Associated Gas Distributors v. Federal Energy Regulatory Commission, Florida Gas Transmission Company, Intervenors

810 F.2d 226, 258 U.S. App. D.C. 107
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 23, 1987
Docket84-1454
StatusPublished
Cited by7 cases

This text of 810 F.2d 226 (Associated Gas Distributors v. Federal Energy Regulatory Commission, Florida Gas Transmission Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Gas Distributors v. Federal Energy Regulatory Commission, Florida Gas Transmission Company, Intervenors, 810 F.2d 226, 258 U.S. App. D.C. 107 (D.C. Cir. 1987).

Opinion

RUTH BADER GINSBURG, Circuit Judge:

Petitioners in this review proceeding are consumers and distributors of natural gas; they challenge a Federal Energy Regulatory Commission (Commission or FERC) order dismissing their protests concerning the Commission’s treatment of certain price escalator clauses (called “area rate clauses”) in gas sale contracts between gas producers and pipeline companies. Contradicting the assertions of the contracting parties, i.e., the producer and pipeline, petitioners allege that the escalator clauses in question do not allow producers to raise prices to the ceilings set by the Natural Gas Policy Act of 1978 (NGPA), 15 U.S.C. §§ 3301-3432 (1982).

FERC has established a regulatory presumption, adopted after notice and comment rulemaking procedures, that the contracting parties’ assertion about what they intended their area rate clause to permit is accurate. Hence, if the producer and the pipeline agree that the clause in their contract authorizes the maximum lawful increase, the Commission will not contest the increase. However, the Commission affords interested third parties, such as petitioners, a circumscribed opportunity to protest. To achieve a hearing in face of the Commission’s presumption, third-party protestors must show that (1) the contract itself contains language precluding the interpretation advanced by producer and pipeline, or (2) they can adduce extrinsic evidence specifically contradicting producer-pipeline averments of their intent. See Transcontinental Gas Pipeline Corp., Opinion 135, 17 FERC ¶ 61,232 (Dec. 11, 1981).

Responding to petitioners’ protests, the Administrative Law Judge (ALJ) rejected the evidence petitioners proffered as an impermissible collateral attack on FERC’s presumption rather than a permissible rebuttal trained on particular area rate clauses. The ALJ therefore dismissed the protests, and the Commission affirmed. Transcontinental Pipe Line Corp., Opinion 215, 27 FERC ¶ 61,180 (May 7, 1984), rehearing denied in Opinion 215-A, 28 FERC ¶ 61,018 (July 5, 1984). Petitioners seek judicial review, challenging both the rejection of their evidence as an impermissible collateral attack, and the “impossibly^ high” burden FERC imposes on protestors as a prerequisite to ordering a hearing. We conclude that the Commission acted within its statutory authority and with the requisite rationality. We therefore affirm the agency dispositions under review.

I. Background

The setting for this case is the complex relationship between private ordering and public regulation in the natural gas industry. Before 1978, the Federal Power Commission and then FERC prescribed just and reasonable natural gas rates through rate proceedings under the Natural Gas Act of 1938 (NGA), 15 U.S.C. §§ 717-717w (1982). In a series of decisions in the late 1950’s, the Supreme Court imposed the requirement that rate increases filed by producers *229 under the NGA be authorized by the contract between the producer/seller and the pipeline/purchaser. See United Gas Pipe Line Co. v. Memphis Light, Gas & Water Div., 358 U.S. 103, 79 S.Ct. 194, 3 L.Ed.2d 153 (1958); United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373 (1956); FPC v. Sierra Pacific Power Co., 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956). Endeavoring to adjust their contracts to these decisions, producers and pipelines developed a variety of clauses designed to provide authority for rate increases. Under arrangements generally called “indefinite price escalator clauses,” the contracting parties specified events that would trigger price rises to a level determined by the particular event. The Commission, by regulation, rejected most clauses of this sort as contrary to the public interest, see 18 C.F.R. § 154.-93 (1986), but did not invalidate clauses that tied the contract price to the “area rate” the Commission periodically established. Id. When the Commission shifted from area ratemaking to national ratemaking, it continued its earlier treatment in force by reading the area rate clauses as national rate clauses. See Pennzoil Co. v. FERC, 645 F.2d 360, 367 (5th Cir.), cert. denied, 454 U.S. 1142, 102 S.Ct. 1000, 71 L.Ed.2d 293 (1981).

In 1978, the Natural Gas Policy Act unsettled this relatively uncomplicated relationship between private contracts and public ratemaking procedures by sharply curtailing the Commission’s authority to set wellhead prices. 15 U.S.C. § 3331 (1982). In place of FERC’s previous authority, Congress established statutory ceiling prices. See Public Service Comm’n v. Mid-Louisiana Gas Co., 463 U.S. 319, 322, 103 S.Ct. 3024, 3027, 77 L.Ed.2d 668 (1983). The NGPA prices were substantially higher than those the Commission had set, but left private parties free to bargain for lower rates. Producers could sell their gas at the NGPA price only if the gas met categorical statutory criteria and had been sold under a contract that authorized, or could be read to authorize, the NGPA price. See 15 U.S.C. § 3311(b)(9).

Inevitably, the question arose whether area rate clauses, which had been sufficient to supply contractual authorization for price increases under the NGA, would also suffice to permit increases to the NGPA ceiling price. The Commission gradually developed an approach to this question. It concluded in its initial Order 23 rulemaking that neither the language nor the legislative history of the NGPA indicated any congressional intent to preclude the use of area rate clauses as authority for charging the NGPA maximum price. See Order 23, FERC Stats. & Regs. 1130,040, at p. 30,315 (March 20, 1979). Whether any particular clause constituted sufficient authority for charging that price, however, was a question of the parties’ intent. If the parties meant to allow the contract price to float to the highest relevant ceiling set by regulatory authorities, then the clause would supply the requisite authority to charge the NGPA price. Id. at p. 30,316.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frierson v. Saul
W.D. North Carolina, 2020
South Dakota Public Utilities Commission v. Federal Energy Regulatory Commission, Maxus Exploration Company, Norfolk Energy, Inc., Arco Oil and Gas Company, Exxon Corporation, Kaneb Exploration, Inc., Okmar Oil Company, Shell Western E & P, Inc., Shenandoah Oil Corporation, Texas International Petroleum Company and Phoenix Resources Company, Kaiser-Francis Oil Company and Leben Oil Corporation, Bass Enterprises Production Company, Intervenors, Northern Natural Gas Co., a Division of Enron Corp. Peoples Natural Gas Company, Division of Utilicorp United, Inc. v. Federal Energy Regulatory Commission, Mapco, Inc., Mapco Oil and Gas Company, Santa Fe Minerals, a Division of Santa Fe International Corporation, Santa Fe-Andover Oil Company, Santa Fe Braun, Inc., Danden Petroleum, Inc., Werner Oil, Inc., Cng Producing Company, and Russell Freeman, D/B/A Continental Energy, John H. Hendrix, Okmar Oil Company, Neleh Gas and Oil Company, Damson Oil Corporation, Montana Consumers Counsel, Public Utilities Commission of South Dakota and Montana Public Utilities Commission, Intervenors, Northern Natural Gas Co., a Division of Enron Corp. Minnesota Public Utilities Commission v. Federal Energy Regulatory Commission, Mapco, Inc., Mapco Oil and Gas Company, Santa Fe Minerals, a Division of Santa Fe International Corporation, Santa Fe-Andover Oil Company, Santa Fe Braun, Inc., Danden Petroleum, Inc., Werner Oil, Inc., Cng Producing Company, and Russell Freeman, D/B/A Continental Energy, Wayman W. Buchanan, Kaneb Exploration, Inc., Champlin Exploration, Inc., Shell Western E & P, Inc., Exxon Corporation, Norfolk Energy, Inc., Arco Oil and Gas Company, Division of Atlantic Richfield Company, Intervenors, Northern Natural Gas Co. A Division of Enron Corp
934 F.2d 346 (D.C. Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
810 F.2d 226, 258 U.S. App. D.C. 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-gas-distributors-v-federal-energy-regulatory-commission-cadc-1987.