Ameren Services Co. v. Federal Energy Regulatory Commission

880 F.3d 571
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 26, 2018
Docket16-1075 Consolidated with 16-1304, 16-1373
StatusPublished
Cited by13 cases

This text of 880 F.3d 571 (Ameren Services Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ameren Services Co. v. Federal Energy Regulatory Commission, 880 F.3d 571 (D.C. Cir. 2018).

Opinions

Dissenting opinion filed by Circuit Judge Rogers.

SILBERMAN, Senior Circuit Judge:

When new sources of power generation connect to the existing transmission grid, the grid often requires new construction beyond the point of interconnection in order to accommodate the increased flows of electricity. FERC issued a series of orders empowering incoming generators within the Midcontinent Independent System Operator (MISO) region1 to elect to self-fund this new construction, or to seek financing from third parties, regardless of whether the current grid owners wish to fund the construction themselves.

The Commission justified the orders on two grounds. First, it found that allowing transmission owners to choose between funding options—and thus, potentially, to impose subsequent charges to generators via transmission owner funding—could allow the transmission owners to discriminate among generators. Secondly, it held that the charges to generators would be (or could be) unjust and unreasonable under the Federal Power Act. Petitioning transmission owners challenge both grounds. We conclude that Petitioners are correct regarding the discrimination point: there is neither evidence nor economic logic supporting FERC’s discriminatory theory as applied to transmission owners without affiliated generation assets.

FERC’s second ground raises a unique and important conceptual issue. Petitioners argue that involuntary generator funding compels them to construct, own, and operate facilities without compensatory network upgrade charges—thus forcing them to accept additional risk without corresponding return as essentially non-profit managers of these upgrade facilities. We [574]*574do not.think that FERC adequately responded to this argument. We therefore remand the case to the Commission.

I.

We have previously explained the' series of steps FERC took to unbundle the electric power system, enabling and encouraging new independent generators to create a competitive market for power generation.2 Transmission owners, which had previously served their own vertically integrated sources of power generation, were obliged to accept power from any sourcé on a non-discriminatory basis.

For independent generators to utilize the grid, they must first connect to it. FERC thus used its rulemaking powers to issue Order No. 2003, which standardized the procedures for generator interconnection and directed each transmission network to maintain a pro forma generator interconnection agreement.3 Order No. 2003 also established the “at or beyond” rule, Which distinguished between two types of new construction necessary to connect new generation sources into the grid. See Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277, 1284-86 (D.C. Cir. 2007). The first category, called “interconnection facilities,” includes those facilities and equipment that lie between the generation source and the point of interconnection with the transmission network. Under the “at or beyond” rule, the cost of interconnection facilities are the sole5 responsibility of the incoming generator. That allocation of costs is undisputed in this, proceeding. And Petitioners do not own or manage those “interconnection facilities.” The, second category. • includes those additional facilities. and equipment that are needed beyond the “point of interconnection”—in other words, any -new construction that occurs within Petitioners’ transmission grid itself to accommodate the incoming flows of new power. This latter category of construction, called “network upgrades,” is the focus of the present dispute. - ' '

* ⅛ *

As we have also explained, FERC encouraged the creation of Regional Transmission Organizations (RTOs) to integrate the fragmented transmission grid.on a regional basis, along- with Independent System Operators (ISOs) as non-profit entities which would control access to the grid within their respective regions. Wisconsin Public Power, Inc., 493 F.3d at 247. In Order No. 2003, the' Commission set a default rule that transmission owners would bear responsibility for the network upgrades, but gave ISOs “flexibility to customize its interconnection procedures and agreements to meet regional needs.” Order No. 2003 at P 827; id. at P 676. In this case, we encounter MISO, which qualifies as both an RTO and an ISO.

Originally, MISO had allocated the costs equally between the incoming generator and the transmission owner. As such, under transmission owner funding—which it could choose—the transmission owner [575]*575would initially provide the capital for construction, but would recover 50 percent of that capital (a “return of’ capital), along with an appropriate return on that capital, through network upgrade charges. It would fund the other 50 percent of the costs by passing them on to all- of its customers through its rates—again, including an appropriate rate of return. Under generator funding, the generator would initially provide the capital for construction, and would receive 50 percent of that capital from the transmission owner through credits for transmission service. E.ON at P 3.

But a problem arose: this 50/50 arrangement placed most of the cost burden on the pricing zone where interconnection occurred, but the power from the new generation sources often exceeded the load within those local zones in which they connected. Midwest Independent Transmission System Operator, Inc., 129 FERC ¶ 61,060, at P 7 (2009) (“MISO Tariff Amendment”). As a result, the local customers of the transmission owner bore a disproportionate share of the cost burden of upgrades that supported power that would ultimately benefit more remote customers throughout the MISO region. Id. at P 11. Rather than forcing their local customers to shoulder this regional burden, several local transmission owners threatened to withdraw from MISO if the cost allocation remained unchanged. Id. at P10.

To remedy this problem, MISO proposed (and FERC approved) a new allocation of capital costs: for network upgrades rated at 345 kilovolts or above, the interconnecting generator bears 90 percent of those costs, and transmission owners (and their local customers) bear 10 percent. -In' other , words, the 10 percent would be included in ■ the transmission owner’s rate base. For projects rated below 345 kilo-volts, the interconnecting generator bears 100 percent of the costs. This reallocation was intended to comport with FERC’s “principle that network upgrades should be paid for by the parties that cause and benefit from such .upgrades.” MISO Tariff Amendment at P 3.

The manner in which the incoming generator and transmission owner .actually pay these capital costs depends upon the way the network upgrades are funded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Hudson Gas & Electric Corporation v. FERC
138 F.4th 531 (D.C. Circuit, 2025)
El Paso Electric v. FERC
76 F.4th 352 (Fifth Circuit, 2023)
Green Development, LLC v. FERC
77 F.4th 997 (D.C. Circuit, 2023)
American Clean Power Assoc v. FERC
54 F.4th 722 (D.C. Circuit, 2022)
Coalition of MISO Transmission v. FERC
45 F.4th 1004 (D.C. Circuit, 2022)
Xcel Energy Services Inc. v. FERC
41 F.4th 548 (D.C. Circuit, 2022)
Nat'l Women's Law Ctr. v. Office of Mgmt. & Budget
358 F. Supp. 3d 66 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
880 F.3d 571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ameren-services-co-v-federal-energy-regulatory-commission-cadc-2018.