Hemlock Semiconductor Corp. v. Kyocera Corp.

Court of Appeals for the Sixth Circuit·Decided August 16, 2018·No. 17-2276·Unpublished

Opinion

NOT RECOMMENDED FOR FULL-TEXT PUBLICATION File Name: 18a0413n.06

Case No. 17-2276

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT

FILED

Aug 16, 2018

DEBORAH S. HUNT, Clerk

HEMLOCK SEMICONDUCTOR ) CORPORATION; HEMLOCK ) SEMICONDUCTOR, LLC, )

) ON APPEAL FROM THE UNITED Plaintiffs-Appellees, ) STATES DISTRICT COURT FOR ) THE EASTERN DISTRICT OF v. ) MICHIGAN )

KYOCERA CORPORATION, )

)

Defendant-Appellant. )

BEFORE: COLE, Chief Judge; CLAY and THAPAR, Circuit Judges.

THAPAR, Circuit Judge. Kyocera Corporation is locked in a long-running bout with Hemlock Semiconductor Corporation and Hemlock Semiconductor, LLC, which supply Kyocera with polysilicon that it uses to make solar panels. Kyocera is fighting to get out of certain obligations under the parties’ contracts. Below, the district court declared victory for Hemlock. But at this stage, Hemlock has earned only a partial victory. We therefore reverse in part and affirm in part.

I.

In the mid-2000s, the market for solar panels was taking off. Kyocera needed a steady supply of quality polysilicon. So it entered into four contracts with Hemlock, in which Kyocera

Hemlock Semiconductor Corp. v. Kyocera Corp. promised to purchase specified amounts of polysilicon from Hemlock at specified prices over the course of the next ten years or so.

Those contracts contain so-called “take-or-pay” provisions. Under these provisions, the contracts require Kyocera to “take” a specified quantity of polysilicon from Hemlock each year. But if Kyocera does not want to take the polysilicon in a given year, Kyocera still has to “pay” full price for it. This means that Kyocera is on the hook for a certain quantity of polysilicon annually, whether it takes the polysilicon or not.

The contracts also contain so-called “acceleration” provisions. If Kyocera defaults under the contracts, these provisions accelerate the amount it owes Hemlock, such that Hemlock can demand all remaining sums owed. For these acceleration provisions to take effect, Kyocera must default, Hemlock must serve notice of default, and Hemlock must give Kyocera 180 days to cure its default. But if Kyocera does not cure, Hemlock can elect to terminate, at which point Kyocera becomes liable for all remaining payments due—effectively, the sum of the take-or-pay provisions.

Several years into Kyocera and Hemlock’s deal, the Chinese government disrupted the solar-panel market by subsidizing Chinese solar-panel companies. This intervention reduced the market price of polysilicon such that the price Kyocera agreed to pay Hemlock was far greater than the going rate. And so Kyocera sought to renegotiate. Initially, the parties came to a compromise, temporarily lowering the price of polysilicon under the parties’ deal. But eventually, Hemlock signaled that it would begin insisting that Kyocera take or pay for polysilicon at the original (and now inflated) price.

This litigation ensued. Hemlock sought a declaratory judgment that Kyocera had repudiated the parties’ contracts by indicating that it would not take or pay at the original price. In response, Kyocera counterclaimed, seeking a declaratory judgment that the “pay” portion of the

Hemlock Semiconductor Corp. v. Kyocera Corp. take-or-pay provisions is an unlawful penalty, and thus that the acceleration provisions are too. Kyocera also counterclaimed for breach of contract, alleging that three of the parties’ contracts obligated Hemlock to expand certain production facilities, which Hemlock had not done. Hemlock moved to dismiss Kyocera’s counterclaims, and the district court agreed. Kyocera now appeals.

II.

Kyocera first appeals the dismissal of its challenge to the take-or-pay provisions. We review the district court’s decision de novo. JPMorgan Chase Bank, N.A. v. Winget, 510 F.3d 577, 581 (6th Cir. 2007). In doing so, we accept Kyocera’s well-pled allegations as true and ask whether Hemlock is nevertheless “clearly entitled to judgment.” Id. (quoting S. Ohio Bank v. Merrill Lynch, Pierce, Fenner & Smith, Inc., 479 F.2d 478, 480 (6th Cir. 1973)). We view the facts as alleged in the light most favorable to Kyocera and draw all reasonable inferences in its favor. See Gavitt v. Born, 835 F.3d 623, 640 (6th Cir. 2016). Our task is to determine whether Kyocera raises a plausible claim for relief. See Bell Atl. Corp. v. Twombly, 550 U.S. 544, 557 (2007). And Kyocera’s claim is plausible if, assuming the truth of Kyocera’s allegations, a reasonable factfinder could rule in its favor. Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009).

In assessing Kyocera’s claim, we apply Michigan law—the law of the forum state and that designated in the parties’ contracts. Erie R. Co. v. Tompkins, 304 U.S. 64, 78 (1938); see Kipin Indus., Inc. v. Van Deilen Int’l, Inc., 182 F.3d 490, 493 (6th Cir. 1999). As it happens, Michigan’s courts provide little guidance here. The thrust of Kyocera’s claim is that the take-or-pay provisions are unlawful penalties in disguise. But there is no case in which a Michigan court has considered such a claim. The closest we have is a Michigan Court of Appeals decision resolving an earlier chapter of the parties’ dispute in which Kyocera attempted to invoke a force majeure clause in the contracts. In dicta, the court referenced the take-or-pay provisions, but only to note their existence

Hemlock Semiconductor Corp. v. Kyocera Corp. and operation as a means of refuting Kyocera’s force-majeure argument. Kyocera Corp. v. Hemlock Semiconductor, LLC, 886 N.W.2d 445, 447–48, 453 (Mich. Ct. App. 2015). Hemlock makes much of this discussion, reading it to suggest that Michigan always enforces take-or-pay provisions and would do so here. But because Kyocera did not challenge the validity of the take- or-pay provisions in those proceedings,1 we cannot read the Michigan court’s discussion as setting out a general rule that it will always enforce take-or-pay provisions or even that it would do so in this case. And neither of the other cases Hemlock identifies goes so far. See McLouth Steel Corp. v. Jewell Coal & Coke Co., 570 F.2d 594, 605 (6th Cir. 1978); Attorney Gen. v. Pub. Serv. Comm’n No. 1, 431 N.W.2d 47, 49 (Mich. Ct. App. 1988).

With no Michigan authority on point, we must look elsewhere to attempt to discern what path the Michigan Supreme Court might take. Combs v. Int’l Ins. Co., 354 F.3d 568, 577 (6th Cir. 2004) (explaining that “when evaluating an undecided question of [state] law, a federal court sitting in diversity must make the [sic] ‘the best prediction, even in the absence of direct state precedent, of what the [state] Supreme Court would do if confronted with [the] question,’” including considering “jurisprudence from other jurisdictions” (last alteration in original) (first quoting Managed Health Care Assocs., Inc. v. Kethan, 209 F.3d 923, 927 (6th Cir. 2000); then quoting Lexington Ins. Co. v. Rugg & Knopp, Inc., 165 F.3d 1087, 1090 (7th Cir. 1999))). Under the approach followed in other jurisdictions, the key question is whether the take-or-pay provisions offer Kyocera two viable performance options, on the one hand, or one performance option coupled with a liquidated damages provision, on the other. See, e.g., Superfos Invs. Ltd. v. FirstMiss Fertilizer, Inc., 821 F. Supp. 432, 434–35 (S.D. Miss. 1993) (collecting cases); Minnick

1 Hemlock makes no argument that Kyocera is precluded from raising this challenge here, despite not doing so previously.

Free access — add to your briefcase to read the full text and ask questions with AI

Hemlock Semiconductor Corp. v. Kyocera Corp., (6th Cir. 2018).

Hemlock Semiconductor Corp. v. Kyocera Corp. (Hemlock Semiconductor Corp. v. Kyocera Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stuart Weitzman, LLC v. Microcomputer Resources, Inc.
542 F.3d 859 (Eleventh Circuit, 2008)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Maryland Casualty Co. v. Pacific Coal & Oil Co.
312 U.S. 270 (Supreme Court, 1941)
Bell v. Hood
327 U.S. 678 (Supreme Court, 1946)
Whitmore Ex Rel. Simmons v. Arkansas
495 U.S. 149 (Supreme Court, 1990)
Calderon v. Ashmus
523 U.S. 740 (Supreme Court, 1998)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
MedImmune, Inc. v. Genentech, Inc.
549 U.S. 118 (Supreme Court, 2007)
Greenlaw v. United States
554 U.S. 237 (Supreme Court, 2008)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Monsanto Co. v. Geertson Seed Farms
561 U.S. 139 (Supreme Court, 2010)
SUREFOOT LC v. Sure Foot Corp.
531 F.3d 1236 (Tenth Circuit, 2008)
Henderson v. Shinseki
131 S. Ct. 1197 (Supreme Court, 2011)
Severe Records, LLC v. Rich
658 F.3d 571 (Sixth Circuit, 2011)