prevent blackouts and equipment damage by keeping the frequency of the electric current at close to 60 Hertz, the standard frequency in the United States. Id. If a utility fails to maintain that frequency, FERC may impose civil penalties on the utility. See 16 U.S.C. § 825o -1.

A utility charges customers for regulation service under Schedule 3 of the utility's Open Access Transmission Tariff, which is filed with FERC. FERC must examine the rate that a utility proposes to charge Schedule 3 customers in order to ensure that the rate is "just and reasonable." 16 U.S.C. § 824d(a), (e). A just and reasonable rate must be fair both to the utility and to its customers: It "should be based on the costs of providing service to the utility's customers, plus a just and fair return on equity." Alabama Electric Cooperative, Inc. v. FERC , 684 F.2d 20, 27 (D.C. Cir. 1982) ; see also FPC v. Hope Natural Gas Co. , 320 U.S. 591, 603, 64 S.Ct. 281, 88 L.Ed. 333 (1944).

This case concerns an attempt by petitioner NorthWestern to revise its Schedule 3 rate. NorthWestern is an electric utility subject to FERC's regulation-service requirement. As relevant here, NorthWestern transmits electricity to wholesale and retail customers in Montana.1 When *1180NorthWestern first began operations in 2002, NorthWestern did not possess sufficient generating capacity to provide its own regulation service. So NorthWestern complied with Order 888 by purchasing regulation service from other utilities. NorthWestern contracted with those other utilities for a set amount of regulation service and passed the cost of that regulation service on to customers under Schedule 3. From 2002 to 2010, NorthWestern purchased, and passed on the cost of, 60 megawatts of regulation service each year to its Schedule 3 customers.

But NorthWestern eventually decided that purchasing regulation service from other utilities was inefficient. So NorthWestern built the Dave Gates Generating Station, a station dedicated to providing regulation service to NorthWestern's customers. The Gates Station has three generators, each with a maximum capacity of 50 megawatts, for a total nominal or "nameplate" capacity of 150 megawatts. The Gates Station began operating in January 2011.

Whereas NorthWestern had previously passed on to its Schedule 3 customers the cost of purchasing regulation service from other utilities, NorthWestern now wanted to recover from its customers the cost of providing regulation service from the Gates Station. So NorthWestern filed a proposed revised Schedule 3 rate for FERC's approval. NorthWestern filed its rate pursuant to Section 205 of the Federal Power Act, which places the burden on the utility to show that its proposed revised rate is just and reasonable. 16 U.S.C. § 824d(e).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XO Energy MA, LP v. FERC
77 F.4th 710 (D.C. Circuit, 2023)
City of Salisbury, North Carolina v. FERC
36 F.4th 1164 (D.C. Circuit, 2022)
In re: NTE Connecticut, LLC
26 F.4th 980 (D.C. Circuit, 2022)
Baltimore Gas and Electric Company v. FERC
954 F.3d 279 (D.C. Circuit, 2020)
Braeburn Inc. v. U.S. Food & Drug Admin.
389 F. Supp. 3d 1 (D.C. Circuit, 2019)
Limnia, Inc. v. U.S. Dep't of Energy
347 F. Supp. 3d 25 (D.C. Circuit, 2018)
ANR Storage Co. v. Fed. Energy Regulatory Comm'n
904 F.3d 1020 (D.C. Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
884 F.3d 1176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nw-corp-v-fed-energy-regulatory-commn-cadc-2018.