Calpine Corp. v. Federal Energy Regulatory Commission

702 F.3d 41, 403 U.S. App. D.C. 176, 2012 U.S. App. LEXIS 25732, 2012 WL 6573964
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 18, 2012
Docket11-1122
StatusPublished
Cited by15 cases

This text of 702 F.3d 41 (Calpine Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calpine Corp. v. Federal Energy Regulatory Commission, 702 F.3d 41, 403 U.S. App. D.C. 176, 2012 U.S. App. LEXIS 25732, 2012 WL 6573964 (D.C. Cir. 2012).

Opinion

Opinion for the Court filed by Senior Circuit Judge SILBERMAN.

SILBERMAN, Senior Circuit Judge:

For the third time, we consider FERC’s authority to regulate public-utility charges to independent generators- for the latter’s use of “station power” — the electricity necessary to operate a generator’s requirements for light, heat, air conditioning, etc. FERC now concludes that it lacks this authority, and we affirm.

I.

We explained the legal and economic background of the electrical energy market in Niagara Mohawk Power Corp. v. FERC, 452 F.3d 822 (D.C.Cir.2006), and Southern California Edison Co. v. FERC, 603 F.3d 996 (D.C.Cir.2010), but we will again summarize. Generators may procure station power through one of three means: (1) “on-site” self-supply, which redirects some of the station’s outbound generated electricity for internal use (also called “behind-the-meter” production); (2) “remote” self-supply, in which power is obtained from an affiliated, off-site facility; or (3) “third-party” supply, in which power is drawn off the grid from unaffiliated providers.

Historically, electrical utilities were vertically integrated and typically acted as local monopolies — they owned generation, transmission, and distribution facilities and sold these services as a bundled package in their service areas. Utilities obviously did not charge themselves for the use of station power at their generating facilities; rather, they simply subtracted (“netted”) the energy consumed as station power against their gross output. But in 1996 FERC issued Order 888, which effectively unbundled generating from transmission and distribution services. The Commission accomplished this goal by requiring utilities to file open-access tariffs that offered rates to all customers on an equal basis — basically, utilities could not prefer their own affiliates over independent generators. Order 888 also encouraged the creation of non-profit independent system operators (“ISOs”) to reduce the market power of utilities and ensure competitive rates; the California Independent System Operator (“CAISO”) is one such entity.

*43 Order 888 was successful in causing major utilities nationwide to divest most of their generating facilities, but it raised questions as to how independent generators would be charged for their use of station power. Under what circumstances could a generator be charged retail rates for either drawing from the grid or self-supplying its station power? FERC answered this question by devising “netting intervals.” If a generator’s net output (total output to the grid minus station power use) is positive over a fixed period, then the generator is not charged retail rates for its consumption. But if the generator uses more power than it sends, it is deemed to have obtained the shortfall in a retail sale from a third party (i.e., a utility).

Generators have an economic interest in a longer netting interval because it affords a greater opportunity to send power to the grid, which would make up for what is consumed. Utilities, by contrast, would prefer shorter netting intervals to enable higher retail charges against independent generators. A generator is only paid for its net output of energy to the grid, so even when the net output is positive, consumption of station power reduces the amount the generator is paid for its production. But retail rates are higher than wholesale rates, so a generator would rather have its station power netted against the total it delivers at wholesale than pay for station power at retail.

The legal issue that triggered this series of cases is how the authority to set netting intervals for different purposes meshes with the Federal Power Act’s division of jurisdiction between federal and state authorities. Section 201(b) of the Act gives FERC jurisdiction over the “transmission of electric energy in interstate commerce” and the “sale of electric energy at wholesale in interstate commerce,” as well as “all facilities for such transmission or sale.” 16 U.S.C. § 824(b)(1). States, however, retain jurisdiction over “any other sale of electric energy” and “facilities used in local distribution” of electricity. Id.

FERC approved a tariff establishing an hourly netting period for the Pennsylvania-New Jersey-Maryland energy market and later approved an amendment expanding the netting interval to one month (if a generator’s net output over a month was positive, then any energy a generator drew from the grid was simply netted against its gross output and no retail charges were permitted). Utility companies raised objections arguing that any third-party provision of station power (and indeed, the generator’s own production of station power) 1 was a retail sale outside of FERC’s jurisdiction. FERC rejected this position because, in its view, if a generator’s net output was positive, no sale had occurred.

The Commission instead agreed with the position advanced by a group of generators — that the station-power netting interval used to determine when to assess transmission fees should be the same period used to calculate when the provision of station power constitutes a retail sale. A “transmission fee” is a fee assessed for the transmission of energy across the electrical grid; it is often called an “access charge” because it is assessed when a party is treated as “accessing” the grid. Netting intervals are used for transmission as well because whether a generator has positive or negative output over a given interval determines what energy is deemed to be transmitted across the grid.

*44 FERC accordingly approved a one-month netting period for both transmission and station power in a tariff filed by the New York ISO, which led New York utilities and the New York state regulator to petition for review in this Court, raising the same jurisdictional objection as the utilities in the prior case. FERC defended its authority to determine when retail sales occur on the basis of its jurisdiction over interstate transmission. A group of generators, as intervenors, contended that the Commission needed to set a uniform netting period to protect them from unfair discrimination by utilities because utility-owned generators, of course, would not be assessed retail charges by the utilities themselves.

In Niagara Mohawk, we noted that “[petitioners’ statutory argument [was] not insubstantial,” that the Commission’s rationale was “a bit confusing,” and that FERC had not “clearly articulated why [transmission] jurisdiction permits it to determine that no sale of any kind — including a retail sale — takes place when the generator takes station power from the grid.” 452 F.3d at 828. We declined, however, to resolve that question on the merits because of a major concession by the petitioners — that FERC had the authority to set an hourly netting interval, just not to expand the interval to one month. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
702 F.3d 41, 403 U.S. App. D.C. 176, 2012 U.S. App. LEXIS 25732, 2012 WL 6573964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calpine-corp-v-federal-energy-regulatory-commission-cadc-2012.