PSE&G v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 2, 2021
Docket19-1091
StatusPublished

This text of PSE&G v. FERC (PSE&G v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PSE&G v. FERC, (D.C. Cir. 2021).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued January 15, 2021 Decided March 2, 2021

No. 19-1091

PUBLIC SERVICE ELECTRIC AND GAS COMPANY , PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION , RESPONDENT

NEW JERSEY BOARD OF PUBLIC UTILITIES, ET AL., INTERVENORS

Consolidated with 20-1039

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

John Longstreth argued the cause for petitioners. With him on the briefs were Cara J. Lewis, Donald A. Kaplan, Kimberly B. Frank, and Steven Nadel. William M. Keyser III entered an appearance.

Gurbir S. Grewal, Attorney General, Office of the Attorney General for the State of New Jersey, Paul Youchak, Deputy Attorney General, and Stefanie A. Brand, Director, 2 New Jersey Division of Rate Counsel, were on the brief for intervenor New Jersey Board of Public Utilities and New Jersey Division of Rate Counsel in support of petitioners. Alex Moreau, Attorney, Office of the Attorney General for the State of New Jersey, Stephen C. Pearson, and Scott H. Strauss entered appearances.

Elizabeth E. Rylander, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were David L. Morenoff, Acting General Counsel, and Robert H. Solomon, Solicitor.

Robert A. Weishaar, Jr., Kenneth R. Stark, Thomas L. Rudebusch, Bhaveeta K. Mody, Timothy G. McCormick, William F. Fields, Joseph G. Cleaver, Michael R. Engleman, Regina A. Iorii, Miles H. Mitchell, Adrienne E. Clair, and Rebecca L. Shelton were on the brief for intervenor Public Service Commission for the State of Delaware, et al. in support of respondent. Kayla Grant entered an appearance.

Before: SRINIVASAN, Chief Judge, ROGERS, Circuit Judge, and EDWARDS, Senior Circuit Judge.

Opinion for the Court by Circuit Judge ROGERS.

ROGERS, Circuit Judge: Public Service Electric and Gas Company and PPL Electric Utilities Corporation petition for review of three orders of the Federal Energy Regulatory Commission concerning cost sharing for certain upgrades to the Mid–Atlantic electricity transmission grid. In 2016, the Commission approved as just and reasonable cost allocations filed by PJM Interconnection, L.L.C. (“PJM”), the Mid– Atlantic’s regional transmission organization, for a project to improve the reliability of three nuclear power plants in New Jersey. In so doing, the Commission denied a complaint lodged 3 by Delaware and Maryland alleging a large imbalance between the costs imposed on the Delmarva transmission zone and the benefits that zone would accrue from the project. On rehearing in 2018, however, the Commission reversed course, concluding that, upon reexamination of the evidence, application of PJM’s cost–allocation method to the project violated cost–causation principles and was therefore unjust and unreasonable in violation of section 206 of the Federal Power Act, 16 U.S.C. § 824e. The Commission’s replacement cost– allocation method shifted primary cost responsibility for the project from the Delmarva zone to utilities in New Jersey.

Petitioners, PJM transmission owners, and intervenors New Jersey Board of Public Utilities and New Jersey Division of Rate Counsel (“New Jersey Agencies”) contest the rationality of the Commission’s volte–face. They contend the Commission departed from precedent without adequate explanation, made findings that are unsupported by substantial evidence, and failed to respond meaningfully to objections raised during the proceedings. For its part, the Commission, with support from a coalition of Delaware and Maryland stakeholders, maintains that it engaged in reasoned decisionmaking. We conclude the Commission reasonably decided to adopt a different cost–allocation method for the type of project at issue here and adequately explained its departure from the cost allocations it had approved in 2016. Accordingly, we deny the petitions for review.

I.

The Federal Power Act requires that the Commission ensure the rates charged by public utilities to provide electricity are “just and reasonable.” 16 U.S.C. § 824d(a). Pursuant to section 206 of the Federal Power Act, the Commission may investigate — on its own initiative or based on a third–party 4 complaint — whether an existing rate is “unjust, unreasonable, unduly discriminatory or preferential.” Id. § 824e(a). The proponent of the rate change bears the burden of proof, and, if the Commission determines that the rate is unlawful, it must establish a just and reasonable replacement rate. Id. § 824e(a), (b). Section 206 therefore “mandates a two–step procedure” whereby the Commission must “make an explicit finding that the existing rate is unlawful before setting a new rate.” Emera Me. v. FERC, 854 F.3d 9, 24 (D.C. Cir. 2017). Thus, “[w]ithout a showing that the existing rate is unlawful,” the Commission “has no authority to impose a new rate.” Id. at 25.

The Commission has long viewed the just–and–reasonable requirement to “incorporate a ‘cost–causation principle.’” Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018). That “principle requires costs ‘to be allocated to those who cause the costs to be incurred and reap the resulting benefits.’” S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 87 (D.C. Cir. 2014) (quoting Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007)). So, although the Commission need not “allocate costs with exacting precision,” the costs assessed against a party must bear some resemblance “to the burdens imposed or benefits drawn by that party.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368–69 (D.C. Cir. 2004). In practice, this means “the Commission generally may not single out a party for the full cost of a project, or even most of it, when the benefits of the project are diffuse.” BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).

Consistent with the cost–causation principle, the Commission issued “Order No. 1000” in 2011 to foster the efficient development of the transmission grid. Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, F.E.R.C. Stats. & Regs. ¶ 31,323, 5 76 Fed. Reg. 49,842 (Aug. 11, 2011), petitions for review denied, S.C. Pub. Serv. Auth., 762 F.3d 41. Among other things, Order No. 1000 requires utilities to participate in regional transmission planning and to include in their tariffs a formula “for allocating the costs of new transmission facilities selected in the regional transmission plan.” Id. at P 558, 76 Fed. Reg. at 49,929. To comply with Order No. 1000, a utility’s cost–allocation method must satisfy six criteria, the first of which embodies the cost–causation principle by requiring that costs be “allocated in a way that is roughly commensurate with benefits.” Id. at P 622, 76 Fed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alcoa Inc. v. Federal Energy Regulatory Commission
564 F.3d 1342 (D.C. Circuit, 2009)
Texas v. Environmental Protection Agency
726 F.3d 180 (D.C. Circuit, 2013)
Maine v. Federal Energy Regulatory Commission
854 F.3d 9 (D.C. Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
PSE&G v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pseg-v-ferc-cadc-2021.