Entergy Arkansas, LLC v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 15, 2022
Docket20-1262
StatusPublished

This text of Entergy Arkansas, LLC v. FERC (Entergy Arkansas, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Entergy Arkansas, LLC v. FERC, (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued November 8, 2021 Decided July 15, 2022

No. 20-1262

ENTERGY ARKANSAS, LLC, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

MISSISSIPPI PUBLIC SERVICE COMMISSION, ET AL., INTERVENORS

Consolidated with 20-1391

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Jennifer S. Amerkhail argued the cause and filed the briefs for petitioners. Zachary C. Schauf entered an appearance.

Carol J. Banta, Attorney, Federal Energy Regulatory Commission, argued the cause for 2 respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

Before: ROGERS and WILKINS, Circuit Judges, and SILBERMAN, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge WILKINS.

WILKINS, Circuit Judge. The instant petition arises from a three-year effort to establish a cost allocation method for allocating Midcontinent Independent System Operator, Inc.’s (“MISO”) share of costs for interregional transmission projects connecting a region operated by MISO and an adjacent region operated by PJM Interconnection, L.L.C. (“PJM”). In 2016, the Federal Energy Regulatory Commission (“FERC” or “Commission”) required MISO to institute reforms to its interregional planning process and directed MISO to propose a cost allocation method for its share of certain interregional project costs. Since that time, MISO has twice submitted proposals for such cost allocation. Both times, FERC rejected the proposals, finding that they were not just and reasonable as required by the Federal Power Act (the “Act”), 16 U.S.C. §§ 791 et seq., because they were inconsistent with the cost causation principle. After the second rejection, FERC, on its own initiative, established a cost allocation method for certain MISO-PJM projects. In this consolidated action, Petitioners challenge FERC’s rejection of MISO’s second proposal and FERC’s corresponding implementation of a cost allocation method. For the reasons below, we deny the petitions and affirm FERC’s orders in all respects. 3 I.

Section 201 of the Act gives FERC jurisdiction over facilities that engage in transmission and sale of electricity at wholesale in interstate commerce. 16 U.S.C. § 824(b)(1). Under the Act, FERC has the power to review rates in connection with transmission services or sales to ensure that such rates are “just and reasonable” and to set aside as “unlawful” any rate or charge it deems not just and reasonable. 16 U.S.C. § 824d(a). Additionally, pursuant to Section 206, if FERC finds a rate or charge to be “unjust, unreasonable, unduly discriminatory or preferential,” FERC “shall determine the just and reasonable rate . . . to be thereafter observed and in force, and shall fix the same by order.” 16 U.S.C. § 824e(a).

In assessing whether a rate is “just and reasonable,” FERC and the courts determine, among other things, whether the rate comports with the “cost-causation principle” which requires that the rates charged for electricity reflect the costs of providing it. See Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018) (hereinafter “Old Dominion”). “We often frame this principle as one that ensures burden is matched with benefit, so that FERC generally may not single out a party for the full cost of a project, or even most of it, when the benefits of the project are diffuse.” Id. (internal quotation marks and citations omitted).

Under a FERC regulation, known as “Order No. 1000,” see Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, 136 FERC ¶ 61,051 (2011), electric utilities are subject to two relevant requirements:

First, utilities in each planning region must jointly produce a regional transmission plan to 4 determine what new facilities would best meet regional needs for electricity. Second, in their respective tariffs, utilities must include a formula for allocating the costs of new transmission facilities selected in the regional transmission plan for purposes of cost allocation. This formula must satisfy six general principles, the first of which is the cost- causation principle: The cost of transmission facilities must be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits. Order No. 1000 requires each utility to show, through compliance filings, that its cost- allocation formula is consistent with the six specified principles.

Old Dominion, 898 F.3d at 1256 (internal quotation marks and citations omitted).

In accordance with Order No. 1000, MISO and PJM jointly planned—and subsequently approved as part of their respective regional transmission plans—interregional projects that connected and benefited both regions. Once interregional projects were identified, MISO and PJM allocated the costs of such projects between their regions. Each region then allocated its share of costs from the interregional project to subdivided zones within their own respective regions. This case involves the cost allocation method for MISO’s share of a MISO-PJM interregional transmission project.

Under MISO’s original regional transmission plan, MISO established different project categories, each with different qualifying criteria and cost allocations. MISO’s share of an 5 interregional project’s costs is then assigned according to the allocation method that corresponds with the MISO project type, of which there were historically three. 1 The most relevant category to this appeal is the “Market Efficiency Project”—a higher-voltage transmission project that reduces congestion and lowers the costs of power in the region. Originally, to qualify as a Market Efficiency Project, a transmission project was required to (1) cost at least $5 million, (2) consist of facilities that have voltages of 345 kilovolts (kV) or higher, and (3) have a total regional benefit-to-cost ratio of at least 1.25-to- 1, with benefits measured using an Adjusted Production Cost Savings metric (“Production Cost Metric”). J.A. 355. The Production Cost Metric measures the extent to which a new transmission project will make electricity cheaper by measuring the total reduction in costs resulting from the new project. See Midwest Independent Transmission System Operator, Inc., 118 FERC ¶ 61,209, ¶ 5 n.6 (2007). Under the original plan, once a project was deemed a Market Efficiency Project, 20 percent of the project cost was allocated on a region-wide basis to all customers across the entire MISO footprint (known as the “postage-stamp approach”). The remaining 80 percent was allocated to zones based on each zone’s proportion of the Production Cost Metric benefits that it received. The orders on review stem from FERC’s resolution of an earlier complaint proceeding and subsequent filings related to this original plan. We start with a brief summary of the relevant proceedings and filings.

1 The three MISO project types are: Baseline Reliability Projects, Market Efficiency Projects, and Multi-Value Projects. See J.A. 354– 55 (describing the three types of projects and corresponding allocation method).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Entergy Arkansas, LLC v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/entergy-arkansas-llc-v-ferc-cadc-2022.