Gas Transmission Northwest Corp. v. Federal Energy Regulatory Commission

363 F.3d 500, 361 U.S. App. D.C. 64, 161 Oil & Gas Rep. 397, 2004 U.S. App. LEXIS 7092, 2004 WL 769247
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 13, 2004
Docket03-1166
StatusPublished
Cited by2 cases

This text of 363 F.3d 500 (Gas Transmission Northwest Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gas Transmission Northwest Corp. v. Federal Energy Regulatory Commission, 363 F.3d 500, 361 U.S. App. D.C. 64, 161 Oil & Gas Rep. 397, 2004 U.S. App. LEXIS 7092, 2004 WL 769247 (D.C. Cir. 2004).

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

STEPHEN F. WILLIAMS, Senior Circuit Judge:

Gas Transmission Northwest Corporation (“GTN”) is an interstate natural gas pipeline that transports gas from the United States/Canada border to the California/Oregon border. In 2002 it sought permission from the Federal Energy Regulatory Commission to amend its tariff so that it could sell available, unsubscribed capacity, or capacity expected to become available, to a shipper willing to execute an agreement for service to start at a specific future date. The Commission approved, finding GTN’s so-called “prearranged deal” program “consistent with Commission policy-.” PG&E Gas Transmission, Northwest Corp., 102 FERC ¶ 61,044 at 61,099, 2003 WL 245764 (2003) (“Initial Order”).

*502 GTN recognized that the Commission’s normal mandate of a right of first refusal (“ROFR”) for all holders of service agreements of a year or more could obstruct the program, as sale of the capacity for the period between agreement and the scheduled start of service, coupled with the ROFR, would undercut GTN’s effort to make a firm commitment of the capacity in the future. See GTN’s October 15, 2002 Filing (“October 2002 Filing”) at 4; see generally 18 C.F.R. § 284.221(d)(2). GTN thus sought a partial waiver of the ROFR requirement, supporting its request by likening its program to a group of “capacity reservation” cases in which the Commission allowed shippers to reserve capacity for future expansion projects and waived the ROFR requirement for capacity sold in the interim. See October 2002 Filing at 3-4; see also, e.g., Northern Border Pipeline Co., 103 FERC ¶ 61,390, 2003 WL 21508072 (2003); Columbia Gulf Transmission Co., 100 FERC ¶ 61,133, 2002 WL 1840045 (2002); Tennessee Gas Pipeline Co., 82 FERC ¶ 61,288, 1998 WL 131415 (1998).

The Commission refused GTN’s request for a waiver, saying that it “disagree[d]” with GTN’s argument that its prearranged deal program was akin to the capacity reservation cases. Initial Order, 102 FERC ¶ 61,044 at 61,100. It purported to explain, saying that ROFR waiver was suitable in the latter cases “so that a general system expansion may be optimally sized.” Id.

GTN requested rehearing, again emphasizing the similarities between its prearranged deal program and the capacity reservation cases and arguing that “granting limited waiver of the ROFR for interim shippers in this case furthers precisely the same goals as those the Commission found determinative for ... [waiving] the ROFR in the capacity reservation context.” Request for Rehearing at 4. The Commission denied rehearing. PG&E Gas Transmission, Northwest Corp., 103 FERC ¶ 61,061 at 61,200 (2003) (“Rehearing Order”).

GTN seeks review, arguing that the Commission has failed to offer a reasoned basis for its refusal to waive the ROFR requirement. We remand so that the Commission may give a rationale, if it has one.

Although our review is under the deferential “arbitrary and capricious” standard, 5 U.S.C. § 706(2)(A), even that modest criterion requires the Commission to “articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made.’” Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (citation omitted).

As we’ve said, the Commission in its Initial Order tried to differentiate GTN’s prearranged deal program from the capacity reservation cases by saying that the former did not insure that “a general system expansion may be optimally sized.” Initial Order, 102 FERC ¶ 61,044 at 61,-100; see also Columbia Gas Transmission Corp., 101 FERC ¶ 61,380 at 62,586, 2002 WL 31975215 (2002) (“The primary purpose of permitting the reservation of capacity is to minimize the size of the expansion[.]”).

Not having been understood, GTN tried to connect the dots in its Request for Rehearing, explaining that its proposal, with partial waiver of the ROFR, “will also help to ensure that future expansion projects are both necessary and properly sized. In fact, making capacity available on a pre-arranged basis may eliminate en *503 tirely the need to construct new capacity to serve the pre-arranged shipper’s currently anticipated future needs.” Request for Rehearing at 4. In other words, avoiding wasteful use of existing capacity obviates or reduces the need for additional, potentially wasteful construction, precisely the object of the capacity reservation program. Thus the Commission’s principal answer fails to distinguish its own prior precedent. See, e.g., PG&E Gas Transmission, Northwest Corp. v. FERC, 315 F.3d 383, 390 (D.C.Cir.2003).

The Commission adds nothing useful in its claim that GTN is seeking “to insulate itself from its decision to enter into a prearranged agreement for future service, at the expense of shippers who enter into service agreements in the interim.” Initial Order, 102 FERC ¶ 61,044 at 61,100 (citing Williams Gas Pipelines Central Inc., 97 FERC ¶ 61,249, 97 FERC P 61249 (2001)). The cited decision says only that “a contractual right of first refusal may broaden the regulatory right of first refusal, but it may not narrow it.” Williams Gas, 97 FERC ¶ 61,249 at 62,110. But that proposition has no applicability here, where GTN is seeking to alter its tariff — not to file a single non-conforming service agreement — so that the regulatory ROFR will not apply to an entire set of service agreements.

In its Rehearing Order the Commission invoked the policy concept behind its ROFR requirement — concern about a pipeline’s potential exercise of market power over shippers who cannot invoke a ROFR. Rehearing Order, 103 FERC ¶ 61,061 at 61,199 (citing Order No. 637, Regulation of Short-Term Natural Gas Transportation Services, and Regulation of Interstate Natural Gas Transportation Services, 65 Fed. Reg. 10,155 (February 25, 2000)). But that plainly supplies no explanation for the Commission’s more stringent insistence on the ROFR here than in the capacity reservation cases. Unless the Commission can explain why the advantages of capacity reservation are superior to those of GTN’s prearranged deal program, or why the negative effects of ROFR waiver are more severe in the latter context, it cannot rest its refusal of GTN’s waiver request simply on the underlying justification for its general ROFR requirement.

If on remand the Commission can adduce a compelling distinction between the two contexts, waiver denial may well be sustainable; if not, not. In any event, we go on to an additional point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
363 F.3d 500, 361 U.S. App. D.C. 64, 161 Oil & Gas Rep. 397, 2004 U.S. App. LEXIS 7092, 2004 WL 769247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gas-transmission-northwest-corp-v-federal-energy-regulatory-commission-cadc-2004.