Opinion for the court filed by Chief Judge J. SKELLY WRIGHT.
J. SKELLY WRIGHT, Chief Judge.
This is a petition for review of the Federal Power Commission’s
resolution of a variety of disputes stemming from efforts by the Town of Norwood, Massachusetts, to discontinue purchasing wholesale power from the Boston Edison Company and commence purchasing it at a lower rate from the New England Power Company (NEP-CO), while using Edison’s transmission facilities to “wheel”
the power thus purchased. The most important issue raised concerns the intersection of the Supreme Court’s
Mobile-Sierra
doctrine
and the
nondiscrimination requirement of Section 205(b) of the Federal Power Act, 16 U.S.C. § 824d(b) (1976). For the reasons discussed below, we conclude that the case must be remanded to the FERC so that the record may be reopened and the issues reconsidered in light of this court’s recent decision in
Boroughs of Chambersburg et al. v. FERC,
188 U.S.App.D.C. 310, 580 F.2d 573 (1978)
(per
curiam), as well as the instant opinion. Because the result on remand may alter or moot some of the other issues raised before this court, we express no opinion as to those other issues.
I
In October 1972 the Town of Norwood informed Edison of its intention to cease purchasing its wholesale electricity requirements from the company “as soon as possible after January 1, 1973” and become an all-requirements customer of NEPCO, utilizing Edison transmission lines to wheel the NEPCO power. Joint Appendix (JA) 260. On December 8, 1972 Edison wrote back stating that it did not have on file a transmission rate appropriate for such wheeling, that it was studying the Town’s plan but was as of then “unable to commit to any particular course of action,” that were the Town to terminate its all-requirements contract with Edison as proposed the company would suffer revenue losses of about $4.75 million, and that it would expect to be compensated for those losses in view of the Town’s failure to comply with advance notice requirements set forth in a tariff settlement to which the Town had been a party. JA 263 — 270.
In a March 8, 1973 letter to Edison the Town stated that NEPCO was willing to supply its needs commencing in November 1974, challenged the Edison figure for termination losses, sought ways of avoiding liability for those losses, and requested terms for the wheeling services it needed. JA 271-272. Edison responded briefly on April 10, JA 273, and more fully on June 26, JA 274-276. In the latter communication the company stated that it would be willing to file a wheeling rate with the Federal Power Commission “if we are definitely advised by Norwood * * * of the Town’s committed plans for changes in the service it desires * * * JA 274. The letter went on to state that Edison intended to seek from the Commission an order defining any Edison obligation to provide wheeling services and to urge the Commission to determine that it would not be in the public interest for Edison to wheel power for the Town.
The company did pledge to provide interim wheeling services if the Commission had not resolved the matter by the time the Town was committed to begin taking power from NEPCO. JA 275. Several months later the company offered to ensure that the Town would not suffer any loss as a result of Edison’s efforts to secure a Commission determination that it was not obligated to furnish wheeling services. In particular, the company indicated that were it successful before the Commission it would either wheel power voluntarily for Norwood until such time as the Town was able to terminate any contract with NEP-
CO without penalty or hold Norwood harmless against any such penalty.
Norwood did not follow up on this offer. Indeed, the parties never got much closer to the bargaining table — perhaps because of the events detailed in the next paragraph.
Just after the Town of Norwood’s first letter, Edison entered into an entirely unrelated agreement to wheel power for NEP-CO, which had become the wholesale supplier for what is termed Quincy-Weymouth area.
The Edison-NEPCO agreement called for wheeling services substantially similar to those sought by the Town of Norwood at a price amounting to $6.36 per kw per year, JA 648, or about 30 percent less than the amount which Edison’s correspondence suggested that Norwood would have to pay.
Although the Edison-NEPCO contract was executed on November 1, 1972, it was not placed on file with the Commission until May 7, 1973. Accordingly, it remained unknown to Norwood (and to the general public) until six months after its effective date.
In June 1973 Norwood sought to intervene in the Edison-NEPCO rate filing, arguing that to prevent undue discrimination it should be given the right to purchase wheeling services at the same rate. The Commission accepted the filing on August 24,1973, and instituted an investigation of the rate under Section 206(a) of the Federal Power Act, 16 U.S.C. § 824e(a) (1976). Norwood was permitted to intervene, JA 457 — 461. Subsequently, NEPCO was permitted to intervene as well.
On March 5, 1974 Edison commenced a separate proceeding before the Commission — this one relating directly to the Town of Norwood. JA 471-520. Edison sought a declaratory order that (1) it was not legally obligated to furnish wheeling services to the Town, (2) the Town had failed to give the required notice of its proposed change of suppliers, (3) Edison had properly computed the adverse financial impact that would result if the Town terminated its all-requirements contract without giving adequate notice to the company, and (4) Edison’s method of calculating the wheeling rate that would apply to the Town was appropriate. JA 471^490.
In September 1974, over the objection of Norwood, the two Commission proceedings were consolidated. Joint hearings began shortly thereafter. An initial decision was issued on May 21, 1976 by an Administrative Law Judge. JA 575-588. The parties excepted to various portions of that decision, and on December 7,1976 the Commission reversed in part and affirmed in part. JA 646-666. Specifically, it concluded (1) that the low wheeling rate in the Edison-NEPCO contract could not be increased without NEPCO’s consent notwithstanding Edison’s assertion that the rate was non-compensatory and unreasonable; (2) that Norwood had no right under the Federal Power Act to demand wheeling at a similarly low rate; (3) that Edison was willing to
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion for the court filed by Chief Judge J. SKELLY WRIGHT.
J. SKELLY WRIGHT, Chief Judge.
This is a petition for review of the Federal Power Commission’s
resolution of a variety of disputes stemming from efforts by the Town of Norwood, Massachusetts, to discontinue purchasing wholesale power from the Boston Edison Company and commence purchasing it at a lower rate from the New England Power Company (NEP-CO), while using Edison’s transmission facilities to “wheel”
the power thus purchased. The most important issue raised concerns the intersection of the Supreme Court’s
Mobile-Sierra
doctrine
and the
nondiscrimination requirement of Section 205(b) of the Federal Power Act, 16 U.S.C. § 824d(b) (1976). For the reasons discussed below, we conclude that the case must be remanded to the FERC so that the record may be reopened and the issues reconsidered in light of this court’s recent decision in
Boroughs of Chambersburg et al. v. FERC,
188 U.S.App.D.C. 310, 580 F.2d 573 (1978)
(per
curiam), as well as the instant opinion. Because the result on remand may alter or moot some of the other issues raised before this court, we express no opinion as to those other issues.
I
In October 1972 the Town of Norwood informed Edison of its intention to cease purchasing its wholesale electricity requirements from the company “as soon as possible after January 1, 1973” and become an all-requirements customer of NEPCO, utilizing Edison transmission lines to wheel the NEPCO power. Joint Appendix (JA) 260. On December 8, 1972 Edison wrote back stating that it did not have on file a transmission rate appropriate for such wheeling, that it was studying the Town’s plan but was as of then “unable to commit to any particular course of action,” that were the Town to terminate its all-requirements contract with Edison as proposed the company would suffer revenue losses of about $4.75 million, and that it would expect to be compensated for those losses in view of the Town’s failure to comply with advance notice requirements set forth in a tariff settlement to which the Town had been a party. JA 263 — 270.
In a March 8, 1973 letter to Edison the Town stated that NEPCO was willing to supply its needs commencing in November 1974, challenged the Edison figure for termination losses, sought ways of avoiding liability for those losses, and requested terms for the wheeling services it needed. JA 271-272. Edison responded briefly on April 10, JA 273, and more fully on June 26, JA 274-276. In the latter communication the company stated that it would be willing to file a wheeling rate with the Federal Power Commission “if we are definitely advised by Norwood * * * of the Town’s committed plans for changes in the service it desires * * * JA 274. The letter went on to state that Edison intended to seek from the Commission an order defining any Edison obligation to provide wheeling services and to urge the Commission to determine that it would not be in the public interest for Edison to wheel power for the Town.
The company did pledge to provide interim wheeling services if the Commission had not resolved the matter by the time the Town was committed to begin taking power from NEPCO. JA 275. Several months later the company offered to ensure that the Town would not suffer any loss as a result of Edison’s efforts to secure a Commission determination that it was not obligated to furnish wheeling services. In particular, the company indicated that were it successful before the Commission it would either wheel power voluntarily for Norwood until such time as the Town was able to terminate any contract with NEP-
CO without penalty or hold Norwood harmless against any such penalty.
Norwood did not follow up on this offer. Indeed, the parties never got much closer to the bargaining table — perhaps because of the events detailed in the next paragraph.
Just after the Town of Norwood’s first letter, Edison entered into an entirely unrelated agreement to wheel power for NEP-CO, which had become the wholesale supplier for what is termed Quincy-Weymouth area.
The Edison-NEPCO agreement called for wheeling services substantially similar to those sought by the Town of Norwood at a price amounting to $6.36 per kw per year, JA 648, or about 30 percent less than the amount which Edison’s correspondence suggested that Norwood would have to pay.
Although the Edison-NEPCO contract was executed on November 1, 1972, it was not placed on file with the Commission until May 7, 1973. Accordingly, it remained unknown to Norwood (and to the general public) until six months after its effective date.
In June 1973 Norwood sought to intervene in the Edison-NEPCO rate filing, arguing that to prevent undue discrimination it should be given the right to purchase wheeling services at the same rate. The Commission accepted the filing on August 24,1973, and instituted an investigation of the rate under Section 206(a) of the Federal Power Act, 16 U.S.C. § 824e(a) (1976). Norwood was permitted to intervene, JA 457 — 461. Subsequently, NEPCO was permitted to intervene as well.
On March 5, 1974 Edison commenced a separate proceeding before the Commission — this one relating directly to the Town of Norwood. JA 471-520. Edison sought a declaratory order that (1) it was not legally obligated to furnish wheeling services to the Town, (2) the Town had failed to give the required notice of its proposed change of suppliers, (3) Edison had properly computed the adverse financial impact that would result if the Town terminated its all-requirements contract without giving adequate notice to the company, and (4) Edison’s method of calculating the wheeling rate that would apply to the Town was appropriate. JA 471^490.
In September 1974, over the objection of Norwood, the two Commission proceedings were consolidated. Joint hearings began shortly thereafter. An initial decision was issued on May 21, 1976 by an Administrative Law Judge. JA 575-588. The parties excepted to various portions of that decision, and on December 7,1976 the Commission reversed in part and affirmed in part. JA 646-666. Specifically, it concluded (1) that the low wheeling rate in the Edison-NEPCO contract could not be increased without NEPCO’s consent notwithstanding Edison’s assertion that the rate was non-compensatory and unreasonable; (2) that Norwood had no right under the Federal Power Act to demand wheeling at a similarly low rate; (3) that Edison was willing to
wheel power for Norwood, and therefore that the company’s request for a declaratory order that it was not compelled to do so was moot; (4) that Norwood had failed to comply with the applicable notice requirements, that that failure was not excused by the difficulty of obtaining a wheeling commitment from Edison, and that Edison had neither waived those requirements nor discriminated unlawfully against Norwood by permitting prior customers to terminate on less notice; and (5) that Edison’s calculations of adverse impact and wheeling rates were, with certain modifications, proper. Various motions for rehearing were filed, initially granted, and ultimately denied. JA 667-750. Thereafter, Norwood filed this appeal seeking a determination that the Commission erred (a) in failing to find that Edison had wrongfully discriminated against the Town; (b) in finding that the Town would be answerable for any adverse impact to Edison caused by its failure to give adequate notice of committed plans to terminate; and (c) in finding that Edison’s methods of computing adverse impact and wheeling rates were just and reasonable. We deal here with only the discrimination issue.
II
The framework in which Norwood’s discrimination claim must be resolved is set by two Supreme Court decisions and Section 205(b) of the Federal Power Act. The two
decisions
— United
Gas Pipe Line Co. v. Mobile Gas Service Corp.,
350 U.S. 332, 76 S.Ct. 373,100 L.Ed. 373 (1956), and
FPC v. Sierra Pacific Power Co.,
350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956) — hold that, under parallel provisions of the Natural Gas and Federal Power Acts, regulated suppliers cannot unilaterally increase the rates charged to customers whose contracts specify fixed rates. In
Mobile
the Court emphasized the need for orderly planning and stable power supply arrangements and the role in meeting that need which can be played by fixed-price contracts. It concluded that denying to suppliers the right through unilateral action to alter contractually set rates would preserve the integrity and reliability of contracts without impairing the power of the Commission to modify rates — whether contractually set or not— where the public interest so requires. 350 U.S. at 344, 76 S.Ct. 373. In
Sierra
the Court went on to indicate three circumstances under which the Commission might conclude that a rate set by contract may be found contrary to the public interest and therefore revised. The mere fact that the rate produces less than a fair return is insufficient, the Court said. Rather “the rate [must be] so low as to adversely affect the public interest — as where it might impair the financial ability of the public utility to continue its service, cast upon other consumers an excessive burden, or be unduly discriminatory.” 350 U.S. at 355, 76 S.Ct. at 372. Together, the two cases make it crystal clear that a heavy burden must be met before a customer who has negotiated a fixed-price contract can be deprived against his will of the benefits of his bargain.
Section 205(b) intersects with this doctrine by adding an independent prohibition against discrimination. It states:
(b) Preference or advantage unlawful
No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.
16 U.S.C. § 824d(b) (1976). In addition, Section 205(a) requires that rates be “just and reasonable.” 16 U.S.C. § 824d(a) (1976).
As this court observed in
Boroughs of Chambersburg et al.
v.
FERC, supra,
a tension arises between
Mobile-Sierra
and Section 205(b) whenever there exits a group of customers some of whom are guaranteed
rather low rates by fixed-price contracts while others who are similarly situated save for the absence of such contracts are charged more. 188 U.S.App.D.C. at 314, 580 F.2d at 577.
See also Towns of Alexandria, Minn., et a 1. v. FPC,
181 U.S.App.D.C. 83, 87-93, 555 F.2d 1020, 1024-1030 (1977). Where this occurs, there are three alternatives: (1) the lower, contractually fixed rate can be revised upward to a reasonable and compensatory level and offered to all customers; (2) the lower, contractually fixed rate can be offered to all customers; or (3) a difference in rates can be tolerated by permitting the contractual customer to receive his bargained-for rate while charging the others reasonable and compensatory rates.
Each alternative is not without its drawbacks. The first deprives the contracting party of a rate upon which he is likely to have relied and undermines the entire purpose of fixed-rate contracts. The second will sometimes place a severe burden on the utility — so much so that it may well decline in the future to enter into any fixed-rate contracts.
And the third sanctions a difference in treatment not immediately reconcilable with the Federal Power Act.
In
Chambersburg
we chose the third alternative under circumstances where the difference in rates charged to various customers was “due
solely
to the fact that [certain low rate customers] were protected by the
Mobile-Sierra
doctrine * * 188 U.S.App.D.C. at 314, 580 F.2d at 577 (emphasis in original).
We were careful to limit that holding to situations in which
“nothing else ’’
had been demonstrated; and we specifically “intimate[d] no view whatever concerning the additional factors necessary to constitute a violation of § 205(b).”
Id.
at 315, 580 F.2d at 578 (emphasis in original). We thus made it quite clear that the mere presence of a
Mobile-Sierra
contract will not automatically shield any and all discriminatory treatment from attack under Section 205(b) of the Federal Power Act. Rather, that section remains an independent force which must be accommodated.
In the instant case, we conclude that the Commission — which of course acted prior to our
Chambersburg
decision — did not arrive at an adequate accommodation. It first determined that the Edison-NEPCO wheeling rate was insulated from unilateral change by Edison, and then applied the three-part
Sierra
test
to determine whether the public interest required that the rate be increased by the Commission acting under Section 206(a).
It found that
the low NEPCO rate would not (1) affect Edison’s capacity to continue in operation, (2) impose an excessive burden on other Edison customers, or (3) be unduly discriminatory for purposes of that test.
JA 658-659. Accordingly, it concluded that the Edison-NEPCO rate could be changed neither by Edison nor by the Commission. Having found a
Mobile-Sierra
shield, the Commission proceeded to give rather short shrift to the Town of Norwood’s argument that under Section 205(b) the low NEPCO rate must be extended to other similarly situated customers. In its original opinion it stated:
Finally, we must reject Norwood’s contention that all similar rates should be lowered to the level of the fixed-rate Quincy-Weymouth Agreement. Having previously made the finding that, since Edison’s other jurisdictional customers should only be paying just and reasonable rates, there is no undue discrimination from this one contract which is governed by the
Sierra-Mobile
doctrine, Norwood has not been aggrieved. Remedies which might ordinarily be available to the Commission under the Federal Power Act are limited in the
Sierra-Mobile
context.
JA 659. Subsequently, when it denied motions for rehearing, it reasoned that its obligation was to set just and reasonable rates, that the Edison-NEPCO rate was not just and reasonable, and therefore that it was not obligated to require Edison to extend that rate to Norwood. JA 748.
In our view, the Commission approach comes altogether too close to reading Section 205(b) out of the Federal Power Act in cases where there is a
Sierra-Mobile
contract. Nothing in the
Mobile
and
Sierra
cases requires such a result. Those decisions merely specify that heavy burdens must be met before contractually fixed low rates may be increased without the consent of the customer; they do not deal with the possibility that the presence of such low rates may require that other rates be lowered to prevent undue discrimination. And this possibility is, in our judgment, a genuine one. Indeed, it may in some circumstances be the only way of reconciling the policies favoring fixed-rate contracts which motivate the
Mobile-Sierra
doctrine with the concerns with fairness and avoidance of competitive advantage which underlie Section 205(b).
We do not, of course, assert that contractually fixed rates must generally be extended to all who later seek them.
Chambersburg
held just the opposite, and for sound reasons. The process of bargaining over contractual terms is necessarily a technique for risk allocation. Where several customers have bargained with a utility over a period of time, it is quite likely that the contracts which result will differ. Customers’ needs may vary, as will their general level of risk aversion and the types of risk to which they are most averse. They may have different projections about likely cost changes, technological advances, or demand fluctuations. And their bargaining power is likely to vary as well.
Chambers-burg
stands for the proposition that when there is no reason to question what occurred at the contract formation stage, the parties may be required to live with their bargains as time passes and various projections about the future are proved correct or incorrect.
In the present case, however, there are allegations wholly different from those in
Chambersburg
— allegations which go to the fairness and good faith of the parties at the contract formation stage. In particular, Norwood challenges the very granting of the low rate to NEPCO in the original contract. It asserts that the wheeling agreement was a “sweetheart” deal negotiated at a time when the two companies were involved in merger discussions.
The Commission, while apparently somewhat perplexed by the source of and rationale for the low and somewhat unusual rate, did not really explore it.
Yet surely neither
Mobile-Sierra
nor our
Chambersburg
decision permits a utility to use a fixed-rate contract as a device to render unassailable an otherwise prohibited undue preference. On the contrary, if such discrimination can be demonstrated, Section 205(b) requires that every effort be made to eliminate it.
The quest for an appropriate means of doing so may well be difficult. The Supreme Court’s
Sierra
test
states that certain forms of undue discrimination can be grounds for disturbing the bargain reached in a fixed-rate contract. Clearly this does not mean that the simple fact that parties protected by such a contract pay less than those not so protected is grounds for revision, for if it did
Sierra
would provide scant protection to the contracting process. Nor do we think it can mean that in every case where there is evidence of something beyond a mere difference of price — evidence clearly establishing undue discrimination or an undue preference — the proper remedy will necessarily be to increase the contractually set, lower rate. It may well be that the customer who benefits from that rate has engaged in good faith in precisely the sort of reliance and long-range planning which
Mobile-Sierra
is intended to protect; and where that can be shown, there is no reason to deprive that customer of the benefit of his bargain merely because the utility has acted to disfavor someone else.
In our judgment, the undue discrimination language in the
Sierra
test merely means that a fixed rate
may
be increased in the presence of undue discrimination if doing so
is otherwise consistent
with the policies motivating the
Mobile-Sierra
doctrine.
In other words, there is no universal rule as
to which rate should be altered in those cases where a valid claim of undue discrimination is raised. Rather, the result turns on the particular facts. If the preference for protecting contractual arrangements that underlies
Mobile-Sierra
seems squarely applicable, discrimination will have to be remedied by reducing the higher rate.
On the other hand, if there is some particular reason to depart from that preference — as where there is evidence of some sort of collusive behavior among the contracting parties — it may be more appropriate to conclude that the contractual customer has no entitlement to his fixed rate and that upward revision is therefore appropriate.
In the present case, we conclude that the proper disposition is to remand the
case to the Commission so that the administrative record may be reopened and Nor-wood’s discrimination claims reconsidered in light of the principles announced in this opinion and in
Chambersburg.
We do so, of course, without expressing any view of the underlying facts or merits beyond the observation that they are in need of further development. And we emphasize that on remand the Commission will have open to it an array of possible remedies and conclusions. In particular, it may conclude that Norwood has failed to produce sufficient evidence to distinguish the present case from
Chambersburg,
and therefore deny relief. Or it may find that there has been undue discrimination and then explore whether the appropriate response is a revision of the Edison-NEPCO agreement or a reduction in the rate offered to Norwood. The choice in the first instance lies with the Commission.
Remanded.