Transcanada Pipelines Limited v. Federal Energy Regulatory Commission, Western Gas Marketing Limited, Intervenors

24 F.3d 305, 306 U.S. App. D.C. 299
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 25, 1994
Docket91-1380, 91-1381, 91-1618, 91-1619, 93-1107, 93-1151, 93-1153, 93-1155, 93-1158, 93-1245 and 93-1246
StatusPublished
Cited by18 cases

This text of 24 F.3d 305 (Transcanada Pipelines Limited v. Federal Energy Regulatory Commission, Western Gas Marketing Limited, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcanada Pipelines Limited v. Federal Energy Regulatory Commission, Western Gas Marketing Limited, Intervenors, 24 F.3d 305, 306 U.S. App. D.C. 299 (D.C. Cir. 1994).

Opinion

Opinion for the Court filed by Circuit Judge SENTELLE.

SENTELLE, Circuit Judge:

Great Lakes, a pipeline company, Trans-Canada, its principal customer, and other interested firms petition for review of several orders of the Federal Energy Regulatory Commission (the “Commission”): Great Lakes Gas Transmission L.P., 57 FERC ¶ 61,140, 61,512 (1991) (“Opinion 867"), reh’g denied, 62 FERC ¶ 61,101, 61,713 (1993) (“Opinion 367-A”); Great Lakes Gas Transmission L.P., 57 FERC ¶ 61,141, 61,534 (1991) (“Opinion 368”), reh’g denied, 62 FERC ¶ 61,102, 61,731 (1993) (“Opinion 368-A”). The orders required Great Lakes to recover the costs of two recent expansions through “incremental” rates rather than “rolled-in” rates. 1 Petitioners claim that the Commission arbitrarily departed from its own precedent, violated the nondiscrimination provisions of the Natural Gas Act, imposed unfair retroactive penalties, and used hearing procedures that contravened the Administrative Procedure Act.

We hold that the Commission employed a standard to judge the permissibility of rolled-in rates that neither accords with the Commission’s precedent nor is compelled by our decisions. As the Commission failed adequately to explain the adoption of the new test, we remand the orders for reconsideration. 2

I

Great Lakes operates an interstate pipeline that runs some 2,000 miles from the Canadian border in Wisconsin to the Canadian border in eastern Michigan. TransCana-da is an affiliate of Great Lakes and uses about 80% of the pipeline’s capacity. The present case arises from two rate filings under Section 4 of the Natural Gas Act, 15 U.S.C. § 717c (1988), in which Great Lakes sought to recover the cost of several expansion projects designed to increase the pipeline’s capacity.

Opinion 367

The filing at issue in Opinion 367 covered expansion projects built to service petitioners TransCanada and Northern Minnesota Utilities. The projects cost some $557 million, which more than doubled Great Lakes’ preexisting rate base from $393 million to $950 million. Great Lakes filed a rate increase request that proposed rates to be calculated by rolling in the expansion costs. The Commission set all the issues for an evidentiary hearing except the question of whether rolled-in rates should be allowed; on that question the Commission ordered “paper hearing” procedures. See Great Lakes Gas Transmission L.P., 55 FERC ¶ 61,336, 61,990 (1991).

After considering the submissions the Commission held that Great Lakes must “specifically address and justify rolled-in rates by showing that systemwide benefits to existing customers are commensurate with the increase in rates.” See Opinion 367, 57 *308 FERC ¶ 61,140 at 61,621. Finding that “the benefits [of the expansions] do not equal or exceed the costs,” id. at 61,522, the Commission accordingly ordered that the costs of the expansions be recouped through incremental pricing. Id. at 61,525-26. The petitioners’ requests for rehearing were subsequently denied. See Opinion 367-A, 62 FERC ¶ 61,101 at 61,716.

Opinion 368

In this proceeding the Commission considered Great Lakes’ request to recover rolled-in rates for two expansion projects built to serve petitioners TransCanada and Midland Cogeneration Venture, with a total cost of $190 million. The rate filing was heard by an Administrative Law Judge (“ALJ”) with the participation of Commission staff. The ALJ ruled that rolled-in rates were permissible under Commission precedent. See Great Lakes Gas Transmission L.P., 55 FERC ¶ 63,037, 65,209 (1991) (“Initial Decision”). On appeal the Commission reversed, holding that the rates should be priced incrementally under the same “commensurate benefits” test employed in Opinion 367, and confirmed its order on rehearing. See Opinion 368, 57 FERC ¶ 61,141 at 61,542; Opinion 368-A, 62 FERC ¶ 61,102 at 61,745.

II

A

Petitioners contend that the standard by which the Commission judged Great Lakes’ rate filing represents an unexplained departure from Commission precedent, and thus constitutes arbitrary decisionmaking under the Administrative Procedure Act. See 5 U.S.C. § 706(2)(A) (1988); Michigan Consol. Gas Co. v. FERC, 883 F.2d 117, 122 (D.C.Cir.), cert. denied, 494 U.S. 1079, 110 S.Ct. 1807, 108 L.Ed.2d 937 (1989). They assert that the Commission’s previous practice was to routinely grant roll-in requests when the pipeline could show that (1) the added facilities would be completely integrated into the mainline system and (2) the facilities would produce some systemwide benefits, qualitatively described. In these proceedings, however, the Commission suddenly adopted a “commensurate benefits” test without adequate explanation.

The Commission concedes that it weighed costs and benefits, but maintains that it has always done so. The only distinctive feature of the Great Lakes orders was that the Commission subjected the claimed benefits to a more rigorous scrutiny because the magnitude of the projects threatened a massive shift of costs onto existing customers. All concerned thus agree on the nature of the test the Commission applied in the present orders; the dispute stems rather from opposed descriptions of the Commission’s precedent.

Petitioners have the better of the argument. At least since Battle Creek Gas Co. v. FPC, 281 F.2d 42 (D.C.Cir.1960), the dominant theme of energy pricing policy has been to allow rolled-in rates whenever the expanding pipeline could show that the new facilities would be integrated into the mainline system and would confer some positive benefit on all the customers of the system. In Battle Creek the court undertook a general description of the Federal Power Commission’s policy which, although not binding on the FERC, captures the historical understanding. See id. at 46-47. In particular, the court conceived the “difficult issue of fact” in this type of proceeding to be whether a particular facility counts as “integrated” or “segregated,” id. at 47, not (as the Commission now claims) whether admittedly integrated facilities provide adequate benefits to existing customers.

Until quite recently the approach detailed in Battle Creek has prevailed without serious challenge. A particularly clean example of the Commission’s normal practice appears in Great Lakes Gas Transmission Co., 45 FERC ¶ 61,237, 61,695 (1988). There the Commission reversed an ALJ’s decision to incrementally price new facilities. Insofar as the Commission claims that it has always balanced the costs and benefits of new facilities, the discussion in that case refutes it:

The Commission reverses the ALJ’s decision and concludes that the rates ... should be computed on a rolled-in basis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
24 F.3d 305, 306 U.S. App. D.C. 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcanada-pipelines-limited-v-federal-energy-regulatory-commission-cadc-1994.