BALDOCK, Circuit Judge.
Appellee and seller, Kaiser-Francis Oil Co. (Kaiser-Francis), sought to enforce the provisions of two similar gas purchase contracts (the “Ellis” and “Cronin” contracts) against appellant and buyer, Producer’s Gas Co. (PGC). Under the contracts, PGC was required to take or pay for certain minimum quantities of gas from wells in which Kaiser-Francis had a percentage interest. When the resale price for natural gas declined, PGC did not pay Kaiser-Francis for gas taken on the theory that it was purchasing the gas from Kaiser-Francis’ co-owners at reduced prices. PGC also declined to pay for the minimum contract
quantities of the gas which were not taken. PGC’s actions were based on various defenses to the contracts. The district court granted summary judgment on the issue of liability in favor of Kaiser-Francis, thereby rejecting all of PGC’s defenses. The parties thereafter stipulated as to the appropriate damages, interest and attorney’s fees that would accrue upon the liability determination. Thus, we consider only issues of liability under the contracts, whether the district court improperly rejected any or all of PGC’s defenses to the contract.
On appeal, PGC contends that the district court erred in granting partial summary judgment in favor of Kaiser-Francis because 1) the force majeure provision in the contracts extends to a partial lack of demand caused by market forces, 2) the gas to be supplied by Kaiser-Francis failed to meet the quality specifications of the contract, 3) PGC was not purchasing gas from Kaiser-Francis, but rather from Kaiser-Francis’ co-owners in various wells, and 4) any take-or-pay payments required under the contract would violate ceiling prices set by the Natural Gas Policy Act [NGPA]. We find each of these contentions without merit and affirm. Our jurisdiction to review this diversity case arises under 28 U.S.C. § 1291. Consistent with the choice of law provision in each contract, we apply Oklahoma substantive law.
Summary judgment is appropriate when the materials submitted to the court “show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). What facts are material depends on the substantive law being applied.
Anderson v. Liberty Lobby, Inc., 477
U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Although we view the evidence in the light most favorable to the party opposing summary judgment,
Adickes v. S.H. Kress & Co.,
398 U.S. 144, 157, 90 S.Ct. 1598, 1608, 26 L.Ed.2d 142 (1970), disputes about immaterial facts will not preclude summary judgment.
Anderson,
477 U.S. at 247-48, 106 S.Ct. at 2509-10. Should a non-moving party make some showing on a material issue, we must consider the standard of proof in the case (here, a preponderance of evidence) and decide whether the showing is sufficient for a reasonable trier of fact to find for the non-moving party on that issue.
Id.
at 253, 106 S.Ct. at 2512-13. A scintilla of evidence in favor of the non-moving party is not enough to preclude summary judgment.
Id.
Moreover, should a non-moving party not make a sufficient showing on any essential element of his case, all other facts are rendered immaterial, and summary judgment is appropriate.
Celotex Corp. v. Catrett,
477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986). Based on our
de novo
review of the grant of partial summary judgment, we are convinced “that the issues before us may be resolved as a matter of law.”
Missouri Pac. R.R. Co. v. Kansas Gas & Elec. Co.,
862 F.2d 796, 799 (10th Cir.1988). Accordingly, summary judgment was proper.
I.
PGC first contends that the force majeure provision
in each contract ex
tends to a lack of demand for gas, thereby providing relief in this case from the take- or-pay obligation
contained in each contract. PGC suggests that there is an issue of fact concerning the extent of the failure of demand for gas. Essentially, PGC contends that a force majeure event occurred because the demand for gas sharply decreased, with a corresponding decrease in the resale price of gas that PGC was obligated to take or pay for under the contracts. Unfortunately for PGC, however, the Oklahoma Supreme Court, in interpreting a similar force majeure provision, has determined that neither a decline in demand, nor an inability to sell gas at or above the contract price, constitutes a force majeure event.
Golsen v. Ong Western, Inc.,
756 P.2d 1209, 1213 (Okla.1988) (interpreting force majeure provision extending to “failure of gas supply or markets”). That decision applies to this case.
PGC’s interpretation of the force maj-eure provision is antithetical to the take-or-pay provision. Under its interpretation, PGC could be expected to take only when the demand for gas resulted in a resale price at or above the contract price. PGC could never be expected to take or pay when the demand for gas resulted in a resale price below the contract price. Rather than taking or paying under the take-or-pay provision, PGC would rely on the force majeure provision. Thus, Kaiser-Francis would be shut in during any drop in demand, for up to twenty years, without any ability to sell in other markets. Such a one-sided interpretation is suspect.
The purpose of the take-or-pay clause is to apportion the risks of natural gas production and sales between the buyer and seller. The seller bears the risk of production. To compensate the seller for that risk, the buyer agrees to take, or pay for if not taken, a minimum quantity of gas. The buyer bears the risk of market demand.
Universal Resources Corp. v. Panhandle E. Pipe Line Co.,
813 F.2d 77, 80 (5th Cir.1987);
see also Golsen,
756 P.2d at 1213; 4 H. Williams
&
C. Meyers,
Oil & Gas Law
§ 724.5 (1988) (take-or-pay provision assures the seller “of a minimum annual return and that his premises will be permitted to produce in paying quantities”). Should the resale price decline below the contract price, PGC could still take the gas and sell it, albeit at a loss, or pay for the gas without taking it, also at a loss. The change in the general or relative resale price of gas does not constitute a “partial failure of gas demand” which would relieve PGC of its obligation to take or pay.
Free access — add to your briefcase to read the full text and ask questions with AI
BALDOCK, Circuit Judge.
Appellee and seller, Kaiser-Francis Oil Co. (Kaiser-Francis), sought to enforce the provisions of two similar gas purchase contracts (the “Ellis” and “Cronin” contracts) against appellant and buyer, Producer’s Gas Co. (PGC). Under the contracts, PGC was required to take or pay for certain minimum quantities of gas from wells in which Kaiser-Francis had a percentage interest. When the resale price for natural gas declined, PGC did not pay Kaiser-Francis for gas taken on the theory that it was purchasing the gas from Kaiser-Francis’ co-owners at reduced prices. PGC also declined to pay for the minimum contract
quantities of the gas which were not taken. PGC’s actions were based on various defenses to the contracts. The district court granted summary judgment on the issue of liability in favor of Kaiser-Francis, thereby rejecting all of PGC’s defenses. The parties thereafter stipulated as to the appropriate damages, interest and attorney’s fees that would accrue upon the liability determination. Thus, we consider only issues of liability under the contracts, whether the district court improperly rejected any or all of PGC’s defenses to the contract.
On appeal, PGC contends that the district court erred in granting partial summary judgment in favor of Kaiser-Francis because 1) the force majeure provision in the contracts extends to a partial lack of demand caused by market forces, 2) the gas to be supplied by Kaiser-Francis failed to meet the quality specifications of the contract, 3) PGC was not purchasing gas from Kaiser-Francis, but rather from Kaiser-Francis’ co-owners in various wells, and 4) any take-or-pay payments required under the contract would violate ceiling prices set by the Natural Gas Policy Act [NGPA]. We find each of these contentions without merit and affirm. Our jurisdiction to review this diversity case arises under 28 U.S.C. § 1291. Consistent with the choice of law provision in each contract, we apply Oklahoma substantive law.
Summary judgment is appropriate when the materials submitted to the court “show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). What facts are material depends on the substantive law being applied.
Anderson v. Liberty Lobby, Inc., 477
U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Although we view the evidence in the light most favorable to the party opposing summary judgment,
Adickes v. S.H. Kress & Co.,
398 U.S. 144, 157, 90 S.Ct. 1598, 1608, 26 L.Ed.2d 142 (1970), disputes about immaterial facts will not preclude summary judgment.
Anderson,
477 U.S. at 247-48, 106 S.Ct. at 2509-10. Should a non-moving party make some showing on a material issue, we must consider the standard of proof in the case (here, a preponderance of evidence) and decide whether the showing is sufficient for a reasonable trier of fact to find for the non-moving party on that issue.
Id.
at 253, 106 S.Ct. at 2512-13. A scintilla of evidence in favor of the non-moving party is not enough to preclude summary judgment.
Id.
Moreover, should a non-moving party not make a sufficient showing on any essential element of his case, all other facts are rendered immaterial, and summary judgment is appropriate.
Celotex Corp. v. Catrett,
477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986). Based on our
de novo
review of the grant of partial summary judgment, we are convinced “that the issues before us may be resolved as a matter of law.”
Missouri Pac. R.R. Co. v. Kansas Gas & Elec. Co.,
862 F.2d 796, 799 (10th Cir.1988). Accordingly, summary judgment was proper.
I.
PGC first contends that the force majeure provision
in each contract ex
tends to a lack of demand for gas, thereby providing relief in this case from the take- or-pay obligation
contained in each contract. PGC suggests that there is an issue of fact concerning the extent of the failure of demand for gas. Essentially, PGC contends that a force majeure event occurred because the demand for gas sharply decreased, with a corresponding decrease in the resale price of gas that PGC was obligated to take or pay for under the contracts. Unfortunately for PGC, however, the Oklahoma Supreme Court, in interpreting a similar force majeure provision, has determined that neither a decline in demand, nor an inability to sell gas at or above the contract price, constitutes a force majeure event.
Golsen v. Ong Western, Inc.,
756 P.2d 1209, 1213 (Okla.1988) (interpreting force majeure provision extending to “failure of gas supply or markets”). That decision applies to this case.
PGC’s interpretation of the force maj-eure provision is antithetical to the take-or-pay provision. Under its interpretation, PGC could be expected to take only when the demand for gas resulted in a resale price at or above the contract price. PGC could never be expected to take or pay when the demand for gas resulted in a resale price below the contract price. Rather than taking or paying under the take-or-pay provision, PGC would rely on the force majeure provision. Thus, Kaiser-Francis would be shut in during any drop in demand, for up to twenty years, without any ability to sell in other markets. Such a one-sided interpretation is suspect.
The purpose of the take-or-pay clause is to apportion the risks of natural gas production and sales between the buyer and seller. The seller bears the risk of production. To compensate the seller for that risk, the buyer agrees to take, or pay for if not taken, a minimum quantity of gas. The buyer bears the risk of market demand.
Universal Resources Corp. v. Panhandle E. Pipe Line Co.,
813 F.2d 77, 80 (5th Cir.1987);
see also Golsen,
756 P.2d at 1213; 4 H. Williams
&
C. Meyers,
Oil & Gas Law
§ 724.5 (1988) (take-or-pay provision assures the seller “of a minimum annual return and that his premises will be permitted to produce in paying quantities”). Should the resale price decline below the contract price, PGC could still take the gas and sell it, albeit at a loss, or pay for the gas without taking it, also at a loss. The change in the general or relative resale price of gas does not constitute a “partial failure of gas demand” which would relieve PGC of its obligation to take or pay. The force majeure provision cannot substitute for a price redetermination or market-out provision which would allow PGC to reduce the price paid to Kaiser-Francis for gas, thereby ameliorating PGC’s take-or-pay obligation when the resale price of natural gas declined.
II.
PGC next contends that it was excused from its take-or-pay obligation because the gas did not meet the quality specification provision concerning allowable water vapor in the gas.
Like gas not taken by reason
of force majeure, ¶ 4.7 of the contracts allows PGC a credit against its take-or-pay obligation for “quantities of gas not taken for failure of the gas to meet the quality specifications” contained in each contract.
See
rec. vol. II, contracts at 114.7 (Attachment to Brief in Support of Kaiser-Francis Oil Company’s Motion for Partial Summary Judgment — 1980 Ellis & 1982 Cronin Contracts). PGC established a factual issue concerning whether the gas met the quality specification,
see
rec. vol. I, doc. 40 (Thompson affidavit), however, Kaiser-Francis conceded the point for purposes of summary judgment.
Still, the district court granted summary judgment on this issue in favor of Kaiser-Francis because of the lack of adequate assurances by PGC that PGC would perform under the contract, even if remedial measures were undertaken by Kaiser-Francis to cure the water vapor problem.
The contract allowed Kaiser-Francis the right to cure.
The district court decision on this issue follows from certain uncontro-verted facts. When Kaiser-Francis notified PGC of its 1982 take-or-pay liability under the Ellis contract, PGC denied liability on the basis of the force majeure and quality specification provisions discussed above. PGC then proposed a contract amendment which would have modified the take-or-pay arrangement with a system of “flexible pricing of natural gas at the wellhead to respond to constantly changing market conditions.” Rec. vol. II (Attachment to Brief in Support of Kaiser-Francis Oil Company’s Motion for Partial Summary Judgment — Letter from PGC to Kaiser dated March 30,1983, at 2). The amendment
would have given PGC, among other things, unilateral control over price. PGC sent its letter and contract amendment to every producer with which it had a gas purchase contract in Oklahoma.
Id.
PGC made it clear that it intended “to take ratably on each system from all producers agreeing to this contract amendment” and that it would only take under the terms and conditions it proposed.
Id.
at 2, 4.
Kaiser-Francis rejected the amendment and demanded that PGC pay for that proportion of gas already taken and attributable to Kaiser-Francis. Rec. vol. II (Attachment to Brief in Support of Kaiser-Francis Oil Company’s Motion for Partial Summary Judgment-Letter from Kaiser-Francis to PGC dated June 15, 1988). Kaiser-Francis also sought assurance that PGC intended to perform its take-or-pay obligation.
Id.;
Okla.Stat.Ann. tit. 12A, § 2-609(1) (West 1981) (right to assurance of performance under U.C.C.). PGC responded by reiterating that the failure of market demand was a force majeure condition and that it intended to fulfill the obligations of the contract. PGC, however, made it abundantly
clear that it would not take-or-pay for any gas of Kaiser-Francis until Kaiser-Francis acceded to PGC’s demands to renegotiate the contracts.
PGC contends that whether Kaiser-Francis was entitled to suspend performance under § 2-609
of the Oklahoma U.C.C. is a factual issue which should not be resolved by summary judgment. Specifically, PGC argues that whether Kaiser-Francis had reasonable grounds for insecurity and whether assurances made by PGC were adequate are inherently factual issues. If Kaiser-Francis had reasonable grounds for insecurity and the assurances offered by PGC were inadequate, Kaiser-Francis was entitled to suspend performance of the contract, including its right to cure the water vapor problem. Okla.Stat. Ann. tit. 12A, § 2-609(1).
We agree with PGC that normally whether a party has reasonable grounds for insecurity and the adequacy of any assurance offered are factual questions resolved with reference to commercial standards.
See
Okla.Stat.Ann. tit. 12A § 2-609(2) & comments 3 & 4 (West 1981). We also recognize, however, that to pre-elude summary judgment on this issue, the evidence relied upon by PGC would have to be such that a rational trier of fact might conclude that Kaiser-Francis did not have reasonable grounds for insecurity and that PGC gave adequate assurance to Kaiser-Francis.
See Anderson,
477 U.S. at 254, 106 S.Ct. at 2513. A rational trier of fact could not make such a conclusion.
PGC stopped performing on these take-or-pay contracts. The clear import of the documentary evidence on this point, much of it drafted by PGC, is that PGC had no intention of performing the contract unless Kaiser-Francis agreed to modify the take-or-pay provision. Kaiser-Francis was under no duty to agree. To be sure, PGC has provided an affidavit from one of its employees explaining its benign purpose in offering the amendments and further explaining that PGC never conditioned its performance upon Kaiser-Francis accepting those amendments. Rec. vol. I, doc. 40 (Keathley affidavit). However, this information, even when viewed in the light most favorable to PGC, is insufficient to preclude summary judgment on the insecurity issue for at least two reasons. First, it is
based on PGC’s erroneous interpretation of what constituted proper performance under the contract. The information does not address honoring the contracts as we interpret them. Second, PGC’s refusal to pay for gas taken and for certain quantities not taken, while repeatedly trying to amend the contracts, could not fail to create reasonable grounds for insecurity.
Likewise, PGC did not provide adequate assurance that it would perform if Kaiser-Francis reduced the water vapor in the gas. To the contrary, PGC indicated it would perform only if the contract was amended. PGC’s interpretation of the take-or-pay provision in the contract was erroneous and assured Kaiser-Francis that PGC would
not
perform absent contract modification. Indeed, PGC did not perform. The evidence is so one-sided on these points that no rational trier of fact could have found otherwise, even crediting PGC’s evidence.
See id.
at 252, 255, 106 S.Ct. at 2512, 2513-14. Kaiser-Francis had reasonable grounds for insecurity, and the purported assurance offered by PGC was inadequate. Thus, summary judgment against PGC on the water vapor defense was proper.
III.
PGC next argues that the district court erred in finding PGC was obligated to pay Kaiser-Francis for gas purchased from co-owners. Kaiser-Francis maintains that it is entitled to payment, at the contract price, for gas taken from wells covered by the contract. The amount of payment should be based on the percentage ownership in the wells held by Kaiser-Francis. The district court agreed with Kaiser-Francis. So do we.
To the extent that PGC’s argument depends upon the premise that PGC had a contractual right to suspend performance, we have rejected that premise above. To accept PGC’s other argument, that it is purchasing gas only from other co-owners in the well, and not Kaiser-Francis, is contrary to the intent of the contracts as would be commonly understood by both parties. Paragraph 11.1 of the contracts is clear that Kaiser-Francis is entitled to payment within a specific time for gas delivered to PGC by Kaiser-Francis. Exhibit A to each contract indicated that Kaiser-Francis owned a percentage interest in each well, not one hundred percent. PGC cannot ignore its contractual obligations to Kaiser-Francis under the guise of purchasing gas only from other co-owners of the well who have agreed to PGC’s reduced, negotiated price.
PGC refers us to the common law and the operating agreements between co-owners of the jointly owned wells, and argues that the co-owners of the wells had the right to sell one hundred percent of the gas to PGC (no doubt at the reduced, negotiated price), if Kaiser-Francis was unable to market its proportionate share of the gas. PGC then suggests that Kaiser-Francis must look to future production from the reservoir or rely on traditional gas balancing remedies for payment. The district court attributed any imbalance in this situation to PGC’s breach of contract and also rejected the balancing solutions offered by PGC. Rec. vol. I, doc. 59 at 6-8.
Cash balancing, which results in the overproduced party (here, a co-owner) compensating the underproduced party (here, Kaiser-Francis) in cash, is done at the price the overproduced party received for the gas. Thus, to the extent a co-owner sold PGC the gas for a price less than the price contained in the PGC/Kaiser-Francis contract, Kaiser-Francis would receive the lower price, not the contract price it bargained for. If the cash balancing were done upon reservoir depletion, rather than on a periodic basis, Kaiser-Francis would incur the additional risk that an overproduced party might be unable to meet his cash balancing obligations at some indefinite date in the future. If the cash balancing were done on a periodic basis, Kaiser-Francis would still not receive its contract price at delivery for the gas.
Balancing in kind, when the underpro-duced party takes a certain increased percentage of the overproduced party’s gas until the imbalance is eliminated, requires that a reservoir not be depleted.
See Beren v. Harper Oil Co.,
546 P.2d 1356, 1359
(Okla.App.1975)
(discussing balancing in-kind). Practically, it offers no solution here because PGC will not purchase gas from Kaiser-Francis if it can purchase the same gas from the co-owners of the well who have accepted a reduced price. We agree with the district court that PGC “is currently depleting the wells under the theory that it is only depleting the gas reserves of other joint interest owners.” Rec. vol. I, doc. 59 at 8.
PGC disclaims any responsibility for the imbalance created under its theory and suggests that the working interest owners should be left to resolve any situation where balancing is necessary.
See HBOP, Ltd. v. Delhi Gas Pipeline Corp.,
645 P.2d 1042, 1045-46 n. 3 (Okla.App.1982).
The cases relied upon by PGC concern split-stream connections, where different purchasers buy from the same well. Although some of the wells here are split-stream connections, that is not the problem. PGC is creating an ostensible imbalance by not paying Kaiser-Francis for gas taken. On the underpayment claim, Kaiser-Francis merely seeks payment for gas taken in accordance with the contract. We reject PGC’s attempt to recast this dispute as one between the joint owners of the wells, instead of one between PGC and one of those owners, Kaiser-Francis. Given its contracts with PGC, Kaiser-Francis need not resort to balancing which would alter 1) the price paid, 2) the time payment is made, and 3) the likelihood that payment would ever be made.
IV.
Finally, PGC challenges the district court’s decision that take-or-pay payments are not for gas already taken, and therefore that such payments do not result in prices for natural gas which exceed NGPA ceilings.
See
15 U.S.C. § 3314(b)(1). The Federal Energy Regulatory Commission (FERC) recently rejected the same position advanced by PGC and stated:
In the context of the gas purchase contract and industry practice, the. take-or-pay payment is not intended to be a payment for gas and is not a part of the price of gas until it is applied at the time of sale. The value to the producer of take-or-pay payments forfeited by the purchaser is therefore not treated as part of the price of gas purchased currently.
ANR Pipeline Co. v. Wagner & Brown,
44 FERC ¶ 61,057 at 61, 158 (1988).
See also Diamond Shamrock Explor. Co. v. Hodel,
853 F.2d 1159, 1167-68 (5th Cir.1988) (take- or-pay payments are not payments for the sale of gas). The district court correctly decided this issue.
AFFIRMED.