Transcanada Power Marketing Ltd. v. Federal Energy Regulatory Commission

811 F.3d 1, 421 U.S. App. D.C. 1, 2015 U.S. App. LEXIS 22304, 2015 WL 9287782
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 22, 2015
Docket14-1103, 14-1104, 14-1105
StatusPublished
Cited by26 cases

This text of 811 F.3d 1 (Transcanada Power Marketing Ltd. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcanada Power Marketing Ltd. v. Federal Energy Regulatory Commission, 811 F.3d 1, 421 U.S. App. D.C. 1, 2015 U.S. App. LEXIS 22304, 2015 WL 9287782 (D.C. Cir. 2015).

Opinion

Opinion for the Court filed by Senior Circuit Judge EDWARDS.

EDWARDS, Senior Circuit Judge:

In June 2013, pursuant to section 205(d) of the Federal Power Act (“FPA”), 16 U.S.C. § 824d(d) (2012), the Independent System Operator for New England (“ISO New England”) filed a tariff revision with the Federal Energy Regulatory Commission (“Commission” or “FERC”). The tariff filing reflected ISO New England’s concern over “the region’s growing reliance on natural gas-fired generators, which can be vulnerable to supply shortages and price volatility.... [ISO New England] had found that many dual-fuel or oil-fired generators did not keep sufficient fuel supplies on hand to meet increased demand in extended or repeated periods of cold weather. Accordingly, [ISO New England] proposed [a] Winter Reliability Program [that] included an Oil Inventory Service component, which would compensate oil-fired and dual-fuel generators, selected through a bidding process, to maintain specified supplies of oil and to provide energy when system conditions were stressed.” Br. for Respondent at 3.

*3 On September 16, 2013, the Commission issued an Order Conditionally Accepting Tariff Revisions in Docket ER13-1851. This Order tentatively approved the Winter 2013-14 Reliability Program (“Program”). In this same Order, however, FERC rejected the tariff proposal to allocate costs to Regional Network Load (ie., to transmission owners) as inconsistent with cost-causation principles and directed ISO New England to submit a compliance filing that would allocate the costs of the Program to Real-Time Load Obligation (ie., to Load-Serving Entities). On October 7, 2013, in Docket ER13-2266, the Commission issued an Order Accepting Bid Results, which effectively approved the Program and the results of ISO New England’s bid-selection process. On October 15, 2013, ISO New England submitted a compliance filing that explained how it had considered and selected the bids. On April 8, 2014, FERC issued orders denying requests for rehearing of the Orders issued in Docket ER13-1851 and Docket ER13-2266. (

On June 6, 2014, Petitioners TransCana-da Power Marketing Ltd. (“TransCanada”) and the Retail Energy Supply Association filed petitions for review with this court challenging the Orders issued by FERC approving the Winter 2013-14 Reliability Program. TransCanada, which is a Load-Serving Entity, principally contends that FERC’s actions should be overturned because, inter alia, (1) there was insufficient evidence in the record to allow FERC to determine whether the cost-based Program and resulting rates were just and reasonable; (2) FERC acted in contravention of cost causation principles when it allocated the costs of the Program to Load-Serving Entities; and (3) FERC abused its discretion in failing to consolidate the proceedings in Docket Nos. ER13-1851 and ER13-2266. The Retail Energy Supply Association, whose members include Load-Serving Entities, joins TransCanada only with respect to the issue relating to the allocation of cost.

We decline to assess FERC’s conditional approval of the Program in Docket ER13-1851 because FERC made it clear that its decision was only tentative. Any alleged defects in the Program were subject to challenge by interested parties and final review by FERC in Docket ER13-2266. Indeed, that is exactly what happened.

The Commission’s decision regarding the allocation of the costs of the Program to Load-Serving Entities was a final action in Docket ER13-1851. It is therefore ripe for review. However, we find no merit in Petitioners’ challenges to the cost-allocation decision. The Commission reasonably explained that its decision, unlike the proposed alternative, adhered to cost-causation principles and agency precedent. We therefore deny the petitions for review of the cost-allocation decision in Docket ER13-1851.

In Docket ER13-2266, FERC gave its stamp of approval to the Program and found that the arrangement pursuant to which suppliers would be compensated at their as-bid price was just and reasonable. TransCanada challenges FERC’s decision in Docket ER13-2266, principally on the ground that the record upon which FERC relied is devoid of any evidence regarding how much of the Program cost was attributable to profit and risk mark-up. Trans-Canada argues that, without this information, FERC could not properly assess whether the Program’s rates were just and reasonable. We agree and thus grant in part the petition for review of Docket ER13-2266. The case is hereby remanded to FERC so that it may either offer a reasoned justification for the Order or revise its disposition to ensure that the rates *4 under the Program are just and reasonable.

Because we remand only one of the two dockets, we need not address whether the Commission abused its discretion in declining to consolidate them.

I. Background

ISO New England is a “private, nonprofit entity [that] administer[s] New England energy markets and operate[s] the region’s bulk power transmission system.” PSEG Energy Res. & Trade LLC v. FERC, 665 F.3d 203, 205-06 (D.C.Cir. 2011) (alterations in original) (quoting Blu-menthal v. FERC, 552 F.3d 875, 878 (D.C.Cir.2009)). To provide access to the transmission system, ISO New England sets rates “in a single, unbundled, grid-wide tariff.” See Braintree Elec. Light Dep’t v. FERC, 667 F.3d 1284, 1286 n. 1 (D.C.Cir.2012) (quoting NRG Power Mktg., LLC v. Me. Pub. Utils. Comm’n, 558 U.S. 165, 169 n. 1, 130 S.Ct. 693, 175 L.Ed.2d 642 (2010)). “Under its tariff, ISO[] [New England] is obligated to assure that New England’s power supply ‘conforms to proper standards of reliability.’ ” Id. (quoting ISO New England, Inc., Transmission, Markets, and Services Tariff § 1.1.3 (“Tariff’)). ISO New England must file its tariff with the Commission for approval under section 205 of the FPA. Braintree Elec. Light Dep’t v. FERC, 550 F.3d 6, 9 (D.C.Cir.2008) (citing 16 U.S.C. § 824d(d)). The Commission can reject the proposed rates only if it finds that the rates are not “just and reasonable.” Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9 (D.C.Cir.2002) (citing 16 U.S.C. § 824d(e)).

A. The Winter 2013-2014 Reliability Program

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramos v. Nielsen
N.D. California, 2025
Snakeroot Solar, LLC v. Public Utilities Commission
2025 ME 64 (Supreme Judicial Court of Maine, 2025)
United States v. Quamaine Smith
134 F.4th 248 (Fourth Circuit, 2025)
Bynoe v. Helling
D. Nevada, 2025
Sheikhalizadehjahed v. Gaudiosi
E.D. California, 2024
New Jersey Conservation Foundation v. FERC
111 F.4th 42 (D.C. Circuit, 2024)
New York State Public Service Commission v. FERC
104 F.4th 886 (D.C. Circuit, 2024)
East Texas Electric Cooperative, Inc. v. FERC
90 F.4th 579 (D.C. Circuit, 2024)
American Clean Power Assoc v. FERC
54 F.4th 722 (D.C. Circuit, 2022)
Belmont Municipal Light Department v. FERC
38 F.4th 173 (D.C. Circuit, 2022)
United States v. Laurent
33 F.4th 63 (Second Circuit, 2022)
California Public Utilities Commission v. FERC
20 F.4th 795 (D.C. Circuit, 2021)
Public Citizen, Inc. v. FERC
7 F.4th 1177 (D.C. Circuit, 2021)
PSE&G v. FERC
D.C. Circuit, 2021
International Transmission Company v. FERC
988 F.3d 471 (D.C. Circuit, 2021)
Delise Adams v. Memorial Hermann
973 F.3d 343 (Fifth Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
811 F.3d 1, 421 U.S. App. D.C. 1, 2015 U.S. App. LEXIS 22304, 2015 WL 9287782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcanada-power-marketing-ltd-v-federal-energy-regulatory-commission-cadc-2015.