Colorado Interstate Gas Co. v. Chemco, Inc.

833 P.2d 786, 1991 WL 272697
CourtColorado Court of Appeals
DecidedAugust 17, 1992
Docket89CA0594
StatusPublished
Cited by21 cases

This text of 833 P.2d 786 (Colorado Interstate Gas Co. v. Chemco, Inc.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colorado Interstate Gas Co. v. Chemco, Inc., 833 P.2d 786, 1991 WL 272697 (Colo. Ct. App. 1992).

Opinion

Opinion by

Judge MARQUEZ.

Defendants, Chemco, Inc., R.E. Neher, Zelda Neher, G. Hamilton Neher, Robin Neher Cann, Robin Investment Co., Inc., Kirchner Farm Associates and Dempsey Investment Company, Inc., (Chemco) appeal the dismissal of their counterclaims for fraud and tortious breach of contract. Plaintiff, Colorado Interstate Gas Company, Inc. (CIG), cross-appeals the judgment entered on the trial court’s ruling that it *788 breached its gas purchase agreement with Chemco and the jury’s subsequent damage award. We affirm.

In 1978, Chemco leased oil and gas acreage and recompleted an old well, the Wear 3-2 well. After recompletion of the well, Chemco approached CIG about purchasing the gas. CIG, however, determined that it would not be economical to install or operate the gathering facilities necessary to purchase this gas.

Around the same time, another company drilled a well near the Wear 3-2. CIG concluded that this well was also uneconomical to connect. However, CIG informed both companies that the two wells together might produce enough gas to make it economical for CIG to install and operate the necessary gathering facilities. CIG informed each company that it would consider purchasing its gas only if a suitable contract were signed with each of them. After negotiations, both Chemco and the other company entered into separate contracts with CIG. Chemco’s contract was effective April 27, 1979, for a term of 15 years. Problems with the other company’s well developed almost immediately.

In 1980, Chemco approached CIG about purchasing gas from several additional wells it intended to rework or recomplete. In September 1980, the parties amended their contract to add the gas from three wells. CIG then constructed new facilities necessary to connect these wells and wells from other sellers. None of these wells produced any significant volumes of natural gas. Another well, the Mundhenke, was never connected.

In late 1983, CIG began negotiating with Chemco regarding the purchase price and the excessive cost of gathering the gas from Chemco’s existing wells. In July 1984, CIG and Chemco agreed to amend the contract for two years, effective October 1983, and to amend it permanently thereafter. Testimony was presented that, by 1985, CIG’s gathering costs were much higher than anywhere else on its system and were in excess of the amount CIG was allowed to recover for gathering in its sales rate.

In 1985, when CIG was unable to renegotiate the terms of the contract, it exercised what it thought to be its right to cease purchasing the gas under section 4.5 of the contract and brought a declaratory judgment action seeking interpretation of that section. Section 4.5 of the contract provides:

Irrespective of any other provision of this Agreement, whenever the quantity of gas being delivered at any delivery point is or becomes so low that it is not economically feasible for the Seller to deliver or the Buyer to take such gas into Buyer’s facilities, either party may elect to discontinue delivering or taking such gas.

Chemco counterclaimed that CIG breached its obligation to take or pay for the gas specified in other provisions of the contract, and it also brought fraud and tor-tious breach of contract claims against CIG.

By agreement of the parties, trial was bifurcated. In phase I, in April 1988, the court ruled that CIG did not properly exercise section 4.5 of the contract and therefore breached it. Following the phase I trial, the court dismissed all of Chemco’s tort claims. In phase II, in March 1989, the jury awarded damages in favor of Chemco for CIG’s breach of the agreement.

I.

CIG now contends that the trial court erred in interpreting its contract with Chemco. We disagree.

Interpretation of a written contract and whether ambiguity exists in a contract is a question of law for the court. Pepcol Manufacturing Co. v. Denver Union Corp., 687 P.2d 1310 (Colo.1984). Therefore, the trial court’s determination regarding the question of ambiguity is not binding on this court. See Fibreglas Fabricators, Inc. v. Kylberg, 799 P.2d 371 (Colo. 1990).

To ascertain whether certain provisions of an agreement are ambiguous, *789 the language used must be examined and construed in harmony with the plain, popular, and generally accepted meaning of the words employed and with reference to all provisions of the document. Heller v. Fire Insurance Exchange, 800 P.2d 1006 (Colo.1990). In making this determination a court may consider extrinsic evidence bearing upon the meaning of the written terms, such as evidence of local usage and the circumstances surrounding the making of the contract. KN Energy, Inc. v. Great Western Sugar Co., 698 P.2d 769 (Colo.1985).

Once the contract is determined to be ambiguous, it must be construed in accordance with the intent of the parties, and relevant evidence may be considered to resolve factual questions of the parties’ intent. Chambliss/Jenkins Associates v. Forster, 650 P.2d 1315 (Colo.App.1982); see Fibreglas Fabricators, Inc. v. Kylberg, supra.

The intent and purpose of parties with respect to the contract may be gleaned from the parties’ conduct, their oral statements and writings, and other evidence illuminating circumstances surrounding making of the contract. I.M.A., Inc. v. Rocky Mountain Airways, Inc., 713 P.2d 882 (Colo.1986).

However, if the terms of a contract are ambiguous, they must be strictly construed against the party drafting the contract. Green Shoe Manufacturing Co. v. Farber, 712 P.2d 1014 (Colo.1986).

Once a contract is determined to be ambiguous, the meaning of its terms is generally an issue of fact to be determined in the same manner as other disputed factual issues. Union Rural Electric Ass’n v. Public Utilities Commission, 661 P.2d 247 (Colo.1983). And, findings of fact made by the trial court are binding on appeal if supported by evidence in the record. Zuments v. Colorado High School Activities Ass’n, 737 P.2d 1113 (Colo.App.1987).

Evidence presented at the phase I trial indicated that the volume of gas produced from the wells from the times they were added to the contracts to 1985, although declining, remained relatively unchanged. However, CIG argued that the quantity was so low that gathering costs made continuation of the contract no longer economically feasible.

The trial court found, and we agree, that section 4.5 was ambiguous on its face.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Denver Homeless Out Loud v. Denver, Colorado
32 F.4th 1259 (Tenth Circuit, 2022)
Leanin' Tree, Inc. v. Thiele Technologies, Inc.
43 F. App'x 318 (Tenth Circuit, 2002)
Electrical Distributors, Inc. v. SFR, Inc.
166 F.3d 1074 (Tenth Circuit, 1999)
Colorado Interstate Gas Co. v. Chemco, Inc.
987 P.2d 829 (Colorado Court of Appeals, 1998)
Decker v. Browning-Ferris Industries of Colorado, Inc.
931 P.2d 436 (Supreme Court of Colorado, 1997)
Decker v. Browning-Ferris Industries of Colorado, Inc.
903 P.2d 1150 (Colorado Court of Appeals, 1995)
Mullaney v. Albertson's, Inc. (In Re Mullaney)
179 B.R. 942 (D. Colorado, 1995)
Klein v. Grynberg
44 F.3d 1497 (Tenth Circuit, 1995)
Kincaid v. Western Operating Co.
890 P.2d 249 (Colorado Court of Appeals, 1994)
Mike Naughton Ford, Inc. v. Ford Motor Co.
862 F. Supp. 264 (D. Colorado, 1994)
Donohue v. Unipac Service Corp.
847 F. Supp. 1530 (D. Colorado, 1994)
Wells Fargo Realty Advisors Funding, Inc. v. Uioli, Inc.
872 P.2d 1359 (Colorado Court of Appeals, 1994)
Amoco Rocmount Co. v. Anschutz Corp.
7 F.3d 909 (Tenth Circuit, 1993)
Colorado Interstate Gas Co. v. Chemco, Inc.
854 P.2d 1232 (Supreme Court of Colorado, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
833 P.2d 786, 1991 WL 272697, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colorado-interstate-gas-co-v-chemco-inc-coloctapp-1992.