Ozark Gas Transmission System v. Federal Energy Regulatory Commission

897 F.2d 548, 283 U.S. App. D.C. 94, 1990 U.S. App. LEXIS 2873
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 27, 1990
Docket87-1751, 88-1411
StatusPublished
Cited by3 cases

This text of 897 F.2d 548 (Ozark Gas Transmission System v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ozark Gas Transmission System v. Federal Energy Regulatory Commission, 897 F.2d 548, 283 U.S. App. D.C. 94, 1990 U.S. App. LEXIS 2873 (D.C. Cir. 1990).

Opinion

Opinion for the Court filed by Circuit Judge MIKVA.

MIKVA, Circuit Judge:

In 1985, the Federal Energy Regulatory Commission (“FERC”) began efforts to increase competition among natural gas pipelines by permitting pipeline companies to carry natural gas on an “open-access, self-implementing” basis. Petitioner, Ozark Gas Transmission System (“Ozark”), sought an open-access blanket certificate for its interstate natural gas pipeline. Because of peculiarities in its financing arrangement and original certificate, Ozark would violate the terms of its loan agreement if it strictly complied with FERC’s open-access regulations. FERC granted Ozark a waiver from the conflicting provisions but attached conditions to Ozark’s blanket certificate which would have required the pipeline to charge more than twice as much as its only competitor and which would not have eliminated the conflict with Ozark’s debt instruments. In light of the purposes of the waiver and FERC’s “open-access” objectives, we find that FERC did not engage in reasoned deci-sionmaking in formulating the conditions attached to Ozark’s blanket certificate. Accordingly, we remand.

I. BACKGROUND

In 1981, Ozark received a certificate from FERC under Section 7(e) of the Natural Gas Act (“NGA”), 15 U.S.C. § 717f(e) (1982), authorizing it to construct and operate a natural gas pipeline in the Arkoma basin, which extends from Arkansas to Oklahoma. Ozark Gas Transmission System, 16 FERC ¶ 61,099, reh’g denied, 17 FERC ¶ 61,024 (1981). The Ozark pipeline was originally designed to transport gas on a regular or “firm” basis for two pipeline companies, Tennessee Gas Pipeline (“Tennessee”) and Columbia Gas Transmission Corporation (“Columbia”). Both Columbia and Tennessee are partners in Ozark, and each contracted for half of Ozark’s pipeline capacity, although neither company uses— or expects to use — its full allotment.

In order to construct and operate its pipeline, Ozark proposed to obtain loans through “project-financing,” a method which has been expressly approved by FERC. Under project-financing, Ozark’s lenders agreed to secure their loans with the anticipated stream of income from the constructed pipeline. The lenders, however, demanded that Ozark guarantee its income stream regardless of the project’s ultimate success. To accomplish this, Ozark proposed that a two-tiered rate system be incorporated into its Section 7(e) certificate. The first part of the rate (the “demand charge” or “minimum bill”) covered all of Ozark’s fixed costs (i.e., operating and maintenance expenses, taxes, amortized debt principal, and debt interest). These demand charges were guaranteed by Columbia and Tennessee regardless of whether any gas was shipped. The second part of the rate (the “commodity charge”) included all other rate components, includ *550 ing return on equity, depreciation of equity, and income taxes. The Commission granted Ozark’s request with certain limitations not relevant here. Id. 16 FERC ¶ 16,099 (1981).

Following the pipeline’s construction, Ozark provided “firm” transportation service to Columbia and Tennessee and “inter-ruptible” service to other shippers. The firm shippers retained first priority access to all of the pipeline’s capacity. When Ozark’s firm shippers required less than the pipeline’s full capacity, Ozark attempted to sell the unused space to interruptible shippers under Section 311 of the Natural Gas Policy Act (“NGPA”). 15 U.S.C. § 3371 (1982) (“Section 311”). The firm shippers continued to pay 100 percent of Ozark’s fixed costs, and thus the interrupti-ble shippers paid only the commodity rate.

In 1985, the Commission undertook a broad restructuring of the natural gas transportation industry to promote competition in gas markets. Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, Order No. 436, 50 Fed.Reg. 42,-408 (1985) (“Order No. 436”); see Associated Gas Distrib’s v. FERC, 824 F.2d 981, 993 (D.C.Cir.1987), cert. denied sub. nom. Southern California Gas Co. v. FERC, 485 U.S. 1006, 108 S.Ct. 1469, 99 L.Ed.2d 698 (1988). Order No. 436 permitted interstate pipelines to obtain a blanket certificate to transport natural gas without having to secure individual certification for each transaction. This new approach allows distributors and consumers to purchase gas from sellers other than pipelines and to have it transported by the pipelines in competition with the pipelines’ own sales of gas. Mobil Oil Corp., et al. v. FERC, 886 F.2d 1023, 1028 (8th Cir.1989). Although this court subsequently vacated Order No. 436 in Associated Gas Distrib’s, supra, FERC repromulgated the relevant portions of Order No. 436 in Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, Order No. 500, 52 Fed.Reg. 30,334 (1987) (“Order No. 500”).

Order No. 436 required Ozark to change its method of calculating charges for inter-ruptible shippers. Under the Commission’s implementing regulations (“Section 284.7”), the rates must be one part, i.e., not include demand charges or minimum bills that guarantee revenues to the pipeline. 18 C.F.R. § 284.7 (1989).

Ozark and various project-financed pipelines sought rehearing of Order No. 436, arguing that they could not meet the rate conditions of Section 284.7. Under the regulations, the pipelines would have to charge a portion of their fixed costs to interrupti-ble shippers based on projected volume. Since those shippers might not meet the pipelines’ projections, the pipelines could no longer guarantee recovery of those fixed costs (through demand charges) as required by their loan agreements. Complying with the Section 284.7 requirements, then, would place these pipelines in default on their loans.

The Commission denied Ozark’s request for a general modification of the Section 284.7 rate conditions for project-financed pipelines, but chose instead to permit case-by-case waivers of those provisions. Order No. 436-A, 50 Fed.Reg. 52,217, 52,247 (1985). Shortly thereafter, Ozark filed its application for a blanket certificate, which included a request for a waiver of the Section 284.7 regulations. Because of its concern that shifting any portion of its demand charges to the interruptible shippers would place its debt instrument in jeopardy, Ozark requested permission to collect only a commodity charge from these shippers — just as it had under Section 311.

Following a technical conference on the matter, Ozark unilaterally offered a settlement: it proposed to provide interruptible service at a maximum rate of 22.5 cents per unit transported (Mcf). In addition, Columbia and Tennessee would receive a “commodity credit” for revenues collected on any unit of interruptible service that exceeded the firm shipping commodity rate (16.28 cents/Mcf).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
897 F.2d 548, 283 U.S. App. D.C. 94, 1990 U.S. App. LEXIS 2873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ozark-gas-transmission-system-v-federal-energy-regulatory-commission-cadc-1990.