California Public Utilities Commission v. FERC

20 F.4th 795
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 17, 2021
Docket20-1388
StatusPublished
Cited by1 cases

This text of 20 F.4th 795 (California Public Utilities Commission v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
California Public Utilities Commission v. FERC, 20 F.4th 795 (D.C. Cir. 2021).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued October 8, 2021 Decided December 17, 2021

No. 20-1388

CALIFORNIA PUBLIC UTILITIES COMMISSION, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION, INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Candace J. Morey argued the cause for petitioner. With her on the briefs were Arocles Aguilar and Aaron R. Jacobs-Smith.

Elizabeth E. Rylander, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor,

Ashley C. Parrish was on the brief for amicus curiae Calpine Corporation in support of neither party. 2 Before: HENDERSON and KATSAS, Circuit Judges, and GINSBURG, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge HENDERSON.

KAREN LECRAFT HENDERSON, Circuit Judge: The Federal Energy Regulatory Commission (Commission) approved California Independent System Operator Corporation’s (CAISO) proposed revision to the compensation structure for its Capacity Procurement Mechanism (CPM), a voluntary program designed to provide electric capacity necessary to maintain grid reliability within CAISO’s network. The California Public Utilities Commission (CPUC), which participated in the Commission’s proceeding, challenges the Commission’s approval of CAISO’s proposal. We grant the petition and remand with vacatur.

I. Background

The Federal Power Act, 16 U.S.C. §§ 791a et seq., governs the transmission and wholesale marketing of electricity in interstate commerce and grants the Commission jurisdiction to regulate these activities in the public interest, see id. § 824(a), (b). Section 205 of the Act requires that “[a]ll rates and charges . . . by any public utility for or in connection with the transmission or sale of electric energy” must be “just and reasonable” and not “undu[ly] preferen[tial].” Id. § 824d(a), (b). A public utility seeking to change its rate structure must file the proposed changes with the Commission and bears “the burden of proof to show that the increased rate or charge is just and reasonable.” Id. § 824d(d), (e). “When acting on a public utility’s rate filing under section 205, the Commission undertakes ‘an essentially passive and reactive role’ and restricts itself to evaluating the confined proposal.” Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 3 2017) (per curiam) (quoting City of Winnfield v. FERC, 744 F.2d 871, 875–76 (D.C. Cir. 1984)).

CAISO is the regional independent system operator that controls (but does not own) the transmission grid in California. See generally Sac. Mun. Util. Dist. v. FERC, 474 F.3d 797, 798–99 (D.C. Cir. 2007). In this role, CAISO has a responsibility to ensure sufficient independent generating resources—such as nuclear power plants, solar farms and natural-gas-fired power plants—are in place to meet California’s present-day and future electricity demands. This is accomplished through the supply and purchase of electric “capacity,” whereby a generating resource “commit[s] to produce electricity or forgo the consumption of electricity when required” by a load-serving entity—usually the public utility that delivers electricity to end users—creating “a kind of options contract” between the two parties. Advanced Energy, 860 F.3d at 659.

CAISO, working in conjunction with the CPUC, administers a resource adequacy program designed to ensure that there is sufficient electric generation in CAISO’s markets to meet consumer demands under all but the most extreme conditions. The resource adequacy program requires utilities to procure enough capacity to meet their forecasted peak load plus a reserve margin set by the CPUC. Resource adequacy obligations are generally met through voluntary bilateral agreements between utilities and generating resources.

Backstop measures come into play if voluntary arrangements turn out to be insufficient to meet resource adequacy obligations. When CAISO determines that there is an unmet resource adequacy or reliability need, it may rely on its capacity procurement authority under the CPM provisions of its tariff to designate specific generating resources to provide 4 additional capacity. Generating resources seeking a CPM designation can enter into a competitive solicitation process. Entry into the CPM solicitation process is voluntary but if a resource submits a bid, and CAISO accepts the bid, the resource must accept the CPM designation. If CAISO unilaterally offers a CPM designation to a resource that did not participate in the solicitation process, that resource has the discretion to decline. The term of a CPM designation can range from a minimum of 30 days up to 12 months.

The central issue before us involves compensation under the CPM. When CAISO initially proposed the CPM program in 2010, it sought to compensate resources at a minimum price of $55 per kilowatt-year (kW-year), which was derived from the going-forward costs—defined as fixed operations and maintenance costs, ad valorem taxes and administrative costs, including insurance—of a reference resource plus a 10% adder. 1 A resource with costs above that price would have been permitted to submit a cost-justified bid to the Commission. The Commission declined to approve CAISO’s proposal, citing concerns that the use of going-forward costs alone could “deny resources a reasonable opportunity to recover fixed costs” and that CAISO had not sufficiently explained “how the use of going-forward costs for CPM compensation will provide incentives or revenue sufficiency for resources to perform long-term maintenance or make [environmental] improvements.” Cal. Indep. Sys. Operator Corp., 134 FERC ¶ 61,211, ¶ 57 (2011) (hereinafter 2011 CPM Order). The Commission instructed its staff to convene a technical conference to address the Commission’s concerns and discuss alternative compensation methodologies. Id. at ¶¶ 55, 58–59. In 2012, after the technical conference, CAISO proposed, and

1 For the reference resource, CAISO used a 50 megawatt (MW) simple-cycle, gas-fired unit built by a merchant generator. 5 the Commission approved, a fixed CPM capacity price— subject to a four-year expiration date—of $67.50 per kW-year for two years, which increased by five per cent to $70.88 for the remaining two years. See Cal. Indep. Sys. Operator Corp., 138 FERC ¶ 61,112, ¶¶ 10, 18–19 (2012).

In 2015, as the 2012 order was set to expire, CAISO proposed the now operative CPM compensation structure, which relies on competitive bidding. Under this structure, a resource can bid up to a “soft-offer cap” of a fixed-dollar amount—$6.31 per kW-month (or $75.68 per kW-year). The soft-offer cap is based on the going-forward costs of a reference resource plus a 20% adder. 2 CAISO reasoned that the 20% adder would allow resources with costs higher than the reference resource to recover their going-forward costs and additional fixed costs, as well as providing investment incentives. In the event that the soft-offer cap does not allow a resource to recover its going-forward costs, that resource can submit a cost-justified filing to the Commission for a higher rate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall v. Saul
District of Columbia, 2022

Cite This Page — Counsel Stack

Bluebook (online)
20 F.4th 795, Counsel Stack Legal Research, https://law.counselstack.com/opinion/california-public-utilities-commission-v-ferc-cadc-2021.