Florida Power & Light Company v. Federal Energy Regulatory Commission

660 F.2d 668, 1981 U.S. App. LEXIS 16251, 1981 WL 638553
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 6, 1981
Docket80-5259
StatusPublished
Cited by31 cases

This text of 660 F.2d 668 (Florida Power & Light Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Power & Light Company v. Federal Energy Regulatory Commission, 660 F.2d 668, 1981 U.S. App. LEXIS 16251, 1981 WL 638553 (5th Cir. 1981).

Opinion

R. LANIER ANDERSON, III, Circuit Judge:

The question petitioner Florida Power & Light Company (“FP&L”) asks us to answer is whether the Federal Energy Regulatory Commission (“Commission”) has the authority to compel FP&L to file a tariff including an FP&L policy relating to the availability of electric transmission service. FP&L’s position is that filing such a tariff in effect would require FP&L to offer electric transmission service to all customers and would convert it into a common carrier for such service. FP&L argues that this amounts to compelled wheeling, which is beyond the authority of the Commission. 1 The Commission, supported by the intervenors, 2 counters that no wheeling has been *670 compelled at all and that it has merely enforced a provision of its regulations specifying the information to be included in rate filings. FP&L’s grievance arises out of two orders which were issued as a part of a larger, and still on-going, proceeding. Docket No. ER78-19, et al. 3 We conclude that FP&L has in effect been made to assume common carrier status and that the Commission had no authority to order the tariff and policy be filed. Therefore, we reverse.

I. FACTS

FP&L is the largest electric utility in the State of Florida with a service area predominantly in the eastern and southern parts of Florida. Together with Florida Power Corporation, Florida’s second largest electric utility, FP&L’s transmission facilities cover nearly all of peninsular Florida. Use of these transmission facilities is frequently necessary for smaller municipally and cooperatively owned utilities, such as intervenors, to obtain electric power to supplement their own production or to obtain base-load power more economically than could be produced by the smaller utilities. The need for smaller utilities to have access to transmission service has increased in recent years and, for some, economic survival may depend on such access.

In May, 1978, FP&L filed a rate schedule for interchange transmission service for the municipal utility of Homestead, Florida. 4 Shortly thereafter, FP&L filed a second such rate schedule for the municipal utility of Fort Pierce, Florida. 5 These rate proceedings were consolidated with the pending proceeding in Docket No. ER78-19, et al.

On June 6, 1978, the Commission staff moved to compel- FP&L to file amended schedules governing the interchange transmission service provided to Homestead and Fort Pierce. The staff requested that the schedules be modified to include a company policy, enunciated by an FP&L vice president, Mr. Ernest Bivens, regarding the availability of transmission services. 6 This statement of policy was sworn, prepared testimony filed in Docket No. ER77-175 as rebuttal to certain staff assertions that FP&L had unduly discriminated among potential users of its transmission services. 7 *671 Mr. Bivens listed four criteria on which FP&L conditions the availability of transmission services:

Q. Does the failure of FPL to file a generally applicable transmission tariff reflect any intention by FPL to preclude neighboring utilities from obtaining transmission service?

A. Most emphatically not. We are willing to provide transmission service when:

1. The specific potential seller and buyer are contractually identified;

2. The magnitude, time and duration of the transaction are specified prior to the commencement of the transmission;

3. It can be determined that the transmission capacity will be available for the term of the contract; and

4. ' The rate for such service is sufficient to compensate FPL for its costs.

(J.A. p. 2207, quoting from Docket No. ER77-175, transcript p. 118). The staff further requested that FP&L be required to include this statement of policy in all future transmission service agreements.

The Commission deferred action on the staff motion for approximately a year and a half. During the interim, FP&L filed 16 additional interchange transmission service schedules, each of which was accepted for filing, suspended, and consolidated into Docket No. ER78-19, et a/. 8 Some of these filings were to amend previously filed rate schedules. Each of these schedules provided for interchange transmission service at the identical, postage-stamp rate, 9 with supporting evidence based on cost data from the same 1978 test year. 10

The Commission granted the staff’s motion in an order issued December 21, 1979. 11 The Commission ordered FP&L to “file a tariff, in substitution for the 18 separate filings. . ., incorporating the provisions of the several transmission service agreements at issue, including the four criteria governing FP&L transmission service availability which were recited in the testimony of Mr. Ernest Bivans in Docket No. ER77175. . . . ” (J.A., p. 2212). The Commission justified the requirement that a tariff be filed in lieu of individual agreements on several grounds. The objectives of Section 205(c) of the Federal Power Act (“FPA”), *672 16 U.S.C.A. § 824d(c) (West 1974), 12 and Section 35.2 of its Regulations, 18 C.F.R. § 35.2 (1980), as well as administrative efficiency, would better be served with a single tariff than by the maintenance of numerous service agreements. The similarity of the filed agreements and the proximity of the filing dates indicated that, as a matter of fact, the policy of availability did control FP&L’s decision of whether to grant requested transmission. Also, because a postage stamp rate is involved with each individual agreement, FP&L would be required in the future to demonstrate that any service at a different rate to a new customer would not be unduly discriminatory, making the filings a tariff service in substance.

FP&L had objected vociferously to the Commission’s requirement that Mr. Bivans’ statement of policy be included in the tariff. The Commission held that this policy statement was a “practice” within the meaning of § 205(c) of the FPA and § 35.1(a), 18 C.F.R. § 35.1(a) (1980), of its regulations. It concluded that because FP&L intended the Commission to rely on this policy statement in Docket No. ER77175, FP&L should have anticipated these availability criteria would be published and given effect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amer Orient Exprs v. STB
484 F.3d 554 (D.C. Circuit, 2007)
Transm Access Plcy v. FERC
225 F.3d 667 (D.C. Circuit, 2000)
Tokio Marine & Fire Insurance v. Amato Motors, Inc.
770 F. Supp. 426 (N.D. Illinois, 1991)
City of Malden v. Union Electric Co.
887 F.2d 157 (Eighth Circuit, 1989)
Mississippi Industries v. Federal Energy Regulatory Commission, Missouri Public Service Commission, Mississippi Power & Light Company, Louisiana Power & Light Company, City of New Orleans, Louisiana, Mississippi Public Service Commission, State of Arkansas, Union Carbide Corporation, Occidental Chemical Corporation, Arkansas & Missouri Congressional Delegations, Louisiana Public Service Commission, Arkansas Public Service Commission, Jefferson Parish, Louisiana, Arkansas Power & Light Company, Middle South Energy, Inc., Middle South Services, Inc., and Cities of Conway and West Memphis, Arkansas, Intervenors. Mississippi Public Service Commission v. Federal Energy Regulatory Commission, Arkansas Power & Light Company v. Federal Energy Regulatory Commission, Mississippi Power & Light Company v. Federal Energy Regulatory Commission, Louisiana Public Service Commission v. Federal Energy Regulatory Commission, Occidental Chemical Corporation v. Federal Energy Regulatory Commission, Reynolds Metals Company v. Federal Energy Regulatory Commission, Edwin Lloyd Pittman, Attorney General of the State of Mississippi v. Federal Energy Regulatory Commission, Arkansas and Missouri Congressional Delegations v. Federal Energy Regulatory Commission, Arkansas Public Service Commission v. Federal Energy Regulatory Commission, State of Arkansas v. Federal Energy Regulatory Commission, Mississippi Legal Services Coalition v. Federal Energy Regulatory Commission, City of New Orleans v. Federal Energy Regulatory Commission, Missouri Public Service Commission v. Federal Energy Regulatory Commission, Representative Webb Franklin v. Federal Energy Regulatory Commission, Jefferson Parish, Louisiana v. Federal Energy Regulatory Commission
808 F.2d 1525 (D.C. Circuit, 1987)
City of Chanute v. Kansas Gas & Electric Co.
564 F. Supp. 1416 (D. Kansas, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
660 F.2d 668, 1981 U.S. App. LEXIS 16251, 1981 WL 638553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-power-light-company-v-federal-energy-regulatory-commission-ca5-1981.