Colorado Interstate Gas Co. v. Chemco, Inc.

854 P.2d 1232, 17 Brief Times Rptr. 953, 23 U.C.C. Rep. Serv. 2d (West) 433, 1993 Colo. LEXIS 509, 1993 WL 199081
CourtSupreme Court of Colorado
DecidedJune 14, 1993
Docket92SC163
StatusPublished
Cited by21 cases

This text of 854 P.2d 1232 (Colorado Interstate Gas Co. v. Chemco, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colorado Interstate Gas Co. v. Chemco, Inc., 854 P.2d 1232, 17 Brief Times Rptr. 953, 23 U.C.C. Rep. Serv. 2d (West) 433, 1993 Colo. LEXIS 509, 1993 WL 199081 (Colo. 1993).

Opinion

Chief Justice ROVIRA

delivered the Opinion of the Court.

We accepted certiorari to review the court of appeals decision in Colorado Interstate Gas Co., Inc. v. Chemco, 833 P.2d 786 (Colo.App.1991), holding that the damages awarded by the trial court were appropriate for breach of a take-or-pay provision in a natural gas contract and that the award did not violate either due process or basic principles of contract law. We affirm.

I

Colorado Interstate Gas Company (CIG) is a natural gas pipeline that gathers gas at wells, transports it, and sells it to consumers of natural gas, generally utility companies. In 1979, as a part of a campaign to expand its gas supply, CIG entered into a long-term “take-or-pay” contract 1 to purchase natural gas from Chemco. 2 The contract provided that CIG would take, and pay for, a designated minimum quantity of gas within a contract year, or if CIG failed to take the minimum quantity of gas it would nevertheless pay for the gas it was required to, but did not, take. On paying for the gas not taken, CIG had the right for the next five years to “make-up” that gas. Although this contract initially encompassed only one well, the Wear 3-2 well, it was later amended to encompass three new wells. 3

The market for natural gas changed dramatically after the parties entered into their agreement. In the early 1970’s inadequate production, due in part to the regulatory price ceilings on natural gas sold in the interstate market, had led to gas shortages and a corresponding increase in prices to consumers. See Mobil Oil Exploration v. United Distribution Co., 498 U.S. 211, 217, 111 S.Ct. 615, 620, 112 L.Ed.2d 636 (1991) (“severe shortages persisted in the interstate market because low ceiling prices for interstate gas sales fell considerably below prices the same gas could command in intrastate markets, which were as yet unregulated”); Prenalta Corp. v. Colorado Interstate Gas Co., 944 F.2d 677, 679 (10th Cir.1991) (“regulatory price ceilings on natural gas sold in the interstate market had contributed to conditions of decreased production and, ultimately ... natural gas shortages”). Congress responded to the natural gas shortage by enacting the Natural Gas Policy Act, 15 U.S.C.A. §§ 3301 to 3432 (1983 & 1993 Supp.), which “comprehensively and dramatically changed the method of pricing natural gas produced in the United States.” Public Service Comm’n, New York v. Mid Louisiana Gas Co., 463 U.S. 319, 322, 103 S.Ct. 3024, 3027, 77 L.Ed.2d 668 (1983). It effectuated this change by, inter alia, giving the Federal Energy Regulatory Commission (FERC) the ability to regulate the intrastate gas market, as well as the interstate market, and established a phased deregulation scheme for new and hard-to-produce gas. Mobil, 498 U.S. at 217, 111 S.Ct. at 620. The incentives for the production of new and difficult-to-produce gas resulted in the gas shortages of the 1970’s turning into the surpluses of the 1980’s.

In response, at least in part, to the changing market brought about by the *1234 Natural Gas Policy Act, the parties amended their agreement. Under the terms of this amendment, from October 1, 1983, through October 1, 1985, CIG’s take obligation was reduced to a flat 130,000 thousand cubic feet (mcf) per year from all Chemco wells committed to the contract, rather than a percentage of the gas wells’ capacity. After October 1, 1985, the 1983 amendment provided that CIG’s take obligation was to be reduced from 75% of the wells’ capacity, as was originally required, to 50% of the wells’ capacity. Additionally, the 1983 amendment gave Chemco the right to determine which wells were to be used to produce the 130,000 mcf. At the conclusion of this two-year modification, October 1, 1985, CIG ceased to perform its obligations under the contract, exercising what it claimed to be its right to cease purchasing gas pursuant to paragraph 4.5 of the contract. 4 Concurrently, it initiated a declaratory judgment action seeking a determination that it had no obligation to purchase gas and accordingly had no take- or-pay liability. Chemco counterclaimed alleging, as relevant to this appeal, breach of the take-or-pay clause prior to October 1, 1983, and subsequent to October 1, 1985. Pursuant to a stipulation between the parties, trial of the case was bifurcated. Phase I was to be tried to the court and was to encompass “[a]ll issues framed by [CIG’s] complaint for declaratory judgment, and any other issues framed by the pleadings with respect to whether [CIG] has breached the contract with [Chem-co].... ” The stipulation provided that phase II would encompass “all remaining issues framed by [Chemco’s] counterclaims [and would] be tried to jury verdict.”

At the conclusion of phase I, the trial court ruled that paragraph 4.5 permitted a suspension of performance only if there was a significant depletion in Chemco’s wells’ capacity to produce gas. Accordingly, the trial court determined that CIG was in breach of the contract by impermissibly exercising paragraph 4.5. Shortly after the conclusion of phase I, CIG purportedly requested full resumption of performance under the contract.

At the conclusion of phase II, the damage phase, the trial court instructed the jury that it had “already determined that CIG [had] breached its contractual obligations” and that the only question to be decided by the jury was “the amount of damages suffered by Chemco as a result of CIG’s breach of contract.” The trial court further instructed the jury that, if they found actual damages, they should award “as such actual damages all take-or-pay payments due Chemco under the terms of the contract....” The jury awarded Chemco over $3 million in damages. The court of appeals affirmed both the finding of liability and the damages award.

II

CIG argues that the trial court improperly instructed the jury on the measure of damages because a contract for the sale of natural gas after severance is a contract for the sale of goods. 5 It urges that because Chemco is a seller of goods its remedies should be limited to those provided by the Colorado Uniform Commercial Code (UCC), specifically section 4-2-703, 2 C.R.S. (1992). Thus, according to CIG, the proper measure of damages is the contract price for the gas, less the market price, plus incidental damages, less expenses saved. See § 4-2-708(1), 2 C.R.S. (1992).

A

Long term contracts, such as the contract at issue here, are prevalent in the natural gas industry. See C.F.R. § 2.61(c) (1992) (requiring pipelines to insure deliver-ability for twelve years).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Xy, LLC v. Trans Ova Genetics, L.C.
890 F.3d 1282 (Federal Circuit, 2018)
Xtreme Coil Drilling Corp. v. Encana Oil & Gas, Inc.
958 F. Supp. 2d 1238 (D. Colorado, 2013)
Electrical Distributors, Inc. v. SFR, Inc.
166 F.3d 1074 (Tenth Circuit, 1999)
Colorado Interstate Gas Co. v. Chemco, Inc.
987 P.2d 829 (Colorado Court of Appeals, 1998)
Decker v. Browning-Ferris Industries of Colorado, Inc.
931 P.2d 436 (Supreme Court of Colorado, 1997)
Lenape Resources Corp. v. Tennessee Gas Pipeline Co.
925 S.W.2d 565 (Texas Supreme Court, 1996)
Decker v. Browning-Ferris Industries of Colorado, Inc.
903 P.2d 1150 (Colorado Court of Appeals, 1995)
St. Jude Medical, Inc. v. Medtronic, Inc.
536 N.W.2d 24 (Court of Appeals of Minnesota, 1995)
Kincaid v. Western Operating Co.
890 P.2d 249 (Colorado Court of Appeals, 1994)
Mike Naughton Ford, Inc. v. Ford Motor Co.
862 F. Supp. 264 (D. Colorado, 1994)
Donohue v. Unipac Service Corp.
847 F. Supp. 1530 (D. Colorado, 1994)
Wells Fargo Realty Advisors Funding, Inc. v. Uioli, Inc.
872 P.2d 1359 (Colorado Court of Appeals, 1994)
Amoco Rocmount Co. v. Anschutz Corp.
7 F.3d 909 (Tenth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
854 P.2d 1232, 17 Brief Times Rptr. 953, 23 U.C.C. Rep. Serv. 2d (West) 433, 1993 Colo. LEXIS 509, 1993 WL 199081, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colorado-interstate-gas-co-v-chemco-inc-colo-1993.