Maine Public Service Company v. Federal Energy Regulatory Commission, Central Maine Power Company, Intervenor

964 F.2d 5, 296 U.S. App. D.C. 5
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 24, 1992
Docket91-1118
StatusPublished
Cited by25 cases

This text of 964 F.2d 5 (Maine Public Service Company v. Federal Energy Regulatory Commission, Central Maine Power Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maine Public Service Company v. Federal Energy Regulatory Commission, Central Maine Power Company, Intervenor, 964 F.2d 5, 296 U.S. App. D.C. 5 (D.C. Cir. 1992).

Opinion

Opinion for the court filed by Circuit Judge RANDOLPH.

RANDOLPH, Circuit Judge:

This case is here on Maine Public Service Company’s petition for review of the Federal Energy Regulatory Commission’s acceptance for filing of an unexecuted transmission service agreement increasing the rate for Central Maine Power Company’s transmission service to Maine Public from *7 $1.6866 per kW/year to $15.02 per kW/ year.

I

Part of the controversy stems from arrangements made in connection with the construction of William Wyman Unit No. 4, a 600 megawatt electric generating unit in Yarmouth, Maine (where Central Maine is located). Central Maine proposed the project in 1973, inviting other New England utilities to become joint owners on condition that they join the New England Power Pool (“NEPOOL”). 1 By November 1974, Maine Public, a privately owned electric utility, and nine other utilities had accepted Central Maine’s offer. At this time, the participants in this joint venture entered into a separate “Transmission Agreement.” Under this agreement, Central Maine would charge these utilities for pool transmission facility (“PTF”) deliveries of electric power, as defined in the NEPOOL Agreement, at the NEPOOL rate. Non-PTF deliveries, if any, were to be charged at “Central Maine’s applicable rate from time to time in effect.” Transmission Agreement § 3(c).

Wyman 4 became operational in 1978. By then, all of the owners except Maine Public had joined NEPOOL. Maine Public said it wanted to wait until October 31, 1980. The other owners agreed to the extension. Central Maine sent Maine Public a letter, stating that it would charge Maine Public for its Wyman 4 entitlements according to Rate Schedule No. 54, which meant $1.6866 per kW/year.

With its self-imposed deadline fast approaching, on October 29,1980, Maine Public decided to put off joining NEPOOL for another two years. The other owners again acquiesced, and Central Maine continued to charge Maine Public the rate set out in the 1978 letter. In 1982, Maine Public again deferred membership. The decade of the 1980’s passed without Maine Public becoming a member of NEPOOL.

Finally, in 1990, Central Maine filed an unexecuted transmission service agreement with the Commission which included a proposed increase of Maine Public’s Wyman 4 entitlement rate to $15.02 per kW/year. In an accompanying letter to the Commission and in its supplemental filings, Central Maine explained that it was seeking a “compensatory” rate because it appeared that Maine Public was never going to join NEPOOL. Central Maine’s proposed rate was a “rolled-in” rate, reflecting the costs to operate the entire transmission network, rather than either of the lower rates prescribed by the NEPOOL Agreement or Rate Schedule No. 54. See Fort Pierce Utils. Auth. v. FERC, 730 F.2d 778, 782 (D.C.Cir.1984); Public Serv. Co. of New Hampshire, 49 F.E.R.C. ¶ 61,030, at 61,116 (1989). The Commission ultimately approved Central Maine’s proposed rate, both in an original order and on rehearing. See Central Maine Power Co., 53 F.E.R.C. ¶ 61,465 (1990) (Order); Central Maine Power Co., 54 F.E.R.C. ¶ 61,206 (1991) (Order on Rehearing).

II

Maine Public throws up all sorts of arguments against the Commission’s decision. Some are made for the first time in this court and, for that reason, must be rejected. Others violate the first principle of advocacy: in order to persuade a court to agree with one’s argument, the argument must be made comprehensible. It comes as somewhat of a surprise that out of this confusing mass several meritorious contentions are able to emerge. The first contention we address is not, however, one of these.

1. As Maine Public sees it, Central Maine’s 1978 letter stating that the rate would be $1.6866 per kW/year amounted to a fixed rate contract. If this were correct, the Mobile-Sierra doctrine would preclude Central Maine from unilaterally filing a different rate with the Commission in the normal course. See United Gas Pipe Line

*8 Co. v. Mobile Gas Serv. Corp., 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373 (1956); FPC v. Sierra Pacific Power Co., 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956). In a ruling adequately supported in fact and law, the Commission decided that the letter was not a fixed rate contract. When Maine Public signed the 1974 Transmission Agreement it knew that Central Maine would be charging it for its Wyman 4 entitlements at Central Maine’s “applicable rate from time to time in effect” until Maine Public joined NEPOOL. Transmission Agreement § 3(c). When Wyman 4 came on line, Central Maine informed Maine Public of its “applicable rate,” namely, Rate Schedule No. 54. The letter itself, which we set forth in full in the margin, 2 bore none of the characteristics of a fixed rate contract. It was not executed. It said nothing about duration, as one would expect in a fixed rate contract. The schedule to which the letter refers, No. 54, was itself an interim rate explicitly subject to change by Central Maine. To the Commission, it therefore appeared that this brief letter did not fix a rate for all time, subject only to revision under the “almost insurmountable” Mobile-Sierra standard. See Order on Rehearing, 54 F.E.R.C. at 61,613-14 (quoting Kansas Cities v. FERC, 723 F.2d 82, 87-88 (D.C.Cir.1983)). There is no basis for disturbing the Commission’s interpretation of the letter. Union Elec. Co. v. FERC, 890 F.2d 1193, 1195-96 (D.C.Cir.1989); Ohio Power Co. v. FERC, 744 F.2d 162, 166 (D.C.Cir.1984).

2. Apart from the fixed-rate question, Maine Public objects to the Commission’s approval of Central Maine’s use of “rolled-in” methodology to reach the new rate of $15.02 per kW/year. Rolled-in rates are based on the costs for the entire transmission network; the theory is that when the system is integrated, all of the facilities in the system contribute to each use of the system. Fort Pierce Utils. Auth. v. FERC, 730 F.2d 778, 782 (D.C.Cir. 1984); Public Serv. Co. of New Hampshire, 49 F.E.R.C. ¶ 61,030, at 61,116 (1989). Integration has been described as higher and lower voltage facilities operating in an interconnected and parallel way. This improves the reliability of the system because the parallel paths of electricity can act as backups for the primary path. Sierra Pacific Power Co. v. FERC, 793 F.2d 1086, 1088 (9th Cir.1986). The Commission has a longstanding policy in favor of rolled-in rates for integrated systems. Otter Tail Power Co., 12 F.E.R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bungie Inc v. Aimjunkies.com
W.D. Washington, 2023
California Public Utilities Commission v. FERC
20 F.4th 795 (D.C. Circuit, 2021)
Sierra Club v. Federal Energy Regulatory Commission
867 F.3d 1357 (D.C. Circuit, 2017)
Nacs v. Board of Governors of the Federal Reserve System
958 F. Supp. 2d 85 (District of Columbia, 2013)
Sabinson v. Dartmouth College Trustee
2007 DNH 141 (D. New Hampshire, 2007)
California Dept of W v. Ferc
Ninth Circuit, 2007
Taite v. Morin
D. New Hampshire, 2007
Ralph v. US Dept. of Labor
2004 DNH 136 (D. New Hampshire, 2004)
Potomac Elec Power v. FERC
D.C. Circuit, 2000
We MA Elec Co v. FERC
D.C. Circuit, 1999

Cite This Page — Counsel Stack

Bluebook (online)
964 F.2d 5, 296 U.S. App. D.C. 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maine-public-service-company-v-federal-energy-regulatory-commission-cadc-1992.