Duke Energy Progress, LLC v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 9, 2024
Docket21-1272
StatusPublished

This text of Duke Energy Progress, LLC v. FERC (Duke Energy Progress, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duke Energy Progress, LLC v. FERC, (D.C. Cir. 2024).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued January 10, 2024 Decided July 9, 2024

No. 21-1272

DUKE ENERGY PROGRESS, LLC, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

EDGECOMBE SOLAR LLC, INTERVENOR

Consolidated with 22-1072, 22-1284, 22-1327

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Misha Tseytlin argued the cause for petitioner. With her on the briefs were Christopher R. Jones, Antonia M. Douglas, and Kevin M. LeRoy.

Jennifer T. Harrod and Robert B. Josey were on the brief for amici curiae North Carolina Utilities Commission and the Public Staff - North Carolina Utilities Commission in support of petitioner. Louis S. Watson, Jr. entered an appearance. 2

Beth G. Pacella, Deputy Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

Tyler O’Connor argued the cause for intervenor. With him on the brief were Holly Rachel Smith and Larry F. Eisenstat. Amanda S. Berman entered an appearance.

Before: WILKINS and CHILDS, Circuit Judges, and EDWARDS, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge CHILDS.

CHILDS, Circuit Judge. Petitioner, Duke Energy Progress, LLC (“Duke Energy”), seeks review of two orders by the Federal Energy Regulatory Commission: (1) rejecting its agreement with an energy generation company, American Beech Solar, LLC, and (2) accepting its agreement with another energy generation company, Edgecombe Solar LLC, which Duke Energy filed unsigned and under protest. Under both contracts, the generators would pay Duke Energy to perform network upgrades enabling them to connect new generation facilities to the electric grid. But the first agreement does not require Duke Energy to reimburse the cost of those upgrades, while the second does. Because we hold that FERC’s orders were not “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law,” 5 U.S.C. § 706(2)(A), we deny the petitions for review. 3 I.

A.

Most electricity in the eastern United States is transmitted on a single grid. That grid is subdivided into regions, each administered by a nonprofit “System Operator” that monitors the flow of electricity to ensure, among other things, an adequate supply of electricity and grid stability. Within each region, sections of the grid’s physical infrastructure are owned by “Grid Operators,” typically public utilities, that connect electricity generation facilities to the grid and transmit the electricity. The generation facilities connected to a Grid Operator’s infrastructure may be owned by the Grid Operator itself or by third parties.

The transmission of electricity in interstate commerce is governed by the Federal Power Act, 16 U.S.C. § 824(b), which requires the Federal Energy Regulatory Commission (the “FERC”) to ensure that the price of electricity is just, reasonable, and not unduly discriminatory or preferential. 16 U.S.C. § 824d(a), (b). Among the transactions that FERC regulates is the connection of a new generation facility to the physical infrastructure owned by a Grid Operator. FERC promulgated Order 2003 (along with Orders 2003-A, 2003-B, and 2003-C) to establish “standard procedures and a standard agreement for interconnecting [large] generators” to jurisdictional public utilities’ transmission systems. Standardization of Generator Interconnection Agreements & Procedures, Order No. 2003, 104 FERC ¶ 61,103 at PP 1, 7 (2003) (“Order 2003”), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220 (2004) (“Order 2003-A”), order on reh’g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004) (“Order 2003- B”), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 4 (2005) (“Order 2003-C”), aff’d sub nom; see also Ameren Servs. Co. v. FERC, 880 F.3d 571, 574 (D.C. Cir. 2018).

Under these standard procedures, a generator must request FERC’s approval to connect a new generation facility to the grid. Ameren Servs. Co., 880 F.3d at 572. The System Operator for the relevant grid section will then determine if any Grid Operator needs to upgrade its infrastructure to handle the increased flow of electricity from the new generation facility. Id. Importantly, upgrades may be needed on a section of the grid to which the generator will directly connect and on other more distant sections of the grid. See Order No. 2003 at n.32. Order 2003 uses different terminology to refer to the owners of directly connected sections (“Transmission Providers”) and the owners of other sections (“Affected System Operators”).

Most of the relevant procedures in Order 2003 relate to the obligations between generators and Transmission Providers. For example, the standard procedures include a standard contract—the pro forma Long Term Interconnection Agreement (“pro forma Agreement”)—that applies between a generator and the Transmission Provider to whose system it proposes to directly connect. Order 2003, Appendix C. If upgrades are needed, Order 2003 and the pro forma Agreement require the generator to pay initial upgrade costs and the Transmission Provider to then reimburse the generator in installments. Order 2003, Appendix C § 11.4.1.

This dispute is about whether that reimbursement requirement also applies when connecting a new generation facility makes network upgrades by an Affected System Operator necessary.

When subject to Order 2003’s standard procedures, a Grid Operator (whether a Transmission Provider or Affected System Operator) can only avoid following such procedures if FERC 5 approves a request for a deviation. Xcel Energy Servs. Inc. v. FERC, 41 F.4th 548, 552 (D.C. Cir. 2022). To obtain a deviation, a Grid Operator must show that the standard procedures would unduly affect its existing customers by submitting a transmission rate filing that “explain[s] the facts of the case and the assumptions on which its calculation is based and provide[s] evidentiary support.” Order No. 2003-B at P 56.

B.

The key players in this dispute are an Affected System Operator, Duke Energy, and two energy generation companies, American Beech Solar, LLC (“American Beech”) and Edgecombe Solar LLC (“Edgecombe”). Duke Energy owns a section of the grid within the Mid-Atlantic region. American Beech and Edgecombe proposed to connect new large solar generating facilities onto a neighboring section of the grid, which would require $20-30 million in network upgrades to Duke Energy’s system. In the two FERC proceedings before us, the parties dispute whether Duke Energy must reimburse the generators for the cost of those network upgrades.

The first proceeding involves American Beech’s proposed interconnection. Duke Energy and American Beech executed an Affected System Operating Agreement under which American Beech would not seek reimbursement for the network upgrade costs (the “American Beech Agreement”). [JA4-82]. After Duke Energy submitted the agreement to FERC for approval, American Beech submitted comments to FERC urging it to require reimbursement anyway. Duke Energy Progress, Comments of American Beech Solar, Docket No. ER21-1955 [JA95-96].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Duke Energy Progress, LLC v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duke-energy-progress-llc-v-ferc-cadc-2024.