Orange & Rockland Utilities, Inc. v. Federal Energy Regulatory Commission

905 F.2d 425, 284 U.S. App. D.C. 320
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 12, 1990
DocketNo. 89-1129
StatusPublished
Cited by2 cases

This text of 905 F.2d 425 (Orange & Rockland Utilities, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orange & Rockland Utilities, Inc. v. Federal Energy Regulatory Commission, 905 F.2d 425, 284 U.S. App. D.C. 320 (D.C. Cir. 1990).

Opinion

STEPHEN F. WILLIAMS, Circuit Judge:

Orange and Rockland Utilities, a customer of Tennessee Gas Pipeline Company, complains of two aspects of the Federal Energy Regulatory Commission’s treatment of Tennessee’s 1982 rate filing. See Order Affirming and Reversing Initial Decision, Tennessee Gas Pipeline Co. (“Order”), 45 FERC ¶ 61,031, pet. for reh’g [322]*322denied in pertinent part (“Order on Rehearing"), 45 FERC ¶ 61,470 (1988). The first is the Commission’s insistence on a so-called “100% load factor rate” (effectively a rate based on fully allocated or average costs) for interruptible sales; the second, its approval of a higher commodity charge for a special class of gas transmission. We uphold the Commission as to the former and remand as to the latter.

Interruptible Sales Rate

Tennessee’s filing proposed to reduce the rate it charged for interruptible gas sales. The proposed rate would have equalled the commodity component of its rates for ordinary firm customers — its contract demand or “CD” customers. Under the “modified fixed variable” rate design approved for Tennessee, this charge would include all its gas costs, the variable costs of transportation and storage, and part of the fixed costs for the latter — return on equity and related income taxes. Thus interruptible purchasers would not have borne a share of that part of Tennessee’s fixed costs allocated to its demand charge.

The administrative law judge concluded that under the proposed reduced rate firm shippers would subsidize the interruptibles, and that Tennessee had shown no competitive need for the proposed rate (as against competition from alternative energy sources). Instead the ALJ reaffirmed the existing, previously approved 100% load factor rate, which matches what a firm customer would pay per unit of gas (in both commodity and demand charges) if it took 100% of its contract demand. See Initial Decision on Reserved Issue, Tennessee Gas Pipeline Co. (“ALJ Opinion”), 31 FERC ¶ 63,001 at 65,004-07 (1985). The Commission affirmed. Order, 45 FERC at 61,102-04.

For pipeline filings under § 4 of the Natural Gas Act, 15 U.S.C. § 717c, the burden of proof is on the pipeline when it proposes a rate increase. See Sea Robin Pipeline Co. v. FERC, 795 F.2d 182, 183 (D.C.Cir.1986); ANR Pipeline Co. v. FERC, 771 F.2d 507, 513 (D.C.Cir.1985). The Commission kept it there, even though the change proposed was a reduction, on the ground that it carried a possibility of shifting costs to firm customers. See 45 FERC at 61,103. The prospect of cost-shifting would seem to turn on projected volumes. If Tennessee's proposal projected a high enough volume under the lower rate, interruptible service thereunder could make a greater contribution to fixed costs than under the 100% load factor rate, shifting costs away from the firm customers. It is not clear exactly how Tennessee handled the matter, but since no party has contested the allocation of the burden to Tennessee, we assume its validity-

In its petition for rehearing, Orange and Rockland rested primarily on what it viewed as the Commission’s failure to recognize the distinctions between the present case and prior Commission decisions applying a 100% load factor rate. That merely puts on the Commission a burden of explaining why it was extending the earlier decisions; it does not in itself make a case for the proposed alternative rate. Here we find that the Commission gave at least plausible explanations for extension of the prior cases. As neither Tennessee nor the customers seeking a lower interruptible rate undertook to show why the Commission’s approach was fundamentally wrong, we affirm.

Thus, Orange and Rockland points out that whereas in the previous instances in which the Commission imposed the 100% load factor rate interruptible sales weren’t truly interruptible, see, e.g., Public Service Comm’n of the State of New York v. FERC, 813 F.2d 448, 453 (D.C.Cir.1987), here they are “interruptible in the extreme.” To this the Commission had two kinds of answers. First, it invoked its prior decision in Texas Eastern Transmission Corp., 37 FERC ¶ 61,260 at 61,697-61,705 (1986), reh’g denied, 41 FERC ¶ 61,015 at 61,028-30 (1987), aff'd sub nom. Texaco, Inc. v. FERC, 886 F.2d 749 (5th Cir.1989), which acknowledged that quality differences called for rate differences but noted that a 100% load factor rate is different from a standard CD rate: a firm customer would pay as little per unit only if it [323]*323bought its full contract quantity. See Order, 45 FERC at 61,104. In essence it appeared to be saying that as the 100% load factor rate was a genuine advantage, it was unwilling to create further refinements for degrees of interruptibility.

More important, the Commission asserted that because interruptible service used the facilities for which the fixed costs were incurred, it properly bears some of those fixed costs. See id.; see also Order on Rehearing, 45 FERC at 62,471. In fact this does not seem necessarily so. In its regulation of interstate sales of electricity, the Commission takes the view that “those creating the critical need for power [i.e., the peak period users] are assigned the cost responsibility for all capacity-related costs.” Union Electric Co., 40 FERG ¶ 61,046 at 61,141 (emphasis in original), modified on reh’g, 41 FERC ¶ 61,343 (1987), rev’d on other grounds sub nom. Union Electric Co. v. FERC, 890 F.2d 1193 (D.C.Cir.1989). This view embodies the principle that regulators should allocate the costs of facilities to those whose demand causes them to be incurred, in order to provide users with correct incentives in their decisions about whether to invest in alternatives and about what quantities to take and when. See Union Electric Co., 890 F.2d at 1198-1201. If peak-period use determines the size of gas transmission facilities, as one would expect by analogy to electricity generation, then it is not clear why interruptible service — at least if it is genuinely interruptible — should bear any portion of the fixed costs. On the other hand, the Commission has for various reasons qualified its general policy of loading the fixed costs of electricity generation onto peak-period users, see discussion at 890 F.2d at 1198-1200, and similar ones may apply, perhaps even more forcefully, for gas pipelines.

In a policy statement issued after the decision under review here, however, the Commission appeared to adopt a view extremely sympathetic to peak-period pricing. Noting that regulations for unbundled transportation rates called for interruptible and off-peak rates that would “maximize throughput,” it observed that this principle should extend to the transportation portion of bundled sales rates as well. Policy Statement Providing Guidance mth Respect to the Designing of Rates, 47 FERC ¶ 61,295 at 62,052 (1989). Although “maximize throughput” is surely hyperbole (a zero rate would do so, but would not cover variable costs), the policy statement appears to reflect an intention to apply to gas pipeline service something at least approximating the cost causation principles that it uses for electricity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
905 F.2d 425, 284 U.S. App. D.C. 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orange-rockland-utilities-inc-v-federal-energy-regulatory-commission-cadc-1990.