San Isabel Electric v. Public Utilities Commission

2021 CO 36
Supreme Court of Colorado·Decided June 4, 2021·No. 20SA103·Published

Opinion

The Supreme Court of the State of Colorado 2 East 14th Avenue • Denver, Colorado 80203

2021 CO 36

Supreme Court Case No. 20SA103 Appeal from the District Court District Court, City and County of Denver, Case No. 19CV31602 Honorable Eric M. Johnson, Judge

Petitioner-Appellant:

San Isabel Electric Association, Inc., v.

Respondents-Appellees:

The Public Utilities Commission of the State of Colorado; Jeffrey Ackermann, in his official capacity as Chairman of the Public Utilities Commission of the State of Colorado; Frances A. Koncilja, in her official capacity as a member of the Public Utilities Commission of the State of Colorado; John Gavan, in his official capacity as a member of the Public Utilities Commission of the State of Colorado;

Black Hills Colorado Electric, LLC; and Black Hills Colorado Wind, LLC.

Judgment Affirmed

en banc

June 1, 2021

Attorney for Petitioner-Appellant: Sisto Mazza Trinidad, Colorado

Attorneys for Respondents-Appellees Public Utilities Commission of the State of Colorado, Jeffrey Ackermann, Frances A. Koncilja, and John Gavan: Philip J. Weiser, Attorney General Paul C. Gomez, First Assistant Attorney General Ruth M. Harper, Assistant Attorney General Denver, Colorado

Attorneys for Respondents-Appellees Black Hills Colorado Electric, LLC; and Black Hills Colorado Wind, LLC: Wilkinson Barker Knauer, LLP Raymond L. Gifford Caitlin M. Shields Ethan D. Jeans Denver, Colorado

Black Hills Corporation Tyler E. Mansholt Denver, Colorado

JUSTICE MÁRQUEZ delivered the Opinion of the Court.

¶1 Appellant San Isabel Electric Association, Inc. is a rural cooperative electric association that holds two certificates of public convenience and necessity (“CPCNs”) issued by the Colorado Public Utilities Commission (“PUC”). Under its CPCNs, San Isabel has the exclusive right to provide electric service as a public utility to members and non-member customers in its certificated area, which spans seven counties in southern Colorado. The question before us is whether San Isabel’s CPCNs include the right to provide station power to two wind farms located in San Isabel’s certificated territory that are owned by another utility, Black Hills Colorado Electric, LLC and Black Hills Colorado Wind, LLC (collectively, “Black Hills”). The PUC concluded that San Isabel’s CPCNs do not include the right to provide station power to operate the wind turbines’ electronics, hydraulic pumps, heaters, and other auxiliary equipment at Black Hills’ wind farms, and that the decision to allow Black Hills to self-supply station power to its wind farms did not violate San Isabel’s state and federal constitutional rights to due process. The district court affirmed the PUC’s ruling.

¶2 We now affirm the judgment of the district court. We hold that, on the facts of this case, the PUC regularly pursued its authority in concluding that San Isabel’s right under its CPCNs does not include the right to provide station power to Black Hills’ generation facilities and that Black Hills, as a vertically integrated utility, may self-supply such power using its own interconnected transmission network

and electric generation resources. We further hold that, because San Isabel did not have a property right to supply station power to another utility, the PUC’s decision did not amount to a taking of property without due process.

I. Facts and Procedural History A. Background

¶3 Section 40-9.5-105(1), C.R.S. (2020), allows the PUC to issue a CPCN assigning specific service territories to a cooperative electric association. An electric utility that has been granted a CPCN generally has the exclusive right to provide electricity in its certificated territory. Pub. Utils. Comm’n v. Home Light & Power Co., 428 P.2d 928, 936 (Colo. 1967) (“[O]nce an area has been [c]ertificated to [a] utility, it and it alone has the right to serve the future needs of that area provided it can do so.”). The key issue in this case is whether such a right includes the provision of “station power,” a term understood in the industry as the electric energy required to operate and maintain electric generation facilities. See, e.g., PJM Interconnection, LLC, 94 FERC ¶ 61,251, at 61,889 (2001) (“PJM II”)1 (Federal Energy Regulatory Commission defining “station power” as the electric energy used for,

1 PJM II was the second in a series of orders issued by the Federal Energy Regulatory Commission addressing the treatment of station power in the Pennsylvania-New Jersey-Maryland (“PJM”) electricity market. See PJM Interconnection, LLC, 95 FERC ¶ 61,470 (2001) (“PJM III”); PJM Interconnection, LLC, 93 FERC ¶ 61,061 (2000) (“PJM I”).

inter alia, “operating the electric equipment that is on the generating facility’s site”).

¶4 An electric generation facility can procure station power through one of three means: (1) on-site self-supply (i.e., by redirecting electricity generated on site for internal use); (2) remote self-supply (i.e., by obtaining power from an off-site generator owned by the same company); or (3) third-party supply (i.e., by drawing power through the grid from an unaffiliated provider). See Calpine Corp. v. FERC, 702 F.3d 41, 42 (D.C. Cir. 2012); PJM II, at 61,890.

¶5 Historically, electric utilities were vertically integrated, meaning they owned all three aspects of electric service—electricity generation, long-distance power transmission, and local distribution of electricity to end users—and sold these services as bundled packages in their service areas. Calpine, 702 F.3d at 42. These vertically integrated utilities did not charge themselves for the use of station power at their generating facilities but instead subtracted (“netted”) the energy consumed as station power from their gross output of electric energy. Id. at 43. In other words, whether through on-site or remote self-supply, a vertically integrated utility used only its own generating resources for station power and accounted for such usage through the practice of netting. In so doing, the energy industry has traditionally treated station power as distinct from other types of electric service.

Free access — add to your briefcase to read the full text and ask questions with AI

San Isabel Electric v. Public Utilities Commission, 2021 CO 36 (Colo. 2021).

2021 CO 36 (San Isabel Electric v. Public Utilities Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Public Service Co. of Colorado v. Public Utilities Commission
765 P.2d 1015 (Supreme Court of Colorado, 1988)
McKenna v. Nigro
372 P.2d 744 (Supreme Court of Colorado, 1962)
Public Service Co. v. Trigen-Nations Energy Co.
982 P.2d 316 (Supreme Court of Colorado, 1999)
Public Utilities Commission v. Poudre Valley Rural Electric Ass'n
480 P.2d 106 (Supreme Court of Colorado, 1971)
Public Utilities Commission v. Colorado Motorway, Inc.
437 P.2d 44 (Supreme Court of Colorado, 1968)
Town of Fountain v. Public Utilities Commission
447 P.2d 527 (Supreme Court of Colorado, 1968)
Public Utilities Commission v. Grand Valley Rural Power Lines, Inc.
447 P.2d 27 (Supreme Court of Colorado, 1968)
Western Colorado Power Co. v. Public Utilities Commission
411 P.2d 785 (Supreme Court of Colorado, 1966)
Public Utilities Commission v. Home Light & Power Co.
428 P.2d 928 (Supreme Court of Colorado, 1967)
Western Colorado Power Co. v. Public Utilities Commission
428 P.2d 922 (Supreme Court of Colorado, 1967)
City of Greeley v. Poudre Valley Rural Electric Ass'n
744 P.2d 739 (Supreme Court of Colorado, 1987)
Integrated Network Services, Inc. v. Public Utilities Commission
875 P.2d 1373 (Supreme Court of Colorado, 1994)
Trans Shuttle, Inc. v. Public Utilities Commission
89 P.3d 398 (Supreme Court of Colorado, 2004)
Durango Transportation, Inc. v. Colorado Public Utilities Commission
122 P.3d 244 (Supreme Court of Colorado, 2005)