American Clean Power Assoc v. FERC

54 F.4th 722
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 2, 2022
Docket20-1453
StatusPublished
Cited by4 cases

This text of 54 F.4th 722 (American Clean Power Assoc v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Clean Power Assoc v. FERC, 54 F.4th 722 (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued December 16, 2021 Decided December 2, 2022

No. 20-1453

AMERICAN CLEAN POWER ASSOCIATION, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

D. E. SHAW RENEWABLE INVESTMENTS, L.L.C., ET AL., INTERVENORS

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Gabriel Tabak argued the cause and filed the briefs for petitioner.

Bruce A. Grabow and Jennifer Brough were on the joint briefs for intervenors in support of petitioner.

Robert M. Kennedy, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. 2 Christopher R. Jones argued the cause for intervenors in support of respondent. With him on the joint brief were Miles H. Kiger, Wendy N. Reed, Wendy B. Warren, Matthew J. Binette, and Ilia Levitine. Kari Valley entered an appearance.

Before: MILLETT, RAO, and WALKER, Circuit Judges.

Opinion for the Court filed by Circuit Judge WALKER.

Opinion concurring in part and dissenting in part by Circuit Judge RAO.

WALKER, Circuit Judge: This case is the latest episode in a long-running dispute over how to fund upgrades to power lines. On one side are owners and operators of power lines; we’ll call them “transmission owners.” On the other side are power generators.

In the orders on review, FERC ruled for the transmission owners. That decision might have been reasonable. But it was not reasonably explained. In particular, FERC failed to adequately address new evidence that many MISO-region transmission owners also own generators. Because the Administrative Procedure Act requires a reasonable explanation, we remand to FERC.

I

A

When power generators build new facilities or update their existing facilities, they need to connect those facilities to the power grid. That connection in turn often requires transmission owners to upgrade their power lines to accommodate the power influx. See Ameren Services Co. v. FERC, 880 F.3d 571, 572 3 (D.C. Cir. 2018). “Direct” transmission owners must upgrade their power lines because their lines directly connect to the new or updated generators. Likewise, “indirect” transmission owners must often upgrade their power lines because they are downstream of the direct transmission owners’ lines.

In the Midcontinent Independent System Operator region, which spans much of middle America and part of Canada, generators pay for almost the whole cost of those upgrades. But there are two relevant ways in which they can pay. Option A: The generators can pay for the upgrades up front. Option B: The transmission owners can initially fund the upgrades and charge the generators over time to recoup those costs. Some transmission owners prefer Option B because they can earn a profitable return on their investment as they recoup their initial costs.

Years ago in the MISO region, direct transmission owners had unilateral funding authority, letting them choose between the two options. But indirect transmission owners did not.

B

In 2015, an indirect transmission owner called Otter Tail Power Company filed a complaint with FERC challenging that differential treatment. Under Section 206 of the Federal Power Act, FERC may, on its own or on a complaint, change a utility’s rate through a two-step process. First, it must find that the current rate is “unjust, unreasonable, unduly discriminatory, or preferential.” 16 U.S.C. § 824e(a). Second, it must determine a “just and reasonable” replacement rate. Id.

FERC agreed with Otter Tail. It found that direct and indirect transmission owners are similarly situated and thus should have the same ability to choose how to fund power line 4 upgrades. MISO, Inc. Otter Tail Power Co. v. MISO, Inc., 151 FERC ¶ 61,220 (Jun. 18, 2015); Otter Tail Power Co. v. MISO, Inc., 153 FERC ¶ 61,352 (Dec. 29, 2015).

But rather than leveling up and granting indirect transmission owners the same unilateral funding authority that direct transmission owners enjoyed, FERC leveled down by taking away all transmission owners’ unilateral funding authority. Otter Tail, 151 FERC ¶ 61,220, at ¶ 48. FERC did so by initiating a new proceeding to determine whether it is unjust and unreasonable for transmission owners to enjoy unilateral funding authority. FERC answered yes because, in its view, transmission-owner funding could allow certain transmission owners to discriminate among generators, which is prohibited by the Federal Power Act. Id.

In Ameren Services Co. v. FERC, this Court vacated and remanded FERC’s orders. 880 F.3d 571 (D.C. Cir. 2018). We noted that there would be a discrimination concern if transmission owners still owned generation facilities, like they did in the “bad old days.” Id. at 578. But in Ameren there was only one petitioning transmission owner that owned a generator, and we found an “absence of evidence” of potential discrimination. Id.

Ameren also held that FERC should have considered that its decision could force transmission owners to incur the financial risks of generator-funded upgrades without the opportunity for a profit. Id. at 581-82. We declined to decide whether those enterprise-risk concerns required a particular result until FERC “developed a record by considering” them. Id. at 584.

After Ameren, FERC still needed to adjudicate the original Otter Tail complaint — the one in which Otter Tail had alleged 5 that it is discriminatory for FERC to deny unilateral funding authority to indirect transmission owners when direct transmission owners enjoy such authority. Ameren had not required FERC to reach a particular outcome in the Otter Tail complaint. But without additional briefing, FERC decided that all transmission owners in MISO should have the unilateral authority to choose to fund upgrades. MISO, Inc. Otter Tail Power Co. v. MISO, Inc., 164 FERC ¶ 61,158 (Aug. 31, 2018).

Then, FERC took briefing on whether to apply that new rule retroactively from the point that this litigation began. The generators moved for rehearing on whether FERC’s new regime would lead to undue discrimination.

In a second order, FERC reaffirmed the first post-remand order and made its rule retroactive. MISO, Inc. Otter Tail Power Co. v. MISO, Inc., 169 FERC ¶ 61,233 (Dec. 20, 2019).

Finally, in response to a rehearing request regarding the retroactivity decision, FERC issued a third order affirming its decision. MISO, Inc. Otter Tail Power Co. v. MISO, Inc., 172 FERC ¶ 61,248 (Sept. 17, 2020).

C

The American Clean Power Association, an association of generators that operate in the MISO region, now petitions us to review those orders. Other generators operating in the MISO region have intervened on the Petitioner’s side. And transmission owners have intervened as Respondents in support of FERC.

The Petitioner argues that FERC failed to follow our command in Ameren to “develop a record.” It also argues that it was arbitrary and capricious for FERC to give transmission 6 owners the unilateral authority to fund power line upgrades. The Petitioner-Intervenors added a third argument: that FERC incorrectly made its decision retroactive.

II

Our jurisdiction extends only to arguments that a party raised in a rehearing application before FERC, “unless there is reasonable ground for failure so to do.” 16 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Center for Biological Diversity v. EPA
141 F.4th 153 (D.C. Circuit, 2025)
Central Hudson Gas & Electric Corporation v. FERC
138 F.4th 531 (D.C. Circuit, 2025)
Sinclair Wyoming Refining Company LLC v. EPA
101 F.4th 871 (D.C. Circuit, 2024)
Green Development, LLC v. FERC
77 F.4th 997 (D.C. Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
54 F.4th 722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-clean-power-assoc-v-ferc-cadc-2022.