North Carolina Utilities Commission v. Federal Energy Regulatory Commission, North Carolina Natural Gas Corporation, Intervenors

42 F.3d 659, 310 U.S. App. D.C. 13, 1994 U.S. App. LEXIS 36138
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 23, 1994
Docket93-1451, 93-1456, 93-1490, and 93-1567
StatusPublished
Cited by15 cases

This text of 42 F.3d 659 (North Carolina Utilities Commission v. Federal Energy Regulatory Commission, North Carolina Natural Gas Corporation, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Carolina Utilities Commission v. Federal Energy Regulatory Commission, North Carolina Natural Gas Corporation, Intervenors, 42 F.3d 659, 310 U.S. App. D.C. 13, 1994 U.S. App. LEXIS 36138 (D.C. Cir. 1994).

Opinion

Opinion for the Court filed by Circuit Judge SENTELLE.

SENTELLE, Circuit Judge:

This is a petition for review of a Federal Energy Regulatory Commission ruling on a request by Transcontinental Gas Pipeline (TGPL) for a rate increase under Section 4 of *661 the Natural Gas Act, 15 U.S.C. § 717c (1988). Petitioners (hereinafter NCUC), the regulatory agencies of North Carolina and New York, and PECO Energy Company, a utility providing gas and electric service in eastern Pennsylvania and northern Maryland, challenge an order of the Federal Energy Regulatory Commission allowing TGPL to earn an alleged return of 24% on its common equity. Specifically, petitioners challenge the Commission’s use of a hypothetical capital structure to reach its result. They also challenge the Commission’s decision to select a rate of return at the high end of the zone of reasonableness for a natural gas pipeline’s common equity. In a separate challenge, petitioner TGPL contends the Commission erred in employing a proxy group of pipeline parent companies to derive the hypothetical structure. Because we find FERC’s decision arbitrary and capricious on these issues, we reverse and remand.

I. BACKGROUND

The Federal Energy Regulatory Commission (FERC) establishes the rates of a regulated pipeline by determining the pipeline’s total revenue requirements. Such requirements are composed of the pipeline’s rate base, its operating costs, and a rate of return sufficient to ensure that pipeline investors are fairly compensated. The rate of return component is calculated based on the weighted average of the costs of the three elements comprising the capital structure: debt, preferred stock, and common equity. To arrive at the proper rate of return, the Commission first determines the appropriate capital structure for the pipeline. The Commission then sets a rate of return for each element of the capital structure. Since the returns attributable to the three components comprising the overall return differ markedly, the capital structure used by the regulated entity to finance its investment can greatly affect the overall return allowed.

The area of contention in this case is the return allowed on the common equity element. To formulate a return on this component, the Commission develops a zone of reasonableness based on the range of returns generally experienced in the industry. The Commission then adjusts the return of the particular pipeline at issue within the zone to reflect the specific investment risks of that pipeline as compared to similar investments.

The proceedings below were initiated on March 2, 1992, when TGPL, a natural gas pipeline subject to FERC’s rate regulation, filed new tariff sheets with the Commission pursuant to Section 4(e) of the Natural Gas Act, 15 U.S.C. § 717c(e). TGPL desired to increase its rates for natural gas service by $234 million. The largest single component of the rate increase was TGPL’s request for a higher rate of return on its investment, specifically an after tax return of 36.4% on its common equity.

Because the Commission had traditionally allowed returns on common equity in the 11%-15% range, TGPL’s request produced much protest from TGPL’s customers and affected state commissions. As a result, the Commission issued an order not only suspending the rate increase until September 1, 1992, but also establishing an expedited hearing to consider the appropriate rate of return on common equity. Transcontinental Gas Pipe Line Corp., 59 FERC ¶ 61,034 at 61,102 (1992).

On July 10, 1992, the administrative law judge (ALJ) issued an order rejecting TGPL’s proposal for a 36.4% rate of return on equity. The ALJ concluded the proposal relied on unacceptable methodologies and lacked adequate evidentiary support. Transcontinental Gas Pipe Line Corp., 60 FERC ¶ 63001 at 65,044 (1992). Specifically, the ALJ concluded TGPL had erred in basing its rate of return proposal on the capital structure of its parent, Transco Energy Company (TEC), rather than on TGPL’s own capital structure. 60 FERC at 65,028-34. The ALJ also rejected an alternative rate of return proposed by petitioner Public Service Commission of the State of New York because it was based on TEC’s capital structure and used an inappropriate comparison group to set the rate of return: local natural gas distribution companies. Id. at 65,047-48.

The ALJ ultimately adopted a rate of return proposal advanced by financial analyst George Shriver on behalf of the Commission *662 staff (hereinafter the Shriver analysis). Consistent with the ALJ’s determination that the pipeline’s capital structure should be used, the Shriver analysis was based on TGPL’s capital structure. Id. at 65,048. To determine the zone of reasonableness for TGPL’s rate of return, Shriver used a primary comparison group of seven publicly owned pipeline parent corporations obtaining over 50% of their revenues from their natural gas pipeline subsidiaries, as well as a secondary comparison group of twenty natural gas pipeline companies that do not have publicly traded stock. Applying a Discounted Cash Flow (DCF) analysis to the secondary comparison group, Shriver arrived at a zone of reasonableness for a rate of return on equity ranging from 9.49% to 13.96%. Shriver further concluded that because TGPL was among the riskiest investments in the industry, TGPL’s rate of return on equity should be set at 13.96%, the upper end of the zone of reasonableness. The ALJ found the Shriver analysis the best supported and methodologically soundest. Id. at 65,048-51.

TGPL and NCUC appealed the ALJ’s order to the Commission. On September 17, 1992, the Commission issued an order adopting the conclusions of the ALJ, except for certain aspects of the rate of return calculation. Transcontinental Gas Pipeline Corp., 60 FERC ¶ 61,246 at 61,820 (1992). The Commission reversed the ALJ’s decision to use TGPL’s actual capital structure. The Commission acknowledged under normal circumstances, its policy would be to impute TEC’s capital structure to TGPL because TEC is the financing source for TGPL’s operations, as TGPL raises none of its own capital directly. Id. at 61,823. However, the Commission found that TEC’s common equity ratio of 16.27% was atypically low. The Commission cryptically declared, as a result, that TEC would require an anomalously high rate of return in relation to rates of return approved for comparable pipelines. Id. Consequently, the Commission determined TGPL’s rate of return on common equity should be derived using a hypothetical capital structure. Id.

Because none of the witnesses in the evi-dentiary hearings testified in support of utilizing a hypothetical capital structure, the Commission relied on the comparison groups discussed in the Shriver analysis. The Commission found the primary comparison group of seven publicly owned companies with pipeline subsidiaries was the most appropriate comparison group to establish a hypothetical capital structure because these publicly traded companies, like TEC, derived more than 50% of their revenue from pipeline corporations. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
42 F.3d 659, 310 U.S. App. D.C. 13, 1994 U.S. App. LEXIS 36138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-carolina-utilities-commission-v-federal-energy-regulatory-cadc-1994.