Texaco, Inc. v. Federal Energy Regulatory Commission

886 F.2d 749, 1989 U.S. App. LEXIS 16092, 1989 WL 115874
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 6, 1989
Docket87-4735
StatusPublished
Cited by5 cases

This text of 886 F.2d 749 (Texaco, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texaco, Inc. v. Federal Energy Regulatory Commission, 886 F.2d 749, 1989 U.S. App. LEXIS 16092, 1989 WL 115874 (5th Cir. 1989).

Opinion

JOHN R. BROWN, Circuit Judge:

FERC Makes for Strange Bedfellows

Texaco Inc. (Texaco), et al 1 appeals the decision 2 of the Federal Energy Regulatory Commission (FERC) accepting a settlement proposed by Texas Eastern Transmission Corp. (Texas Eastern), 3 which resolved Texas Eastern’s 1985 general rate case and put into effect open access pursuant to FERC Order No. 436. 4

Texaco challenges (i) the allowing of Texas Eastern to use the 100% Load Factor rate 5 in fixing the Interruptible Transportation rate, 6 and (ii) FERC’s determining *752 that the cost of service is properly allocated between the types of services offered by Texas Eastern. Exxon challenges FERC’s decision to not require Texas Eastern to charge seasonally differentiated Interrupti-ble Transportation rates. In addition to its arguments regarding the 100% Load Factor rate, PGC raises the issue of the assessment of penalties for monthly imbalances between amounts scheduled for delivery, amounts delivered and amounts actually taken for use.

On review of the various appeals, we affirm the decision of FERC below.

The Facts of the Matter

Texas Eastern submitted to FERC proposed settlement rates for an interim Inter-ruptible Transportation rate (TS-3 rate) 7 and for a permanent Interruptible Transportation rate (IT-1 rate) and Firm Transportation rate (FT-1 rate). The IT-1 was equal to the TS-3 rate and both the IT-1 and FT-1 rates included provisions for penalties.

In the Order Approving the Contested Offer of Settlement, 8 FERC approved the settlement, including the FT-1 rate and the use of 100% Load Factor rates for Inter-ruptible Transportation rates. FERC also approved the lack of seasonal rates and deferred consideration of seasonal rates proposed by the petitioners. Regarding the question of penalties, FERC did not approve Texas Eastern’s proposed penalties but did adopt modified penalties to be used on an interim basis, subject to refund and pending a hearing.

Applications for rehearing were filed by various parties. FERC stood by its decisions regarding the use of 100% Load Factor rates and seasonal rates and decided to approve the modified penalties it ordered when it accepted the Settlement without the hearing that had also been ordered. Texas Eastern subsequently rejected the FT-1 and IT-1 rates, including the penalties associated with those rates, as approved by FERC. Consequently, the FT-1 and IT-1 rates, and their associated penalties, have not been put into effect. 9

Load Factor Rates

The issue of the 100% Load Factor rate basis and open access transportation under Order No. 436 has recently been dealt with by the Eighth Circuit 10 and we herein adopt their conclusion that FERC has not erred in allowing the use of the 100% Load Factor rate as the basis for Interruptible Transportation rates. 11 Thus, we hold that FERC has not abused its discretion in allowing the use of the 100% Load Factor rate and that the 100% Load Factor rate adequately reflects the relative reliability of Interruptible service. 12

The argument that 100% Load Factor rates are anticompetitive is based on the contention that Texas Eastern’s sales cus *753 tomers will continue to buy Texas Eastern’s own natural gas because they must continue to pay Texas Eastern the sales demand charge 13 under their sales contracts in addition to paying the cost of third party natural gas transported by Texas Eastern. In effect, there is a bias for Texas Eastern’s own natural gas because it will always be cheaper for sales customers to buy from Texas Eastern rather than pay Texas Eastern the sales demand charge and then buy natural gas from third party shippers who have also paid Texas Eastern a demand charge.

Although competitive rates are a goal to be considered when approving rates, FERC is not bound by such considerations, rather, it must weigh them “along with other important public interest considerations.” 14 FERC has determined that the greater interest is that Interruptible Transportation rates should recoup all the costs associated with providing the service and that to approve Interruptible Transportation rates based on the commodity charge alone would be a greater evil by allowing Inter-ruptible shippers to avoid payment of costs associated with providing them with transportation. Regarding the anticompetitive claim raised below, we therefore also hold that FERC did not err in its decision to use the 100% Load Factor rate as the basis for the Interruptible Transportation rate.

Allocation of Costs

In addition to the arguments raised above regarding the 100% Load Factor rate, Texaco also complains that the Inter-ruptible Transportation rate does not properly recover the costs of service. Specifically, Texaco objects because the Firm Transportation rate was determined by allocating fixed costs to two demand categories, D-l and D-2 while the Interruptible Transportation rate utilized only one demand charge, D-l. Thus, the Firm Transportation rate comprised (D-l + D-2) + Commodity Charge while the Interruptible Transportation rate was structured as D-l + Commodity Charge.

This is really just another version of Texaco’s attack on the 100% Load Factor rates. Texaco argues that Demand costs should be excluded from Interruptible Transportation rates leaving the Commodity Charge as the basis for Interruptible Transportation rates. We reject this argument because Interruptible shippers should bear the same burden of fixed costs that Firm shippers bear as both classes of shippers benefit from the same service, transportation between two points. Provided the 100% Load Factor rate is used to determine the Interruptible Transportation rate, it is irrelevant whether or not the Interrup-tible Transportation rate has one or two categories of demand charges. In practice, all the fixed costs associated with transportation will be recovered regardless.

Moreover, FERC was not indifferent to this problem. FERC required Texas Eastern to file work papers showing the breakdown of its costs and projected volumes, and FERC considered those breakdowns and projected volumes when it determined that any error in the structuring of the Interruptible Transportation rate was harmless.

We agree with FERC that any error in structuring the Demand portion of the In-terruptible Transportation rate was harmless given the fact that the Interruptible Transportation rate is equivalent to the 100% Load Factor rate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
886 F.2d 749, 1989 U.S. App. LEXIS 16092, 1989 WL 115874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texaco-inc-v-federal-energy-regulatory-commission-ca5-1989.